Doubtnut Promotions Sticky

A can do a piece of work in 15 days and B is 25% more efficient than A. If A and B both work for 4 days and after 4 days C can complete the remaining work alone in 8 days, then find time taken by A, B and C together to complete the whole work.

A

6 days

B

5 days

C

8 days

D

10 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:B

|
Answer

Step by step video, text & image solution for A can do a piece of work in 15 days and B is 25% more efficient than A. If A and B both work for 4 days and after 4 days C can complete the remaining work alone in 8 days, then find time taken by A, B and C together to complete the whole work. by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Similar Practice Problems

  • Question 1 - Select One

    A can do a piece of work in 24 days. If B is 60% more efficient than A, then how many days does B require to do the same work?

    A17 days
    B18 days
    C15 days
    D12 days
  • Question 1 - Select One

    A can complete a work in 12 days and B can complete the same work in 24 days. Find the time taken by both A and B together to complete the work.

    A8 days
    B10 days
    C6 days
    D9 days
  • Question 1 - Select One

    A can do a picec of work in 10 days and B is 25% more
    efficient than A. In what time will the work be finished if A
    and B work together ?

    A449 days
    B557 days
    C5 days
    D623 days
  • Question 1 - Select One

    A can do a piece of work in 6 days. B is 25% more efficient than A. How long would B alone take to finish this work?

    A446 days
    B313 days
    C514 days
    D223 days
  • Question 1 - Select One

    A can do a work in 15 days. B is 25% more effcient than a In how many days working together A and B is complete the same work ?

    A214
    B257
    C245
    D203
  • Question 1 - Select One

    A and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?

    A60 days
    B36 days
    C45 days
    D24 days
  • Question 1 - Select One

    (A + B) can do a piece of work in 12 days. (B + C) can do same work in 623 days. A work for 3 days, B works for 4 days and C completed the remaining work in 7 days. In how many days will A, B and C do this work alone ?

    A18,15.,20
    B30,20,10
    C10,15,25
    D15,10,25
  • Question 1 - Select One

    A can do a piece of work in 12 days and B in 15 days. They work together for 5 days and then B left. The days taken by A to finish the remaining work is

    A3
    B5
    C10
    D121

Similar Questions