Each of A, B, C and D need a unique time to do a certain work. A can do the work in x days and B can do the work in 2x days. A started the work and do it for 2229days then he is replaced by B, who completed remaining work in same time as C and D together can complete the whole work. The ratio of the efficiency of C and D is 4 : 5. If C and D work for alternative days starting from C then they can do the total work in 4412days.
What is the value of x?

A

6623

B

3313

C

1623

D

1427

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, let's break down the information given and derive the value of x.

Step 1: Determine the total work done by C and D
C and D work in the ratio of 4:5. If we let C's efficiency be 4k and D's efficiency be 5k, the total efficiency of C and D together is 4k+5k=9k.

Given that C and D can complete the work in 4412 days (which is 44.5 days), we can calculate the total work:

Total Work=Efficiency×Time=9k×44.5

Calculating 9×44.5:

9×44.5=400.5k

Thus, the total work W=400.5k.

Step 2: Calculate the work done by A
A can complete the work in x days, so A's efficiency is Wx.

A works for 2229 days (which is 2009 days). The work done by A is:

Work done by A=Efficiency×Time=Wx×2009

Substituting W=400.5k:

Work done by A=400.5kx×2009=80010k9x

Step 3: Calculate the remaining work
The remaining work after A has worked is:

Remaining Work=WWork done by A=400.5k80010k9x

Step 4: Calculate the work done by B
B completes the remaining work in the same time that C and D together can complete the whole work. Since C and D can complete the work in 44.5 days, B's work time is also 44.5 days.

B's efficiency is W2x. Thus, the work done by B is:

Work done by B=W2x×44.5=400.5k2x×44.5=400.5×44.5k2x

Step 5: Set up the equation
Since the remaining work done by B equals the remaining work calculated earlier, we can set up the equation:

400.5k80010k9x=400.5×44.5k2x

Step 6: Simplify the equation
Dividing through by k (assuming k0):

400.5800109x=400.5×44.52x

Step 7: Solve for x
Multiply through by 18x to eliminate the fractions:

18x×400.51600200=9×400.5×44.5

Calculating 9×400.5×44.5:

9×400.5×44.5=160020

Thus, we have:

7215x1600200=160020

Combining like terms:

7215x=160020+1600200
7215x=1760220

Finally, solving for x:

x=17602207215=244.5

Conclusion
The value of x is 3313 days.

Updated on:8/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Each of A, B, C and D need a umique
    time to do a certain work. A can do the work in x days and B can
    do the work in 2x days. A started the work and do it for 2229 days
    then he is replaced by B and B completed remaining work in same
    time as C and D together can complete the whole work.
    The ratio of the efficiency of C and D is 4:5. If C and D work for
    alternative days starting form C then they can do the total work
    in 4412 days.

    A66(2/3)
    B33(1/3)
    C16(2/3)
    D14(2/7)
  • Each of A, B, C and D need a umique
    time to do a certain work. A can do the work in x days and B can
    do the work in 2x days. A started the work and do it for 2229 days
    then he is replaced by B and B completed remaining work in same
    time as C and D together can complete the whole work.
    The ratio of the efficiency of C and D is 4:5. If C and D work for
    alternative days starting form C then they can do the total work
    in 4412 days.

    A6623
    B3313
    C1623
    D1427
  • A can do 25 of a work in 6 days and B can do 23 of the same work in 12 days. A and B worked together for 6 days. C alone completed the remaining work in 8 days. A and C, working together, will complete the same work in:

    A12 days
    B9 days
    C10 days
    D8 days