Each of A, B, C and D need a unique time to do a certain work. A can do the work in x days and B can do the work in 2x days. A started the work and do it for 2229days then he is replaced by B, who completed remaining work in same time as C and D together can complete the whole work. The ratio of the efficiency of C and D is 4 : 5. If C and D work for alternative days starting from C then they can do the total work in 4412days.
A and B together can compete 225% of the work in how many days?
6623 days
60 days
50 days
25 days
The correct Answer is:C
To solve the problem step by step, we will follow the information given in the question and derive the necessary values.
Step 1: Determine the total work done by C and D
- The efficiency ratio of C and D is given as 4:5.
- When C and D work alternately starting from C, they complete the work in 4412 days.
- First, convert 4412 days into improper fraction:
4412=892 days
- In 2 days, C and D together complete:
4+5=9 units of work
- In 44 days, they will complete:
892÷2=44.5 days⇒44 complete cycles of 2 days+1 day of C
- Therefore, the total work done in 44 complete cycles:
44×9=396 units
- On the last day, C works for half a day, completing:
42=2 units
- Thus, the total work done is:
396+2=398 units
Step 2: Calculate the efficiencies of A and B
- Let A's time to complete the work be x days, then B's time is 2x days.
- The efficiency of A is:
Efficiency of A=1x (work per day)
- The efficiency of B is:
Efficiency of B=12x
Step 3: Calculate the work done by A in 2229 days
- Convert 2229 into improper fraction:
2229=2009 days
- Work done by A in this time:
Work by A=2009×1x=2009x
Step 4: Calculate remaining work
- Total work is 398 units, so remaining work after A's contribution is:
Remaining Work=398−2009x
Step 5: Determine the time taken by B to finish the remaining work
- Since B completes the remaining work in the same time as C and D can complete the whole work, we know:
398−2009x12x=Time taken by B
- The time taken by C and D together to complete the whole work is:
39892=398×29=7969 days
Step 6: Set up the equation
- Equating the time taken by B to finish the remaining work to the time taken by C and D:
398−2009x12x=7969
- Solving this equation will yield the value of x.
Step 7: Calculate the total work A and B can complete together in 225%
- Total work is 398 units, so 225% of the work is:
398×225100=448.5 units
- Combined efficiency of A and B:
Combined Efficiency=1x+12x=32x
- Time taken by A and B together to complete 448.5 units:
Time=448.532x=448.5×2x3=897x3
Step 8: Substitute x and calculate the final answer
- Substitute the value of x obtained from previous calculations to find the total time.
- The efficiency ratio of C and D is given as 4:5.
- When C and D work alternately starting from C, they complete the work in 4412 days.
- First, convert 4412 days into improper fraction:
4412=892 days
- In 2 days, C and D together complete:
4+5=9 units of work
- In 44 days, they will complete:
892÷2=44.5 days⇒44 complete cycles of 2 days+1 day of C
- Therefore, the total work done in 44 complete cycles:
44×9=396 units
- On the last day, C works for half a day, completing:
42=2 units
- Thus, the total work done is:
396+2=398 units
- Let A's time to complete the work be x days, then B's time is 2x days.
- The efficiency of A is:
Efficiency of A=1x (work per day)
- The efficiency of B is:
Efficiency of B=12x
- Convert 2229 into improper fraction:
2229=2009 days
- Work done by A in this time:
Work by A=2009×1x=2009x
- Total work is 398 units, so remaining work after A's contribution is:
Remaining Work=398−2009x
- Since B completes the remaining work in the same time as C and D can complete the whole work, we know:
398−2009x12x=Time taken by B
- The time taken by C and D together to complete the whole work is:
39892=398×29=7969 days
- Equating the time taken by B to finish the remaining work to the time taken by C and D:
398−2009x12x=7969
- Solving this equation will yield the value of x.
- Total work is 398 units, so 225% of the work is:
398×225100=448.5 units
- Combined efficiency of A and B:
Combined Efficiency=1x+12x=32x
- Time taken by A and B together to complete 448.5 units:
Time=448.532x=448.5×2x3=897x3
- Substitute the value of x obtained from previous calculations to find the total time.
Topper's Solved these Questions
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PREVIOUS YEAR QUESTIONS
32 Videos
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 2)
40 Videos
- SPEED, TIME AND DISTANCEBOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions
31 Videos
Similar Questions
A can do a work in x days and B can do the same work in y days. If x>y , then who can do more work in 6 days?
View SolutionA can do a piece of work in 10 days and B can do same work in 15 days. Both A and B start the work and after 3 days B left. In how many days will A do the remaining work?
View Solution
Knowledge Check
Each of A, B, C and D need a umique
time to do a certain work. A can do the work in x days and B can
do the work in 2x days. A started the work and do it for 2229 days
then he is replaced by B and B completed remaining work in same
time as C and D together can complete the whole work.
The ratio of the efficiency of C and D is 4:5. If C and D work for
alternative days starting form C then they can do the total work
in 4412 days.A66(2/3)B33(1/3)C16(2/3)D14(2/7)Each of A, B, C and D need a umique
time to do a certain work. A can do the work in x days and B can
do the work in 2x days. A started the work and do it for 2229 days
then he is replaced by B and B completed remaining work in same
time as C and D together can complete the whole work.
The ratio of the efficiency of C and D is 4:5. If C and D work for
alternative days starting form C then they can do the total work
in 4412 days.A6623B3313C1623D1427A can do 25 of a work in 6 days and B can do 23 of the same work in 12 days. A and B worked together for 6 days. C alone completed the remaining work in 8 days. A and C, working together, will complete the same work in:
A12 daysB9 daysC10 daysD8 days
A can do a piece of work in 20 days and B can do same work in 25 days. Both A and B start the work and after 8 days A left. In how many days will the total work be completed ?
View SolutionA can do 45 of a work in 20 days and B can do 34 of the same work in 15 days. They work together for 10 days. C alone completes the remaining work in 1 day. B and C together can complete 34 of the same work in:
View SolutionA can do a work in 20 days and B can do the same work in 30 days in how many days canA and B together do the work?
View SolutionA can do of a work in 10 days. B can do of the work in 20 days. In how many days can both A and B together do the work?
View SolutionA can do a piece of work in 10 days and B can dothe same piece of work in 20 days. They start the work together but after 5 days A leaves off. B will do the remaining piece of work in..
View Solution