A can do a piece of work in 6 days working 8 hours a day while B can do the same work in 4 days working 10 hours a day. If the work has to be completed in 5 days, so how many hours do they need to work together in a days?
4
5411
6411
4411
The correct Answer is:D
To solve the problem step by step, we need to determine how many hours A and B need to work together each day to complete the work in 5 days.
Step 1: Calculate the total work done by A and B.
- A's Work Calculation:
A can complete the work in 6 days, working 8 hours a day.
Total work by A=6 days×8 hours/day=48 hours
- B's Work Calculation:
B can complete the work in 4 days, working 10 hours a day.
Total work by B=4 days×10 hours/day=40 hours
Step 2: Determine the total amount of work required.
The total work required to complete the task is the same as the work done by A or B, which is the maximum of the two:
Total Work=48 hours (A's work)
Step 3: Calculate the work done per hour by A and B.
- A's Work Rate:
Work rate of A=1 work48 hours=148 work/hour
- B's Work Rate:
Work rate of B=1 work40 hours=140 work/hour
Step 4: Combine their work rates.
To find the combined work rate of A and B:
Combined work rate=148+140
To add these fractions, we need a common denominator. The least common multiple of 48 and 40 is 240.
Converting the fractions:
148=5240,140=6240
So,
Combined work rate=5240+6240=11240 work/hour
Step 5: Calculate the total work needed in 5 days.
If they need to complete the work in 5 days, the total work done in 5 days at their combined work rate is:
Total work in 5 days=5 days×H hours/day×11240 work/hour
Setting this equal to 1 (the total work):
5H⋅11240=1
Step 6: Solve for H.
Rearranging the equation:
H=2405×11=24055=4811
Step 7: Convert hours into a mixed number.
H=4411 hours
Final Answer:
A and B need to work together for approximately 4411 hours each day to complete the work in 5 days.
---
A can complete the work in 6 days, working 8 hours a day.
Total work by A=6 days×8 hours/day=48 hours
B can complete the work in 4 days, working 10 hours a day.
Total work by B=4 days×10 hours/day=40 hours
Total Work=48 hours (A's work)
Work rate of A=1 work48 hours=148 work/hour
Work rate of B=1 work40 hours=140 work/hour
Combined work rate=148+140
148=5240,140=6240
So,
Combined work rate=5240+6240=11240 work/hour
Total work in 5 days=5 days×H hours/day×11240 work/hour
Setting this equal to 1 (the total work):
5H⋅11240=1
H=2405×11=24055=4811
A and B need to work together for approximately 4411 hours each day to complete the work in 5 days.
Topper's Solved these Questions
- TIME AND WORKBOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-II
45 Videos
- TIME AND WORKBOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-III
31 Videos
- TIME AND DISTANCEBOOK - KIRAN PUBLICATIONCHAPTER - TIME AND DISTANCEEXERCISE - Type -XI
74 Videos
- TRIGONOMETRY BOOK - KIRAN PUBLICATIONCHAPTER - TRIGONOMETRY EXERCISE - TEST YOURSELF
25 Videos
Similar Questions
Knowledge Check
P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work ? 5511 b. 5611 c. 6611 d. 6611
A5511B5611C6511D6611P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how man days can they complete the work ?
A5511B5611C6511D6611A can do a piece of work in 16 days and B can do the same work in 20 days. In how many days can they do the same work, working together?
A819B989C889D918
A can do a piece of work in 9 days, In how many days can the work be completed if A and B work together ?
View Solution10 men working 6 hours a day can complete a work in 18 days. How many hours a day must 15 men work to complete the same work in 12 days.
View SolutionIf A can do a piece of work in 4 days, B can do the same work in 8 days and C can do the same work in 12 days , then working together , how many days will they take to complete the work ?
View SolutionIf 25 men can do a piece of work in 36 days working 10 hours a day, then how many men are required to complete the work working 6 hours a day in 20 days?
View SolutionA can complete a work in 12 days with a working of 8 hours per day. B can complete the same work in 8 days when working 10 hours a day. If Both start the work together, working 8 hours a day, the work can be completed in __ days.
View Solution