A can complete a work in 12 days with a working of 8 hours per day. B can complete the same work in 8 days when working 10 hours a day. If Both start the work together, working 8 hours a day, the work can be completed in __ days.

A

5511

B

4511

C

6411

D

6511

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we will first determine the total work done by A and B, their efficiencies, and then calculate how long it will take them to complete the work together.

Step 1: Calculate the total work done by A and B

1. Work done by A:
- A can complete the work in 12 days, working 8 hours a day.
- Total hours worked by A = 12 days × 8 hours/day = 96 hours.
- Therefore, the total work (in units) can be defined as 1 unit of work per hour.
- Total work = 96 units.

2. Work done by B:
- B can complete the work in 8 days, working 10 hours a day.
- Total hours worked by B = 8 days × 10 hours/day = 80 hours.
- Therefore, the total work (in units) can be defined as 1 unit of work per hour.
- Total work = 80 units.

3. Finding the LCM for total work:
- The total work can be taken as the LCM of the total hours worked by A and B.
- LCM of 96 and 80 is 480 units.

Step 2: Calculate the efficiency of A and B

1. Efficiency of A:
- A's efficiency = Total work / Total time = 480 units / 96 hours = 5 units/hour.

2. Efficiency of B:
- B's efficiency = Total work / Total time = 480 units / 80 hours = 6 units/hour.

Step 3: Calculate combined efficiency when A and B work together

1. Combined efficiency:
- When A and B work together, their combined efficiency = Efficiency of A + Efficiency of B = 5 units/hour + 6 units/hour = 11 units/hour.

Step 4: Calculate the total work done in one day

1. Working hours per day:
- Both A and B work together for 8 hours a day.
- Work done in one day = Combined efficiency × Working hours per day = 11 units/hour × 8 hours = 88 units/day.

Step 5: Calculate the total time to complete the work

1. Total work to be completed:
- Total work = 480 units.

2. Time taken to complete the work:
- Time = Total work / Work done in one day = 480 units / 88 units/day = 5.45 days.

Step 6: Convert to mixed fraction

1. Convert 5.45 to mixed fraction:
- 5.45 = 5 + 0.45 = 5 + 5/11.

Thus, the work can be completed in 5 5/11 days.

Final Answer:
The work can be completed in 5 5/11 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how man days can they complete the work ?

    A5511
    B5611
    C6511
    D6611
  • Question 2 - Select One

    P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work ? 5511 b. 5611 c. 6611 d. 6611

    A5511
    B5611
    C6511
    D6611
  • Question 3 - Select One

    Working 5 hours a day. A can complete a work in 8 days and working 6 hours a day, B can complete the same work in 10 days. Working 8 hours a day, they can jointly complete the work in

    A3 days
    B4 days
    C4.5 days
    D5.4 days