A can complete a work in 12 days with a working of 8 hours per day. B can complete the same work in 8 days when working 10 hours a day. If Both start the work together, working 8 hours a day, the work can be completed in __ days.
5511
4511
6411
6511
The correct Answer is:A
To solve the problem step by step, we will first determine the total work done by A and B, their efficiencies, and then calculate how long it will take them to complete the work together.
Step 1: Calculate the total work done by A and B
1. Work done by A:
- A can complete the work in 12 days, working 8 hours a day.
- Total hours worked by A = 12 days × 8 hours/day = 96 hours.
- Therefore, the total work (in units) can be defined as 1 unit of work per hour.
- Total work = 96 units.
2. Work done by B:
- B can complete the work in 8 days, working 10 hours a day.
- Total hours worked by B = 8 days × 10 hours/day = 80 hours.
- Therefore, the total work (in units) can be defined as 1 unit of work per hour.
- Total work = 80 units.
3. Finding the LCM for total work:
- The total work can be taken as the LCM of the total hours worked by A and B.
- LCM of 96 and 80 is 480 units.
Step 2: Calculate the efficiency of A and B
1. Efficiency of A:
- A's efficiency = Total work / Total time = 480 units / 96 hours = 5 units/hour.
2. Efficiency of B:
- B's efficiency = Total work / Total time = 480 units / 80 hours = 6 units/hour.
Step 3: Calculate combined efficiency when A and B work together
1. Combined efficiency:
- When A and B work together, their combined efficiency = Efficiency of A + Efficiency of B = 5 units/hour + 6 units/hour = 11 units/hour.
Step 4: Calculate the total work done in one day
1. Working hours per day:
- Both A and B work together for 8 hours a day.
- Work done in one day = Combined efficiency × Working hours per day = 11 units/hour × 8 hours = 88 units/day.
Step 5: Calculate the total time to complete the work
1. Total work to be completed:
- Total work = 480 units.
2. Time taken to complete the work:
- Time = Total work / Work done in one day = 480 units / 88 units/day = 5.45 days.
Step 6: Convert to mixed fraction
1. Convert 5.45 to mixed fraction:
- 5.45 = 5 + 0.45 = 5 + 5/11.
Thus, the work can be completed in 5 5/11 days.
Final Answer:
The work can be completed in 5 5/11 days.
---
- A can complete the work in 12 days, working 8 hours a day.
- Total hours worked by A = 12 days × 8 hours/day = 96 hours.
- Therefore, the total work (in units) can be defined as 1 unit of work per hour.
- Total work = 96 units.
- B can complete the work in 8 days, working 10 hours a day.
- Total hours worked by B = 8 days × 10 hours/day = 80 hours.
- Therefore, the total work (in units) can be defined as 1 unit of work per hour.
- Total work = 80 units.
- The total work can be taken as the LCM of the total hours worked by A and B.
- LCM of 96 and 80 is 480 units.
- A's efficiency = Total work / Total time = 480 units / 96 hours = 5 units/hour.
- B's efficiency = Total work / Total time = 480 units / 80 hours = 6 units/hour.
- When A and B work together, their combined efficiency = Efficiency of A + Efficiency of B = 5 units/hour + 6 units/hour = 11 units/hour.
- Both A and B work together for 8 hours a day.
- Work done in one day = Combined efficiency × Working hours per day = 11 units/hour × 8 hours = 88 units/day.
- Total work = 480 units.
2. Time taken to complete the work:
- Time = Total work / Work done in one day = 480 units / 88 units/day = 5.45 days.
- 5.45 = 5 + 0.45 = 5 + 5/11.
The work can be completed in 5 5/11 days.
Topper's Solved these Questions
Similar Questions
P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work ? 5511 b. 5611 c. 6611 d. 6611
View SolutionUday working 4 hours a day completes a work in 10 days, while Subhash working 8 hours a day can complete the same work in 15 days. How many days will it take for both of them working together 10 hours a day to complete the work ?
View Solution
Knowledge Check
- Question 1 - Select One
P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how man days can they complete the work ?
A5511B5611C6511D6611 - Question 2 - Select One
P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work ? 5511 b. 5611 c. 6611 d. 6611
A5511B5611C6511D6611 - Question 3 - Select One
Working 5 hours a day. A can complete a work in 8 days and working 6 hours a day, B can complete the same work in 10 days. Working 8 hours a day, they can jointly complete the work in
A3 daysB4 daysC4.5 daysD5.4 days
Working 5 hours a day. A can' complete a work in 8 days and working 6 hours a day, B can complete the same work in 10 days. Working 8 hours a day, they can jointly complete the work in
View SolutionA man completes a work in 10 days by doing 5 hours per day. By doing 7 hours per day, he can complete this work in -
View SolutionMohan can complete a job in 8 days working 9 hourse a day. Sohan can complte it in I daays wrorking 10 hours a day. In how many days can Mohan and Sohan together complete it working 8 hours a day ?
View SolutionIf 20 men complete a work in 56 days by working 10 hours a day how many days will 40 men take to complete the same work by working 8 hours a day?
View SolutionIf 40 men working 12 hours a day can complete a work in 8 days, then how many men working 4 hours a day can complete the same work in 16 days ?
यदि 40 लोग प्रतिदिन 12 घंटे कार्य करके किसी कार्य को 8 दिनों में समाप्त कर सकते हैं, तो इस कार्य को प्रतिदिन 4 घंटे कार्य करते हुए 16 दिनों में समाप्त करने के लिए कितने पुरुषों की आवश्यकता होगी ?View Solution