Working 5 hours a day. A can' complete a work in 8 days and working 6 hours a day, B can complete the same work in 10 days. Working 8 hours a day, they can jointly complete the work in
3 days
4 days
4.5 days
5.4 days
The correct Answer is:A
To solve the problem step by step, we will first determine the total amount of work done by A and B individually, and then find out how long they take to complete the work together when working 8 hours a day.
Step 1: Calculate the total work done by A
A works for 5 hours a day and can complete the work in 8 days.
- Total work done by A = hours worked per day × number of days
- Total work done by A = 5 hours/day × 8 days = 40 hours
Step 2: Calculate the total work done by B
B works for 6 hours a day and can complete the work in 10 days.
- Total work done by B = hours worked per day × number of days
- Total work done by B = 6 hours/day × 10 days = 60 hours
Step 3: Calculate the work rate of A and B
The work rate is the fraction of work completed in one hour.
- Work rate of A = 1/Total work done by A = 1/40
- Work rate of B = 1/Total work done by B = 1/60
Step 4: Calculate the combined work rate of A and B
To find the combined work rate when A and B work together, we add their individual work rates:
- Combined work rate = Work rate of A + Work rate of B
- Combined work rate = 1/40 + 1/60
To add these fractions, we need a common denominator. The least common multiple (LCM) of 40 and 60 is 120.
- 1/40 = 3/120
- 1/60 = 2/120
- Combined work rate = 3/120 + 2/120 = 5/120 = 1/24
Step 5: Calculate the time taken to complete the work together
If A and B can complete 1/24 of the work in one hour, then the total time taken to complete the entire work is the reciprocal of their combined work rate:
- Time taken = 1 / (1/24) = 24 hours
Step 6: Calculate the time taken when working 8 hours a day
Now, we need to determine how many days it will take them to complete the work if they work 8 hours a day:
- Total hours needed = 24 hours
- Days needed = Total hours needed / hours worked per day
- Days needed = 24 hours / 8 hours/day = 3 days
Final Answer
Therefore, working together for 8 hours a day, A and B can complete the work in 3 days.
A works for 5 hours a day and can complete the work in 8 days.
- Total work done by A = hours worked per day × number of days
- Total work done by A = 5 hours/day × 8 days = 40 hours
B works for 6 hours a day and can complete the work in 10 days.
- Total work done by B = hours worked per day × number of days
- Total work done by B = 6 hours/day × 10 days = 60 hours
The work rate is the fraction of work completed in one hour.
- Work rate of A = 1/Total work done by A = 1/40
- Work rate of B = 1/Total work done by B = 1/60
To find the combined work rate when A and B work together, we add their individual work rates:
- Combined work rate = Work rate of A + Work rate of B
- Combined work rate = 1/40 + 1/60
- 1/40 = 3/120
- 1/60 = 2/120
- Combined work rate = 3/120 + 2/120 = 5/120 = 1/24
If A and B can complete 1/24 of the work in one hour, then the total time taken to complete the entire work is the reciprocal of their combined work rate:
- Time taken = 1 / (1/24) = 24 hours
Now, we need to determine how many days it will take them to complete the work if they work 8 hours a day:
- Total hours needed = 24 hours
- Days needed = Total hours needed / hours worked per day
- Days needed = 24 hours / 8 hours/day = 3 days
Therefore, working together for 8 hours a day, A and B can complete the work in 3 days.
Similar Questions
10 men working 6 hours a day can complete a work in 18 days. How many hours a day must 15 men work to complete the same work in 12 days.
View SolutionP can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work ? 5511 b. 5611 c. 6611 d. 6611
View Solution
Knowledge Check
Working 2 hours in a day, P can complete a work in 10 days and working 5 hours in a day, Q can complete the same work in 6 days. Working 3 hours in a day, in how many days both P and Q together can complete the same work?
A3 daysB6 daysC4 daysD5 daysIf 40 men working 12 hours a day can complete a work in 8 days, then how many men working 4 hours a day can complete the same work in 16 days ?
यदि 40 लोग प्रतिदिन 12 घंटे कार्य करके किसी कार्य को 8 दिनों में समाप्त कर सकते हैं, तो इस कार्य को प्रतिदिन 4 घंटे कार्य करते हुए 16 दिनों में समाप्त करने के लिए कितने पुरुषों की आवश्यकता होगी ?A50B60C54D45P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how man days can they complete the work ?
A5511B5611C6511D6611
Uday working 4 hours a day completes a work in 10 days, while Subhash working 8 hours a day can complete the same work in 15 days. How many days will it take for both of them working together 10 hours a day to complete the work ?
View SolutionP can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work ? 5511 b. 5611 c. 6611 d. 6611
View SolutionA person invests money in two different schemes for 5 years and 8 years at 12% and 10% simple interest, respectively. At the completion of each scheme he gets the same interest. The ratio of his investments is
View SolutionA man working 8 hours a day takes 5 days to complete a project. How many hours a day must he work to complete. It in 4 days?
View SolutionIf 16 men working 12 hours a day can complete a work in 27 days, then working for how many hours a day can 18 men complete the work in 24 days ?
यदि 16 पुरुष प्रतिदिन 12 घंटे कार्य करके किसी कार्य को 27 दिनों में पूरा करते हैं, तो इस कार्य को 24 दिनों में पूरा करने के लिए 18 पुरुषों को दिन में कितने घंटे कार्य करना पड़ेगा ?
View Solution