Working 5 hours a day. A can' complete a work in 8 days and working 6 hours a day, B can complete the same work in 10 days. Working 8 hours a day, they can jointly complete the work in

A

3 days

B

4 days

C

4.5 days

D

5.4 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we will first determine the total amount of work done by A and B individually, and then find out how long they take to complete the work together when working 8 hours a day.

Step 1: Calculate the total work done by A
A works for 5 hours a day and can complete the work in 8 days.
- Total work done by A = hours worked per day × number of days
- Total work done by A = 5 hours/day × 8 days = 40 hours

Step 2: Calculate the total work done by B
B works for 6 hours a day and can complete the work in 10 days.
- Total work done by B = hours worked per day × number of days
- Total work done by B = 6 hours/day × 10 days = 60 hours

Step 3: Calculate the work rate of A and B
The work rate is the fraction of work completed in one hour.
- Work rate of A = 1/Total work done by A = 1/40
- Work rate of B = 1/Total work done by B = 1/60

Step 4: Calculate the combined work rate of A and B
To find the combined work rate when A and B work together, we add their individual work rates:
- Combined work rate = Work rate of A + Work rate of B
- Combined work rate = 1/40 + 1/60

To add these fractions, we need a common denominator. The least common multiple (LCM) of 40 and 60 is 120.
- 1/40 = 3/120
- 1/60 = 2/120
- Combined work rate = 3/120 + 2/120 = 5/120 = 1/24

Step 5: Calculate the time taken to complete the work together
If A and B can complete 1/24 of the work in one hour, then the total time taken to complete the entire work is the reciprocal of their combined work rate:
- Time taken = 1 / (1/24) = 24 hours

Step 6: Calculate the time taken when working 8 hours a day
Now, we need to determine how many days it will take them to complete the work if they work 8 hours a day:
- Total hours needed = 24 hours
- Days needed = Total hours needed / hours worked per day
- Days needed = 24 hours / 8 hours/day = 3 days

Final Answer
Therefore, working together for 8 hours a day, A and B can complete the work in 3 days.

Updated on:7/8/2024
|


Similar Questions


Knowledge Check

  • Working 2 hours in a day, P can complete a work in 10 days and working 5 hours in a day, Q can complete the same work in 6 days. Working 3 hours in a day, in how many days both P and Q together can complete the same work?

    A3 days
    B6 days
    C4 days
    D5 days
  • If 40 men working 12 hours a day can complete a work in 8 days, then how many men working 4 hours a day can complete the same work in 16 days ?
    यदि 40 लोग प्रतिदिन 12 घंटे कार्य करके किसी कार्य को 8 दिनों में समाप्त कर सकते हैं, तो इस कार्य को प्रतिदिन 4 घंटे कार्य करते हुए 16 दिनों में समाप्त करने के लिए कितने पुरुषों की आवश्यकता होगी ?

    A50
    B60
    C54
    D45
  • P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how man days can they complete the work ?

    A5511
    B5611
    C6511
    D6611