Sabir is thrice as good as Anish in work. Sabir is able to finish a job in 60 days less than Anish. Both can finish the work in - days working together.
18 days
2212days
24 days
26 days
The correct Answer is:B
To solve the problem step by step, let's denote:
- The number of days Anish takes to complete the work as D.
- Since Sabir is thrice as good as Anish, his efficiency can be represented as 3 times Anish's efficiency.
Step 1: Establish the relationship between Sabir's and Anish's work days
Given that Sabir finishes the job in 60 days less than Anish, we can express this as:
DS=D−60
where DS is the number of days Sabir takes to complete the work.
Step 2: Relate their efficiencies to the number of days
Since efficiency is inversely proportional to the number of days taken to complete the work, we can write:
- Efficiency of Anish = 1D
- Efficiency of Sabir = 1D−60
Given that Sabir is thrice as efficient as Anish, we can express this as:
1D−60=3⋅1D
Step 3: Set up the equation
Cross-multiplying gives us:
D=3(D−60)
Expanding this:
D=3D−180
Rearranging the equation:
180=3D−D
180=2D
D=90
Step 4: Calculate Sabir's days
Now that we have D, we can find the number of days Sabir takes:
DS=D−60=90−60=30
Step 5: Calculate the total work done
The total work can be calculated using the efficiency:
- Total work = Efficiency × Days
- For Anish: Total Work=190×90=1 (1 unit of work)
- For Sabir: Total Work=130×30=1 (1 unit of work)
Step 6: Calculate the combined work rate
When working together, their combined efficiency is:
Combined Efficiency=1D+1DS=190+130
Finding a common denominator (which is 90):
Combined Efficiency=190+390=490=245
Step 7: Calculate the time taken when working together
If their combined efficiency is 245, the time taken to complete the work together is:
Time=Total WorkCombined Efficiency=1245=452=22.5 days
Conclusion
Thus, both Sabir and Anish can finish the work together in 22.5 days.
- Since Sabir is thrice as good as Anish, his efficiency can be represented as 3 times Anish's efficiency.
Given that Sabir finishes the job in 60 days less than Anish, we can express this as:
DS=D−60
where DS is the number of days Sabir takes to complete the work.
Since efficiency is inversely proportional to the number of days taken to complete the work, we can write:
- Efficiency of Anish = 1D
- Efficiency of Sabir = 1D−60
1D−60=3⋅1D
Cross-multiplying gives us:
D=3(D−60)
Expanding this:
D=3D−180
Rearranging the equation:
180=3D−D
180=2D
D=90
Now that we have D, we can find the number of days Sabir takes:
DS=D−60=90−60=30
The total work can be calculated using the efficiency:
- Total work = Efficiency × Days
- For Anish: Total Work=190×90=1 (1 unit of work)
- For Sabir: Total Work=130×30=1 (1 unit of work)
When working together, their combined efficiency is:
Combined Efficiency=1D+1DS=190+130
Finding a common denominator (which is 90):
Combined Efficiency=190+390=490=245
If their combined efficiency is 245, the time taken to complete the work together is:
Time=Total WorkCombined Efficiency=1245=452=22.5 days
Thus, both Sabir and Anish can finish the work together in 22.5 days.
Topper's Solved these Questions
Similar Questions
Two men A and B started a job in which A was thrice as good as B and therefore took 60 days less than B to finish the job. How many days will they take to finish the job, if they start working together?
View SolutionP is thrice as good a workman as Q and therefore able to finish a Job in 48 days less than . Working together, they can do it in :
View Solution
Knowledge Check
A is thrice as good a workman as B and therefore is able to finish a job in 30 days less than B. How many days will they take to finish the job working together?
A1014B1134C1114D1113A is thrice as good a workman as B and therefore is able to finish a job in 40 days less than B. Working together, they can do it in
A14 daysB13 daysC20 daysD15 daysA is thrice as good a workman B and therefore is able to finish a job in 40 days less titan B. Working together, they can do it in
A14 daysB13 daysC20 daysD15 days
A is twice as good a workman as B and together they finish a piece of work in 14 days. In how many days can A alone finish the work?
View SolutionA is thrice as good a workman as B and is, therefore, able to finish a piece of work in 60 days less than B. The time (in days) in which they can do it working together is
View SolutionM is thrice as good as workman as N and together they finish a piece of work in 30 days. In how many days will M alone finish the work?
View SolutionA is twice as good a workman as B and together they finish a piece of work in 7 days. In how many days can A alone finish the work?
View SolutionA is twice as good a workman as B and together they finish a piece of work in 7 days. In how many days can B alone finish the work?
View Solution