Doubtnut Promotions Sticky

Some carpenters promised to do a job in 9 days but 5 of them were absent and remaining men did the job in 12 days. The original number of carpenters was

A

24

B

20

C

16

D

18

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:B

|
Answer

Step by step video, text & image solution for Some carpenters promised to do a job in 9 days but 5 of them were absent and remaining men did the job in 12 days. The original number of carpenters was by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Related Playlists


Knowledge Check

  • Question 1 - Select One

    Some carpenters promised to do a job in 15 days but 3 of them were absent and remaining did the job in 20 days. What was the original number of carpenters?

    A10
    B15
    C12
    D14
  • Question 1 - Select One

    Some mans promised to do a work in 10 days but 8 of them were absent and remaining did the work in 18 days. What was the original number of mans?

    A10
    B21
    C15
    D18
  • Question 1 - Select One

    A certain-job was assigned to a group of men to do in 20 days. But 12 men did not turn up for the job and remaining men did the job in 32 days. The original number of men in the group was :

    A32
    B36
    C42
    D40
  • Question 1 - Select One

    A certain job was assigned to a group of men to do in 20 days. But 12 men did not turn up for the job and the remaining men did the job in 32 days. The original number of men in the group was :

    A32
    B36
    C42
    D40
  • Question 1 - Select One

    A group of men decided to do a work in 10 days, but 5 of them become absent. if the rest of the group did the work in 12 days, find the original number of men?

    A20
    B25
    C30
    D35
  • Question 1 - Select One

    Some staff promised to do a job in 18 days, but 6 of them went on leave. So the remaining men took 20 days to complete the job. How many men were there originally?

    A55
    B62
    C56
    D60
  • Question 1 - Select One

    24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :

    A30
    B40
    C25
    D50
  • Question 1 - Select One

    If 30 men can do a job in 30 days, find what part of the job can be completed by 1 man in 1 day.

    A130
    B1900
    C190
    D160
  • Question 1 - Select One

    If 12 men can do a job in 7 days, what fraction of the job can be done by one man in one day?

    A114
    B712
    C184
    D172

Similar Questions