Some carpenters promised to do a job in 9 days but 5 of them were absent and remaining men did the job in 12 days. The original number of carpenters was

A

24

B

20

C

16

D

18

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we can follow this approach:

Step 1: Define the Variables
Let the original number of carpenters be x.

Step 2: Calculate Total Work
The carpenters promised to complete the job in 9 days. Therefore, the total work can be expressed as:
Total Work=Number of Carpenters×Days=x×9=9x

Step 3: Calculate Work Done by Remaining Carpenters
Since 5 carpenters were absent, the number of carpenters who actually worked is:
x5
They completed the job in 12 days, so the total work done can also be expressed as:
Total Work=Number of Remaining Carpenters×Days=(x5)×12

Step 4: Set Up the Equation
Since both expressions represent the total work, we can set them equal to each other:
9x=12(x5)

Step 5: Expand and Simplify the Equation
Expanding the right side:
9x=12x60
Now, rearranging the equation to isolate x:
9x12x=60
3x=60

Step 6: Solve for x
Dividing both sides by -3:
x=20

Conclusion
The original number of carpenters was 20.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Some carpenters promised to do a job in 15 days but 3 of them were absent and remaining did the job in 20 days. What was the original number of carpenters?

    A10
    B15
    C12
    D14
  • Some mans promised to do a work in 10 days but 8 of them were absent and remaining did the work in 18 days. What was the original number of mans?

    A10
    B21
    C15
    D18
  • A certain-job was assigned to a group of men to do in 20 days. But 12 men did not turn up for the job and remaining men did the job in 32 days. The original number of men in the group was :

    A32
    B36
    C42
    D40