Some carpenters promised to do a job in 9 days but 5 of them were absent and remaining men did the job in 12 days. The original number of carpenters was
A
24
B
20
C
16
D
18
Video Solution
Text Solution
The correct Answer is:B
|
Answer
Step by step video, text & image solution for Some carpenters promised to do a job in 9 days but 5 of them were absent and remaining men did the job in 12 days. The original number of carpenters was by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Updated on:21/07/2023
Related Playlists
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-II45videos
TIME AND WORK
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-III31videos
TIME AND WORK
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND DISTANCEEXERCISE - Type -XI74videos
TIME AND DISTANCE
- BOOK - KIRAN PUBLICATIONCHAPTER - TRIGONOMETRY EXERCISE - TEST YOURSELF25videos
TRIGONOMETRY
Knowledge Check
- Question 1 - Select One
Some carpenters promised to do a job in 15 days but 3 of them were absent and remaining did the job in 20 days. What was the original number of carpenters?
A10B15C12D14 - Question 1 - Select One
Some mans promised to do a work in 10 days but 8 of them were absent and remaining did the work in 18 days. What was the original number of mans?
A10B21C15D18 - Question 1 - Select One
A certain-job was assigned to a group of men to do in 20 days. But 12 men did not turn up for the job and remaining men did the job in 32 days. The original number of men in the group was :
A32B36C42D40 - Question 1 - Select One
A certain job was assigned to a group of men to do in 20 days. But 12 men did not turn up for the job and the remaining men did the job in 32 days. The original number of men in the group was :
A32B36C42D40 - Question 1 - Select One
A group of men decided to do a work in 10 days, but 5 of them become absent. if the rest of the group did the work in 12 days, find the original number of men?
A20B25C30D35 - Question 1 - Select One
Some staff promised to do a job in 18 days, but 6 of them went on leave. So the remaining men took 20 days to complete the job. How many men were there originally?
A55B62C56D60 - Question 1 - Select One
24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :
A30B40C25D50 - Question 1 - Select One
If 30 men can do a job in 30 days, find what part of the job can be completed by 1 man in 1 day.
A130B1900C190D160 - Question 1 - Select One
If 12 men can do a job in 7 days, what fraction of the job can be done by one man in one day?
A114B712C184D172