Some carpenters promised to do a job in 9 days but 5 of them were absent and remaining men did the job in 12 days. The original number of carpenters was
24
20
16
18
The correct Answer is:B
To solve the problem step by step, we can follow this approach:
Step 1: Define the Variables
Let the original number of carpenters be x.
Step 2: Calculate Total Work
The carpenters promised to complete the job in 9 days. Therefore, the total work can be expressed as:
Total Work=Number of Carpenters×Days=x×9=9x
Step 3: Calculate Work Done by Remaining Carpenters
Since 5 carpenters were absent, the number of carpenters who actually worked is:
x−5
They completed the job in 12 days, so the total work done can also be expressed as:
Total Work=Number of Remaining Carpenters×Days=(x−5)×12
Step 4: Set Up the Equation
Since both expressions represent the total work, we can set them equal to each other:
9x=12(x−5)
Step 5: Expand and Simplify the Equation
Expanding the right side:
9x=12x−60
Now, rearranging the equation to isolate x:
9x−12x=−60
−3x=−60
Step 6: Solve for x
Dividing both sides by -3:
x=20
Conclusion
The original number of carpenters was 20.
---
Let the original number of carpenters be x.
The carpenters promised to complete the job in 9 days. Therefore, the total work can be expressed as:
Total Work=Number of Carpenters×Days=x×9=9x
Since 5 carpenters were absent, the number of carpenters who actually worked is:
x−5
They completed the job in 12 days, so the total work done can also be expressed as:
Total Work=Number of Remaining Carpenters×Days=(x−5)×12
Since both expressions represent the total work, we can set them equal to each other:
9x=12(x−5)
Expanding the right side:
9x=12x−60
Now, rearranging the equation to isolate x:
9x−12x=−60
−3x=−60
Dividing both sides by -3:
x=20
The original number of carpenters was 20.
Topper's Solved these Questions
- TIME AND WORKBOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-II
45 Videos
- TIME AND WORKBOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-III
31 Videos
- TIME AND DISTANCEBOOK - KIRAN PUBLICATIONCHAPTER - TIME AND DISTANCEEXERCISE - Type -XI
74 Videos
- TRIGONOMETRY BOOK - KIRAN PUBLICATIONCHAPTER - TRIGONOMETRY EXERCISE - TEST YOURSELF
25 Videos
Similar Questions
6 men or 8 women can do a job in 10 days In how many days can 5 men and 9 women do the same job?
View SolutionA certain job was assigned to a group of men to do in 20 days. But 12 men did not turn up for the job and the remaining men did the job in 32 days. The original number of men in the group was :
View Solution
Knowledge Check
Some carpenters promised to do a job in 15 days but 3 of them were absent and remaining did the job in 20 days. What was the original number of carpenters?
A10B15C12D14Some mans promised to do a work in 10 days but 8 of them were absent and remaining did the work in 18 days. What was the original number of mans?
A10B21C15D18A certain-job was assigned to a group of men to do in 20 days. But 12 men did not turn up for the job and remaining men did the job in 32 days. The original number of men in the group was :
A32B36C42D40
A group of men decided to do a work in 10 days, but 5 of them become absent. if the rest of the group did the work in 12 days, find the original number of men?
View SolutionSome staff promised to do a job in 18 days, but 6 of them went on leave. So the remaining men took 20 days to complete the job. How many men were there originally?
View Solution24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :
View SolutionIf 30 men can do a job in 30 days, find what part of the job can be completed by 1 man in 1 day.
View SolutionIf 12 men can do a job in 7 days, what fraction of the job can be done by one man in one day?
View Solution