Doubtnut Promotions Sticky

A group of men decided to do a work in 10 days, but 5 of them become absent. if the rest of the group did the work in 12 days, find the original number of men?

A

20

B

25

C

30

D

35

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:30

|
Answer

Step by step video, text & image solution for A group of men decided to do a work in 10 days, but 5 of them become absent. if the rest of the group did the work in 12 days, find the original number of men? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Related Playlists


Knowledge Check

  • Question 1 - Select One

    Some mans promised to do a work in 10 days but 8 of them were absent and remaining did the work in 18 days. What was the original number of mans?

    A10
    B21
    C15
    D18
  • Question 1 - Select One

    Some carpenters promised to do a job in 9 days but 5 of them were absent and remaining men did the job in 12 days. The original number of carpenters was

    A24
    B20
    C16
    D18
  • Question 1 - Select One

    A certain numner of men agreed to do a work in 20 days. 5 men did come for work. Others completed the work in 40 days. Find the number of men who had agreed to do the work originally.

    AA) 8
    BB) 10
    CC) 12
    DD) 15
  • Question 1 - Select One

    A certain job was assigned to a group of men to do in 20 days. But 12 men did not turn up for the job and the remaining men did the job in 32 days. The original number of men in the group was :

    A32
    B36
    C42
    D40
  • Question 1 - Select One

    A contractor undertook to do a piece of work in 9 days. He employed certain number of laboures but 6 of them were absent from the very first day and the rest could finish the work in only 15 days. Find the number of men originally employed

    A15
    B6
    C13
    D9
  • Question 1 - Select One

    A certain-job was assigned to a group of men to do in 20 days. But 12 men did not turn up for the job and remaining men did the job in 32 days. The original number of men in the group was :

    A32
    B36
    C42
    D40
  • Question 1 - Select One

    A contractor undertook to do a certain piece of work in 18 days. He employed certain number of men but 12 of them being absent from the very 1st day , the rest could finish the work in 30 days . Find the number of men originally employed .

    A40
    B15
    C45
    D30
  • Question 1 - Select One

    A group of persons can do a work in 10 days. If 5 persons remains absent from first day, then the work is completed in 12 days by remaining persons. Tell how many persons were in the group initially?

    A1. 20
    B2. 25
    C3. 45
    D4. 30
  • Question 1 - Select One

    'x' number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men is

    A6
    B10
    C12
    D15
  • Question 1 - Select One

    'x' number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men is

    A6
    B10
    C12
    D15