A contractor undertook to do a certain piece of work in 18 days. He employed certain number of men but 12 of them being absent from the very 1st day , the rest could finish the work in 30 days . Find the number of men originally employed .
40
15
45
30
The correct Answer is:D
To solve the problem step by step, we can follow these calculations:
Step 1: Define Variables
Let X be the number of men originally employed by the contractor.
Step 2: Work Done Calculation
The total work can be expressed in terms of men and days. If X men can complete the work in 18 days, the total work W can be expressed as:
W=X×18
Step 3: Adjust for Absenteeism
Since 12 men were absent from the first day, the number of men actually working is X−12. These remaining men completed the work in 30 days. Therefore, the work done by these men can be expressed as:
W=(X−12)×30
Step 4: Set the Two Expressions for Work Equal
Since both expressions represent the same total work W, we can set them equal to each other:
X×18=(X−12)×30
Step 5: Expand and Rearrange the Equation
Expanding the right side:
18X=30X−360
Now, rearranging the equation to isolate X:
18X−30X=−360
−12X=−360
Step 6: Solve for X
Dividing both sides by -12:
X=36012=30
Conclusion
Thus, the number of men originally employed by the contractor is 30.
---
Let X be the number of men originally employed by the contractor.
The total work can be expressed in terms of men and days. If X men can complete the work in 18 days, the total work W can be expressed as:
W=X×18
Since 12 men were absent from the first day, the number of men actually working is X−12. These remaining men completed the work in 30 days. Therefore, the work done by these men can be expressed as:
W=(X−12)×30
Since both expressions represent the same total work W, we can set them equal to each other:
X×18=(X−12)×30
Expanding the right side:
18X=30X−360
Now, rearranging the equation to isolate X:
18X−30X=−360
−12X=−360
Dividing both sides by -12:
X=36012=30
Thus, the number of men originally employed by the contractor is 30.
Topper's Solved these Questions
- WORK AND TIME BOOK - ARIHANT SSCCHAPTER - WORK AND TIME EXERCISE - EXERCISE HIGHER SKILL LEVEL QUESTION
16 Videos
- WORK AND TIME BOOK - ARIHANT SSCCHAPTER - WORK AND TIME EXERCISE - EXERCISE HIGHER SKILL LEVEL QUESTION
16 Videos
- VOLUME AND SURFACE AREA BOOK - ARIHANT SSCCHAPTER - VOLUME AND SURFACE AREA EXERCISE - FAST TRACK PRACTICE
111 Videos
- WORK AND WAGES BOOK - ARIHANT SSCCHAPTER - WORK AND WAGES EXERCISE - EXERCISE (HIGHER SKILL LEVEL QUESTIONS)
7 Videos
Similar Questions
A certain number of men com plete a piece of work in 60 days. If there were 8 men more, the work can be finished in 10 days less. The number of men originally is:
View SolutionA certain number of men com plete a piece of work in 60 days. If there were 8 men more, the work can be finished in 10 days less. The number of men originally is:
View Solution
Knowledge Check
A contractor undertook to do a piece of work in 9 days. He employed certain number of laboures but 6 of them were absent from the very first day and the rest could finish the work in only 15 days. Find the number of men originally employed
A12B15C18D24A contractor undertook to do a piece of work in 9 days. He employed certain number of laboures but 6 of them were absent from the very first day and the rest could finish the work in only 15 days. Find the number of men originally employed
A15B6C13D9A contractor planned to finish work in 12 days and employed a certain number of men. However, 6 of them remained absent from the very first day. The rest could finish the work in 20 days. The number of men originally employed were:
एक ठेकेदार ने किसी कार्य को 12 दिनों में समाप्त करने की योजना बनाई और निश्चित संख्या में पुरुषों को काम पर लगाया | हालाँकि, इनमें से 6 पहले ही दिन से अनुपस्थिति रहे | शेष पुरुष इस कार्य को 20 दिनों में समाप्त कर सके |आरंभ में कितने पुरुषों को कार्य पर लगाया गया था ?A24B20C18D15
A certain numner of men agreed to do a work in 20 days. 5 men did come for work. Others completed the work in 40 days. Find the number of men who had agreed to do the work originally.
View SolutionA certain number of men complete a work in 45 days. If there were 5 men more, the work could be fin- ished in 9 days less How many men were originally there?
View SolutionA group of men decided to do a work in 10 days, but 5 of them become absent. if the rest of the group did the work in 12 days, find the original number of men?
View SolutionA certain number of men can do a plece of work in 60 days. If there were 6 men more, the work can be finished 20 days earlier. The number of men working is :
View Solution34 men can do a piece of work in 12 days . How many days will 51 men take to do it
View Solution