A contractor undertook to do a certain piece of work in 18 days. He employed certain number of men but 12 of them being absent from the very 1st day , the rest could finish the work in 30 days . Find the number of men originally employed .

A

40

B

15

C

45

D

30

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, we can follow these calculations:

Step 1: Define Variables
Let X be the number of men originally employed by the contractor.

Step 2: Work Done Calculation
The total work can be expressed in terms of men and days. If X men can complete the work in 18 days, the total work W can be expressed as:
W=X×18

Step 3: Adjust for Absenteeism
Since 12 men were absent from the first day, the number of men actually working is X12. These remaining men completed the work in 30 days. Therefore, the work done by these men can be expressed as:
W=(X12)×30

Step 4: Set the Two Expressions for Work Equal
Since both expressions represent the same total work W, we can set them equal to each other:
X×18=(X12)×30

Step 5: Expand and Rearrange the Equation
Expanding the right side:
18X=30X360
Now, rearranging the equation to isolate X:
18X30X=360
12X=360

Step 6: Solve for X
Dividing both sides by -12:
X=36012=30

Conclusion
Thus, the number of men originally employed by the contractor is 30.

---

Updated on:15/07/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A contractor undertook to do a piece of work in 9 days. He employed certain number of laboures but 6 of them were absent from the very first day and the rest could finish the work in only 15 days. Find the number of men originally employed

    A12
    B15
    C18
    D24
  • A contractor undertook to do a piece of work in 9 days. He employed certain number of laboures but 6 of them were absent from the very first day and the rest could finish the work in only 15 days. Find the number of men originally employed

    A15
    B6
    C13
    D9
  • A contractor planned to finish work in 12 days and employed a certain number of men. However, 6 of them remained absent from the very first day. The rest could finish the work in 20 days. The number of men originally employed were:
    एक ठेकेदार ने किसी कार्य को 12 दिनों में समाप्त करने की योजना बनाई और निश्चित संख्या में पुरुषों को काम पर लगाया | हालाँकि, इनमें से 6 पहले ही दिन से अनुपस्थिति रहे | शेष पुरुष इस कार्य को 20 दिनों में समाप्त कर सके |आरंभ में कितने पुरुषों को कार्य पर लगाया गया था ?

    A24
    B20
    C18
    D15