A contractor undertook to do a piece of work in 9 days. He employed certain number of laboures but 6 of them were absent from the very first day and the rest could finish the work in only 15 days. Find the number of men originally employed
15
6
13
9
The correct Answer is:A
To solve the problem step by step, we can follow these instructions:
Step 1: Define Variables
Let the total number of men originally employed be x.
Step 2: Calculate Total Work
The total work to be done can be expressed in terms of man-days. Since the contractor planned to complete the work in 9 days with x men, the total work is:
Total Work=x×9 man-days
Step 3: Adjust for Absenteeism
Since 6 men were absent from the very first day, the number of men actually working is:
Men working=x−6
Step 4: Calculate Work Done by Remaining Men
The remaining men, x−6, can complete the work in 15 days. Therefore, the total work done by these men can also be expressed as:
Total Work=(x−6)×15 man-days
Step 5: Set Equations Equal
Since both expressions represent the same total work, we can set them equal to each other:
x×9=(x−6)×15
Step 6: Expand and Rearrange the Equation
Expanding the right side gives:
9x=15x−90
Now, rearranging this equation:
90=15x−9x
90=6x
Step 7: Solve for x
Dividing both sides by 6 gives:
x=906=15
Conclusion
The number of men originally employed is 15.
---
Let the total number of men originally employed be x.
The total work to be done can be expressed in terms of man-days. Since the contractor planned to complete the work in 9 days with x men, the total work is:
Total Work=x×9 man-days
Since 6 men were absent from the very first day, the number of men actually working is:
Men working=x−6
The remaining men, x−6, can complete the work in 15 days. Therefore, the total work done by these men can also be expressed as:
Total Work=(x−6)×15 man-days
Since both expressions represent the same total work, we can set them equal to each other:
x×9=(x−6)×15
Expanding the right side gives:
9x=15x−90
Now, rearranging this equation:
90=15x−9x
90=6x
Dividing both sides by 6 gives:
x=906=15
The number of men originally employed is 15.
Topper's Solved these Questions
- TIME AND WORKBOOK - DISHA PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - Practice Exercise (Expert Level)
27 Videos
- TIME AND WORKBOOK - DISHA PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - Test Yourself
15 Videos
- TIME AND WORKBOOK - DISHA PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - Practice Exercise (Foundation Level)
51 Videos
- SET THEORYBOOK - DISHA PUBLICATIONCHAPTER - SET THEORYEXERCISE - Test Yourself
15 Videos
- TIME, SPEED AND DISTANCEBOOK - DISHA PUBLICATIONCHAPTER - TIME, SPEED AND DISTANCEEXERCISE - Test Yourself
15 Videos
Similar Questions
If 5 men do a piece of work in 28 days, then the number of persons required to do the same work in 7 days is
View SolutionIn a factory, 150 workers were engaged to finish a piece of work in a certain number of days. However, if 4 workers are dropped everyday, except the first day, it will take 8 more days to finish the work. Find the number of days in which the work was to be completed.
View Solution
Knowledge Check
A contractor undertook to do a piece of work in 9 days. He employed certain number of laboures but 6 of them were absent from the very first day and the rest could finish the work in only 15 days. Find the number of men originally employed
A12B15C18D24A contractor undertook to do a certain piece of work in 18 days. He employed certain number of men but 12 of them being absent from the very 1st day , the rest could finish the work in 30 days . Find the number of men originally employed .
A40B15C45D30A contractor planned to finish work in 12 days and employed a certain number of men. However, 6 of them remained absent from the very first day. The rest could finish the work in 20 days. The number of men originally employed were:
एक ठेकेदार ने किसी कार्य को 12 दिनों में समाप्त करने की योजना बनाई और निश्चित संख्या में पुरुषों को काम पर लगाया | हालाँकि, इनमें से 6 पहले ही दिन से अनुपस्थिति रहे | शेष पुरुष इस कार्य को 20 दिनों में समाप्त कर सके |आरंभ में कितने पुरुषों को कार्य पर लगाया गया था ?A24B20C18D15
A group of men decided to do a work in 10 days, but 5 of them become absent. if the rest of the group did the work in 12 days, find the original number of men?
View SolutionA certain number of men com plete a piece of work in 60 days. If there were 8 men more, the work can be finished in 10 days less. The number of men originally is:
View SolutionA contractor undertakes to complete a work in 20 days. He employs 30 labourers on this job. How many more labourers would he employ to complete the work in 15 days?
View SolutionA certain numner of men agreed to do a work in 20 days. 5 men did come for work. Others completed the work in 40 days. Find the number of men who had agreed to do the work originally.
View Solution150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped the second day, four more workers dropped the third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed.
View Solution