A contractor undertook to do a piece of work in 9 days. He employed certain number of laboures but 6 of them were absent from the very first day and the rest could finish the work in only 15 days. Find the number of men originally employed

A

15

B

6

C

13

D

9

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we can follow these instructions:

Step 1: Define Variables
Let the total number of men originally employed be x.

Step 2: Calculate Total Work
The total work to be done can be expressed in terms of man-days. Since the contractor planned to complete the work in 9 days with x men, the total work is:
Total Work=x×9 man-days

Step 3: Adjust for Absenteeism
Since 6 men were absent from the very first day, the number of men actually working is:
Men working=x6

Step 4: Calculate Work Done by Remaining Men
The remaining men, x6, can complete the work in 15 days. Therefore, the total work done by these men can also be expressed as:
Total Work=(x6)×15 man-days

Step 5: Set Equations Equal
Since both expressions represent the same total work, we can set them equal to each other:
x×9=(x6)×15

Step 6: Expand and Rearrange the Equation
Expanding the right side gives:
9x=15x90
Now, rearranging this equation:
90=15x9x
90=6x

Step 7: Solve for x
Dividing both sides by 6 gives:
x=906=15

Conclusion
The number of men originally employed is 15.

---

Updated on:8/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A contractor undertook to do a piece of work in 9 days. He employed certain number of laboures but 6 of them were absent from the very first day and the rest could finish the work in only 15 days. Find the number of men originally employed

    A12
    B15
    C18
    D24
  • A contractor undertook to do a certain piece of work in 18 days. He employed certain number of men but 12 of them being absent from the very 1st day , the rest could finish the work in 30 days . Find the number of men originally employed .

    A40
    B15
    C45
    D30
  • A contractor planned to finish work in 12 days and employed a certain number of men. However, 6 of them remained absent from the very first day. The rest could finish the work in 20 days. The number of men originally employed were:
    एक ठेकेदार ने किसी कार्य को 12 दिनों में समाप्त करने की योजना बनाई और निश्चित संख्या में पुरुषों को काम पर लगाया | हालाँकि, इनमें से 6 पहले ही दिन से अनुपस्थिति रहे | शेष पुरुष इस कार्य को 20 दिनों में समाप्त कर सके |आरंभ में कितने पुरुषों को कार्य पर लगाया गया था ?

    A24
    B20
    C18
    D15