After working for 8 days, Anil finds that only of the work has been done. He employs Rakesh who is 60% efficient as Anil. How many more days will Anil take to complete the job?
15 days
26.6 days
25 days
20 days
The correct Answer is:C
To solve the problem step by step, let's break it down clearly:
Step 1: Determine the total work done by Anil in 8 days.
Anil has completed 13 of the work in 8 days.
Step 2: Calculate the total work.
If 13 of the work is done in 8 days, then the total work (W) can be calculated as:
W=8 days×3=24 days
This means Anil would take 24 days to complete the entire work alone.
Step 3: Calculate Anil's daily work efficiency.
Anil’s efficiency can be determined as:
Efficiency of Anil=WTotal days=124 of the work per day
Step 4: Determine the remaining work.
Since 13 of the work is done, the remaining work is:
Remaining work=1−13=23
Step 5: Calculate Rakesh's efficiency.
Rakesh is 60% as efficient as Anil. Therefore, Rakesh's efficiency is:
Efficiency of Rakesh=0.6×124=0.624=140 of the work per day
Step 6: Calculate the total work done by Anil and Rakesh together.
Now, Anil and Rakesh will work together to complete the remaining work. Their combined efficiency is:
Combined efficiency=Efficiency of Anil+Efficiency of Rakesh=124+140
To add these fractions, find a common denominator (which is 120):
124=5120,140=3120
Thus,
Combined efficiency=5120+3120=8120=115 of the work per day
Step 7: Calculate the time taken to complete the remaining work.
To find out how many days it will take to finish the remaining 23 of the work, we can use the formula:
Time=Remaining workCombined efficiency=23115=23×15=10 days
Conclusion:
Anil will take 10 more days to complete the job with Rakesh's help.
---
Anil has completed 13 of the work in 8 days.
If 13 of the work is done in 8 days, then the total work (W) can be calculated as:
W=8 days×3=24 days
This means Anil would take 24 days to complete the entire work alone.
Anil’s efficiency can be determined as:
Efficiency of Anil=WTotal days=124 of the work per day
Since 13 of the work is done, the remaining work is:
Remaining work=1−13=23
Rakesh is 60% as efficient as Anil. Therefore, Rakesh's efficiency is:
Efficiency of Rakesh=0.6×124=0.624=140 of the work per day
Now, Anil and Rakesh will work together to complete the remaining work. Their combined efficiency is:
Combined efficiency=Efficiency of Anil+Efficiency of Rakesh=124+140
To add these fractions, find a common denominator (which is 120):
124=5120,140=3120
Thus,
Combined efficiency=5120+3120=8120=115 of the work per day
To find out how many days it will take to finish the remaining 23 of the work, we can use the formula:
Time=Remaining workCombined efficiency=23115=23×15=10 days
Anil will take 10 more days to complete the job with Rakesh's help.
Topper's Solved these Questions
- TIME AND WORKBOOK - DISHA PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - Practice Exercise (Expert Level)
27 Videos
- TIME AND WORKBOOK - DISHA PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - Test Yourself
15 Videos
- TIME AND WORKBOOK - DISHA PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - Practice Exercise (Foundation Level)
51 Videos
- SET THEORYBOOK - DISHA PUBLICATIONCHAPTER - SET THEORYEXERCISE - Test Yourself
15 Videos
- TIME, SPEED AND DISTANCEBOOK - DISHA PUBLICATIONCHAPTER - TIME, SPEED AND DISTANCEEXERCISE - Test Yourself
15 Videos
Similar Questions
Knowledge Check
A can complete a piece of work in 12 days. B is 60% more efficient than A. The number of days, that B will take to complete the same work, is
A6B712C8D812A can do a piece of work in 40 days. B does the same work with 60% more efficiency. How many days will B take to complete the work alone?
A30 daysB18 daysC15 daysD25 daysA is twice as efficient as B and together they finish a piece of work in 18 days. How many days will A take to complete the work alone?
A27B24C36D42
A can complete a piece of work in 12 days. B is 60% more efficient than A. The number of days, that B will take to complete the same work, is
View SolutionA man completes 5/8 of a job in 10 days. At this rate, how many more days will it take him to finish the job?
View SolutionShantanu completes 5/8 of a job in 20 days. At this rate, how many more days will he take to finish the job ?
View SolutionA man completes 58 of a job in 10 days. At this rate, how many more days will it take him to finish the job? 5 b. 6 c. 7 d. 712
View SolutionA contractor undertakes to complete a work in 20 days. He employs 30 labourers on this job. How many more labourers would he employ to complete the work in 15 days?
View Solution