After working for 8 days, Anil finds that only 1 3 of the work has been done. He employs Rakesh who is 60% efficient as Anil. How many more days will Anil take to complete the job?

A

15 days

B

26.6 days

C

25 days

D

20 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, let's break it down clearly:

Step 1: Determine the total work done by Anil in 8 days.
Anil has completed 13 of the work in 8 days.

Step 2: Calculate the total work.
If 13 of the work is done in 8 days, then the total work (W) can be calculated as:
W=8 days×3=24 days
This means Anil would take 24 days to complete the entire work alone.

Step 3: Calculate Anil's daily work efficiency.
Anil’s efficiency can be determined as:
Efficiency of Anil=WTotal days=124 of the work per day

Step 4: Determine the remaining work.
Since 13 of the work is done, the remaining work is:
Remaining work=113=23

Step 5: Calculate Rakesh's efficiency.
Rakesh is 60% as efficient as Anil. Therefore, Rakesh's efficiency is:
Efficiency of Rakesh=0.6×124=0.624=140 of the work per day

Step 6: Calculate the total work done by Anil and Rakesh together.
Now, Anil and Rakesh will work together to complete the remaining work. Their combined efficiency is:
Combined efficiency=Efficiency of Anil+Efficiency of Rakesh=124+140
To add these fractions, find a common denominator (which is 120):
124=5120,140=3120
Thus,
Combined efficiency=5120+3120=8120=115 of the work per day

Step 7: Calculate the time taken to complete the remaining work.
To find out how many days it will take to finish the remaining 23 of the work, we can use the formula:
Time=Remaining workCombined efficiency=23115=23×15=10 days

Conclusion:
Anil will take 10 more days to complete the job with Rakesh's help.

---

Updated on:8/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A can complete a piece of work in 12 days. B is 60% more efficient than A. The number of days, that B will take to complete the same work, is

    A6
    B712
    C8
    D812
  • A can do a piece of work in 40 days. B does the same work with 60% more efficiency. How many days will B take to complete the work alone?

    A30 days
    B18 days
    C15 days
    D25 days
  • A is twice as efficient as B and together they finish a piece of work in 18 days. How many days will A take to complete the work alone?

    A27
    B24
    C36
    D42