In a factory, 150 workers were engaged to finish a piece of work in a certain number of days. However, if 4 workers are dropped everyday, except the first day, it will take 8 more days to finish the work. Find the number of days in which the work was to be completed.

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem, we need to find the number of days (N) required to complete the work with 150 workers, considering that 4 workers are dropped every day after the first day, which results in an additional 8 days to complete the work.

1. Define Variables:
Let N be the original number of days required to complete the work with 150 workers.

2. Calculate Total Work:
The total work done can be expressed as:
Total Work=Number of Workers×Number of Days=150×N

3. Work Done with Dropping Workers:
If 4 workers are dropped every day after the first day, the number of workers on each day will be:
- Day 1: 150 workers
- Day 2: 146 workers
- Day 3: 142 workers
- ...
- Day N: 1504(N1) workers

The number of workers on the k-th day can be expressed as:
Workers on Day k=1504(k1)

4. Total Work with Dropping Workers:
The total work done when dropping 4 workers every day (except the first day) over N+8 days is:
Total Work=150+146+142++(1504(N1))
This is an arithmetic series where:
- First term a=150
- Last term l=1504(N1)=1544N
- Number of terms =N

The sum of an arithmetic series is given by:
S=n2×(a+l)
Therefore, the total work can be expressed as:
Total Work=N2×(150+(1544N))=N2×(3044N)

5. Set Up the Equation:
Since both expressions for total work are equal, we can set them equal to each other:
150N=N2×(3044N)

6. Simplify the Equation:
Multiply both sides by 2 to eliminate the fraction:
300N=N(3044N)
Expanding the right side gives:
300N=304N4N2
Rearranging the equation:
4N24N0=0
Simplifying further:
N2N600=0

7. Solve the Quadratic Equation:
Using the quadratic formula N=b±b24ac2a:
N=(1)±(1)24×1×(600)2×1
N=1±1+24002
N=1±24012
N=1±492
This gives us two possible solutions:
N=502=25orN=482=24
Since the number of days cannot be negative, we have:
N=25

8. Conclusion:
The original number of days required to complete the work is 25 days.

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • 150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped the second day, four more workers dropped the third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed.

    A24 days
    B40 days
    C17 days
    D25 days
  • A contractor planned to finish work in 12 days and employed a certain number of men. However, 6 of them remained absent from the very first day. The rest could finish the work in 20 days. The number of men originally employed were:
    एक ठेकेदार ने किसी कार्य को 12 दिनों में समाप्त करने की योजना बनाई और निश्चित संख्या में पुरुषों को काम पर लगाया | हालाँकि, इनमें से 6 पहले ही दिन से अनुपस्थिति रहे | शेष पुरुष इस कार्य को 20 दिनों में समाप्त कर सके |आरंभ में कितने पुरुषों को कार्य पर लगाया गया था ?

    A24
    B20
    C18
    D15
  • 15 men can finish a piece of work in 40 days. The number of days after which 5 men should leave the work so that the work is finished in 45 days altogether is:

    A10
    B20
    C30
    D35