A and B working together can do a piece of work in 24 days, B and C working together can do the same piece of work in 15 days and A and C working together can do the same piece of work in 20 days. They all worked together for 6 days and then A and C leaves the work. How many days will B take to finish the remaining work?

A

A)15 days

B

B)8 days

C

C)12 days

D

D)18 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, let's break down the information given and calculate accordingly.

Step 1: Determine the work done by A, B, and C
We know:
- A and B together can complete the work in 24 days.
- B and C together can complete the work in 15 days.
- A and C together can complete the work in 20 days.

Let the total work be represented as 120 units (this is a convenient LCM of the denominators).

Step 2: Calculate the efficiencies of A, B, and C
1. Efficiency of A and B:
Work done by A and B in 1 day=12024=5 units

2. Efficiency of B and C:
Work done by B and C in 1 day=12015=8 units

3. Efficiency of A and C:
Work done by A and C in 1 day=12020=6 units

Step 3: Set up equations to find individual efficiencies
Let:
- Efficiency of A = a
- Efficiency of B = b
- Efficiency of C = c

From the above calculations, we can set up the following equations:
1. a+b=5 (1)
2. b+c=8 (2)
3. a+c=6 (3)

Step 4: Solve the equations
To find the values of a, b, and c, we can manipulate these equations.

From equation (1):
b=5a(4)

Substituting (4) into equation (2):
(5a)+c=8c=85+ac=3+a(5)

Now substituting (4) and (5) into equation (3):
a+(3+a)=62a+3=62a=3a=1.5

Now substituting a back to find b and c:
From (4):
b=51.5=3.5
From (5):
c=3+1.5=4.5

So, we have:
- Efficiency of A = 1.5 units/day
- Efficiency of B = 3.5 units/day
- Efficiency of C = 4.5 units/day

Step 5: Calculate the total work done in 6 days
Now, when A, B, and C work together for 6 days:
Total efficiency of A, B, and C=a+b+c=1.5+3.5+4.5=9.5 units/day
Work done in 6 days=9.5×6=57 units

Step 6: Calculate the remaining work
Total work is 120 units, so the remaining work after 6 days is:
Remaining work=12057=63 units

Step 7: Calculate how long B will take to finish the remaining work
After A and C leave, only B continues to work. The efficiency of B is 3.5 units/day.
Time taken by B to finish remaining work=Remaining workEfficiency of B=633.5=18 days

Final Answer
B will take 18 days to finish the remaining work.

---

Updated on:8/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A and B together can do a piece of work in 5 days and A alone can do it in 8 days. B alone can do the same piece of work in:

    A1113 days
    B1313 days
    C1645 days
    D1235 days
  • A and B can do a piece of work in 30 days, while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work ? 18 days b.  24 days c. 30 days d. 36 days

    A18 days
    B24 days
    C30 days
    D36 days
  • A and B can do a piece of work in 30 days while B and C can do the same work in 24 days and and A in 20 days. They all work together for 10 days when B and Cleave. How many days more will A take to finish the work ?

    A18 days
    B24 days
    C30 days
    D36 days