A and B working together can do a piece of work in 24 days, B and C working together can do the same piece of work in 15 days and A and C working together can do the same piece of work in 20 days. They all worked together for 6 days and then A and C leaves the work. How many days will B take to finish the remaining work?
A)15 days
B)8 days
C)12 days
D)18 days
To solve the problem step by step, let's break down the information given and calculate accordingly.
Step 1: Determine the work done by A, B, and C
We know:
- A and B together can complete the work in 24 days.
- B and C together can complete the work in 15 days.
- A and C together can complete the work in 20 days.
Let the total work be represented as 120 units (this is a convenient LCM of the denominators).
Step 2: Calculate the efficiencies of A, B, and C
1. Efficiency of A and B:
Work done by A and B in 1 day=12024=5 units
2. Efficiency of B and C:
Work done by B and C in 1 day=12015=8 units
3. Efficiency of A and C:
Work done by A and C in 1 day=12020=6 units
Step 3: Set up equations to find individual efficiencies
Let:
- Efficiency of A = a
- Efficiency of B = b
- Efficiency of C = c
From the above calculations, we can set up the following equations:
1. a+b=5 (1)
2. b+c=8 (2)
3. a+c=6 (3)
Step 4: Solve the equations
To find the values of a, b, and c, we can manipulate these equations.
From equation (1):
b=5−a(4)
Substituting (4) into equation (2):
(5−a)+c=8⟹c=8−5+a⟹c=3+a(5)
Now substituting (4) and (5) into equation (3):
a+(3+a)=6⟹2a+3=6⟹2a=3⟹a=1.5
Now substituting a back to find b and c:
From (4):
b=5−1.5=3.5
From (5):
c=3+1.5=4.5
So, we have:
- Efficiency of A = 1.5 units/day
- Efficiency of B = 3.5 units/day
- Efficiency of C = 4.5 units/day
Step 5: Calculate the total work done in 6 days
Now, when A, B, and C work together for 6 days:
Total efficiency of A, B, and C=a+b+c=1.5+3.5+4.5=9.5 units/day
Work done in 6 days=9.5×6=57 units
Step 6: Calculate the remaining work
Total work is 120 units, so the remaining work after 6 days is:
Remaining work=120−57=63 units
Step 7: Calculate how long B will take to finish the remaining work
After A and C leave, only B continues to work. The efficiency of B is 3.5 units/day.
Time taken by B to finish remaining work=Remaining workEfficiency of B=633.5=18 days
Final Answer
B will take 18 days to finish the remaining work.
---
We know:
- A and B together can complete the work in 24 days.
- B and C together can complete the work in 15 days.
- A and C together can complete the work in 20 days.
1. Efficiency of A and B:
Work done by A and B in 1 day=12024=5 units
Work done by B and C in 1 day=12015=8 units
Work done by A and C in 1 day=12020=6 units
Let:
- Efficiency of A = a
- Efficiency of B = b
- Efficiency of C = c
1. a+b=5 (1)
2. b+c=8 (2)
3. a+c=6 (3)
To find the values of a, b, and c, we can manipulate these equations.
b=5−a(4)
(5−a)+c=8⟹c=8−5+a⟹c=3+a(5)
a+(3+a)=6⟹2a+3=6⟹2a=3⟹a=1.5
From (4):
b=5−1.5=3.5
From (5):
c=3+1.5=4.5
- Efficiency of A = 1.5 units/day
- Efficiency of B = 3.5 units/day
- Efficiency of C = 4.5 units/day
Now, when A, B, and C work together for 6 days:
Total efficiency of A, B, and C=a+b+c=1.5+3.5+4.5=9.5 units/day
Work done in 6 days=9.5×6=57 units
Total work is 120 units, so the remaining work after 6 days is:
Remaining work=120−57=63 units
After A and C leave, only B continues to work. The efficiency of B is 3.5 units/day.
Time taken by B to finish remaining work=Remaining workEfficiency of B=633.5=18 days
B will take 18 days to finish the remaining work.
Topper's Solved these Questions
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - MAINS QUESTIONS
55 Videos
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PREVIOUS YEAR QUESTIONS
32 Videos
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 1)
40 Videos
- SPEED, TIME AND DISTANCEBOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions
31 Videos
Similar Questions
A can do a piece of work in 25 days and B can finish it in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the remaining work ?
View SolutionA and B do a piece of work in 20 days and B in 15 days. They work together for 2 days and then A goes away. In how many days will B finish the remaining work?
View Solution
Knowledge Check
A and B together can do a piece of work in 5 days and A alone can do it in 8 days. B alone can do the same piece of work in:
A1113 daysB1313 daysC1645 daysD1235 daysA and B can do a piece of work in 30 days, while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work ? 18 days b. 24 days c. 30 days d. 36 days
A18 daysB24 daysC30 daysD36 daysA and B can do a piece of work in 30 days while B and C can do the same work in 24 days and and A in 20 days. They all work together for 10 days when B and Cleave. How many days more will A take to finish the work ?
A18 daysB24 daysC30 daysD36 days
A and B together can do a piece of work in 12 days. While B and C together can do a piece of work in 8 days. C and A together can do a piece of work in 6 days. In how many days will this work be completed by B alone?
View SolutionA and B together can do a piece of work in 12 days; B and C can do it in 20 days while C and A can do it in 15 days. A, B and C all working together can do it in
View SolutionA can do a piece of work in 12 days and B in 15 days. They work together for 5 days and then B left. The days taken by A to finish the remaining work is
View SolutionA and B together can do a piece of work in 4 days and A alone can do it in 6 days, B alone can do the same work in :
View SolutionA can do a work in 25 days and B can do the same work in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the work?
View Solution