The efficiency of A is 40% more than that of B and efficiency of C is 1427% less than that of A. Time taken by A and B together to complete the work is 11 days. Find the number of days taken by all of them to complete the thrice of the same work, working simultaneously.

A

A)13 days

B

B)22 days

C

C)11 days

D

D)26 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we will first determine the efficiencies of A, B, and C based on the information provided, then calculate the total work done, and finally find out how long it will take for A, B, and C to complete three times that work together.

Step 1: Determine the efficiencies of A, B, and C

Let the efficiency of B be x.
Then, the efficiency of A, which is 40% more than B, can be calculated as:
Efficiency of A=x+0.4x=1.4x

Next, we need to find the efficiency of C. The efficiency of C is given as 1427% less than that of A.
First, convert 1427% to a fraction:
1427%=1007%
This means C's efficiency is:
Efficiency of C=Efficiency of A(1007×Efficiency of A100)
=1.4x1.4x7=1.4x(117)=1.4x×67=8.4x7

Thus, we have:
- Efficiency of A = 1.4x
- Efficiency of B = x
- Efficiency of C = 8.4x7

Step 2: Calculate the combined efficiency of A and B

The combined efficiency of A and B is:
Efficiency of A + B=1.4x+x=2.4x

Step 3: Calculate the total work done by A and B in 11 days

According to the problem, A and B together take 11 days to complete the work. Therefore, the total work can be calculated as:
Total Work=Efficiency of A + B×Time=2.4x×11=26.4x

Step 4: Calculate the total work for three times the work

Now, we need to find the time taken by A, B, and C to complete three times the work:
Total Work for 3 times=3×26.4x=79.2x

Step 5: Calculate the combined efficiency of A, B, and C

The combined efficiency of A, B, and C is:
Efficiency of A + B + C=1.4x+x+8.4x7
To combine these, we can convert 1.4x and x into fractions with a common denominator of 7:
1.4x=9.8x7,x=7x7
Thus,
Efficiency of A + B + C=9.8x7+7x7+8.4x7=25.2x7

Step 6: Calculate the time taken by A, B, and C to complete the work

Now, we can find the time taken by A, B, and C to complete the total work of 79.2x:
Time=Total WorkEfficiency of A + B + C=79.2x25.2x7=79.2x×725.2x
The x cancels out:
=79.2×725.2=554.425.2=22 days

Final Answer
The time taken by A, B, and C to complete thrice the work together is 22 days.

---

Updated on:8/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A is thrice as efficient as B.A and B cam complete a piece of work in 12 days. Find the number of days in which A alone complete it.

    A48
    B16
    C20
    D32
  • B is twice efficient than A and the total time taken to complete the work by both A and B together is 22 days. Find the number of days taken by B to complete the work alone.

    A11 days
    B44 days
    C33 days
    D30 days
  • If a work can be completed by A in 30 days and by B in 60 days. Then, the number of days taken by them to complete the work, working together is

    A25 days
    B45 days
    C50 days
    D20 days