The efficiency of A is 40% more than that of B and efficiency of C is 1427% less than that of A. Time taken by A and B together to complete the work is 11 days. Find the number of days taken by all of them to complete the thrice of the same work, working simultaneously.
A)13 days
B)22 days
C)11 days
D)26 days
The correct Answer is:B
To solve the problem step by step, we will first determine the efficiencies of A, B, and C based on the information provided, then calculate the total work done, and finally find out how long it will take for A, B, and C to complete three times that work together.
Step 1: Determine the efficiencies of A, B, and C
Let the efficiency of B be x.
Then, the efficiency of A, which is 40% more than B, can be calculated as:
Efficiency of A=x+0.4x=1.4x
Next, we need to find the efficiency of C. The efficiency of C is given as 1427% less than that of A.
First, convert 1427% to a fraction:
1427%=1007%
This means C's efficiency is:
Efficiency of C=Efficiency of A−(1007×Efficiency of A100)
=1.4x−1.4x7=1.4x(1−17)=1.4x×67=8.4x7
Thus, we have:
- Efficiency of A = 1.4x
- Efficiency of B = x
- Efficiency of C = 8.4x7
Step 2: Calculate the combined efficiency of A and B
The combined efficiency of A and B is:
Efficiency of A + B=1.4x+x=2.4x
Step 3: Calculate the total work done by A and B in 11 days
According to the problem, A and B together take 11 days to complete the work. Therefore, the total work can be calculated as:
Total Work=Efficiency of A + B×Time=2.4x×11=26.4x
Step 4: Calculate the total work for three times the work
Now, we need to find the time taken by A, B, and C to complete three times the work:
Total Work for 3 times=3×26.4x=79.2x
Step 5: Calculate the combined efficiency of A, B, and C
The combined efficiency of A, B, and C is:
Efficiency of A + B + C=1.4x+x+8.4x7
To combine these, we can convert 1.4x and x into fractions with a common denominator of 7:
1.4x=9.8x7,x=7x7
Thus,
Efficiency of A + B + C=9.8x7+7x7+8.4x7=25.2x7
Step 6: Calculate the time taken by A, B, and C to complete the work
Now, we can find the time taken by A, B, and C to complete the total work of 79.2x:
Time=Total WorkEfficiency of A + B + C=79.2x25.2x7=79.2x×725.2x
The x cancels out:
=79.2×725.2=554.425.2=22 days
Final Answer
The time taken by A, B, and C to complete thrice the work together is 22 days.
---
Then, the efficiency of A, which is 40% more than B, can be calculated as:
Efficiency of A=x+0.4x=1.4x
First, convert 1427% to a fraction:
1427%=1007%
This means C's efficiency is:
Efficiency of C=Efficiency of A−(1007×Efficiency of A100)
=1.4x−1.4x7=1.4x(1−17)=1.4x×67=8.4x7
- Efficiency of A = 1.4x
- Efficiency of B = x
- Efficiency of C = 8.4x7
Efficiency of A + B=1.4x+x=2.4x
Total Work=Efficiency of A + B×Time=2.4x×11=26.4x
Total Work for 3 times=3×26.4x=79.2x
Efficiency of A + B + C=1.4x+x+8.4x7
To combine these, we can convert 1.4x and x into fractions with a common denominator of 7:
1.4x=9.8x7,x=7x7
Thus,
Efficiency of A + B + C=9.8x7+7x7+8.4x7=25.2x7
Time=Total WorkEfficiency of A + B + C=79.2x25.2x7=79.2x×725.2x
The x cancels out:
=79.2×725.2=554.425.2=22 days
The time taken by A, B, and C to complete thrice the work together is 22 days.
Topper's Solved these Questions
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - MAINS QUESTIONS
55 Videos
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PREVIOUS YEAR QUESTIONS
32 Videos
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 1)
40 Videos
- SPEED, TIME AND DISTANCEBOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions
31 Videos
Similar Questions
Knowledge Check
A is thrice as efficient as B.A and B cam complete a piece of work in 12 days. Find the number of days in which A alone complete it.
A48B16C20D32B is twice efficient than A and the total time taken to complete the work by both A and B together is 22 days. Find the number of days taken by B to complete the work alone.
A11 daysB44 daysC33 daysD30 daysIf a work can be completed by A in 30 days and by B in 60 days. Then, the number of days taken by them to complete the work, working together is
A25 daysB45 daysC50 daysD20 days
A is thrice as efficient as B and hence completes a work in 40 days less than the number of days taken by B. What will be the number of days taken by both of them when working together?
View SolutionIf a work can be completed by A in 30 days and by B in 60 days. Then, the number of days taken by them to complete the work, working together is
View SolutionA can complete a work in 12 days and B can complete the same work in 24 days. Find the time taken by both A and B together to complete the work.
View SolutionThe efficiency of A is thrice as that of B and efficiency of B is twice as that of C. If B alone can finish a work in 15 days, in how many days A and C together will complete that work?
View SolutionThe efficiency of A is thrice as that of B and efficiency of B is twice as that of C. If B alone can finish a work in 15 days, in how many days A and C together will complete that work?
View Solution