A does 6623% of work in 8 days and is replaced by B and B completes the remaining work. If whole work is completed in 14 days, then find difference of days taken by A and B alone to complete the work.

A

A)3 days

B

B)5 days

C

C)6 days

D

D)2 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:C

|
Answer

Step by step video, text & image solution for A does 66(2)/(3)% of work in 8 days and is replaced by B and B completes the remaining work. If whole work is completed in 14 days, then find difference of days taken by A and B alone to complete the work. by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can do a piece of work in 15 days and B is 25% more efficient than A. If A and B both work for 4 days and after 4 days C can complete the remaining work alone in 8 days, then find time taken by A, B and C together to complete the whole work.

    A6 days
    B5 days
    C8 days
    D10 days
  • Question 2 - Select One

    A can complete a work in 12 days and B can complete the same work in 24 days. Find the time taken by both A and B together to complete the work.

    A8 days
    B10 days
    C6 days
    D9 days
  • Question 3 - Select One

    Working together A, B and C can complete a piece of work in 24 days. After working together for 4 days. C left the work. A and B completed the remaining work in 30 days. The number of days taken by C alone to complete the same work is:

    A60
    B54
    C72
    D90