7 men and 6 women together can complete a piece of work in 8 days and work done by a woman in one day is half the work done by a man in one day. If 8 men and 4 women started working and after 3 days 4 men left the work and 4 new women joined then, in how many more days will the work be completed.
A)7 days
B)6 days
C)5.25 days
D)6.25 days
The correct Answer is:D
To solve the problem step by step, let's break it down clearly:
Step 1: Determine the Work Done by Men and Women
Let the work done by one man in one day be m and the work done by one woman in one day be w. According to the problem, the work done by a woman in one day is half the work done by a man in one day. Therefore, we can express this as:
w=12m
Step 2: Calculate Total Work
We know that 7 men and 6 women can complete the work in 8 days. The total work can be calculated as:
Total Work=(Number of Workers)×(Efficiency)×(Time)
Thus,
Total Work=(7m+6w)×8
Substituting w in terms of m:
Total Work=(7m+6⋅12m)×8=(7m+3m)×8=10m×8=80m
So, the total work is 80m.
Step 3: Work Done by 8 Men and 4 Women in 3 Days
Next, we calculate how much work is done by 8 men and 4 women in 3 days:
Work Done=(8m+4w)×3
Substituting w:
Work Done=(8m+4⋅12m)×3=(8m+2m)×3=10m×3=30m
Step 4: Remaining Work After 3 Days
Now, we find the remaining work after 3 days:
Remaining Work=Total Work−Work Done=80m−30m=50m
Step 5: Work Done After 4 Men Leave and 4 Women Join
After 3 days, 4 men leave and 4 new women join. The new workforce consists of 4 men and 8 women. We calculate their combined work in one day:
New Work Rate=(4m+8w)=(4m+8⋅12m)=(4m+4m)=8m
Step 6: Calculate Days to Complete Remaining Work
Let t be the number of days required to complete the remaining work of 50m:
Remaining Work=New Work Rate×t
Thus,
50m=8m×t
Solving for t:
t=50m8m=508=6.25 days
Final Answer
The work will be completed in 6.25 days after the changes in workforce.
---
Let the work done by one man in one day be m and the work done by one woman in one day be w. According to the problem, the work done by a woman in one day is half the work done by a man in one day. Therefore, we can express this as:
w=12m
We know that 7 men and 6 women can complete the work in 8 days. The total work can be calculated as:
Total Work=(Number of Workers)×(Efficiency)×(Time)
Thus,
Total Work=(7m+6w)×8
Substituting w in terms of m:
Total Work=(7m+6⋅12m)×8=(7m+3m)×8=10m×8=80m
So, the total work is 80m.
Next, we calculate how much work is done by 8 men and 4 women in 3 days:
Work Done=(8m+4w)×3
Substituting w:
Work Done=(8m+4⋅12m)×3=(8m+2m)×3=10m×3=30m
Now, we find the remaining work after 3 days:
Remaining Work=Total Work−Work Done=80m−30m=50m
After 3 days, 4 men leave and 4 new women join. The new workforce consists of 4 men and 8 women. We calculate their combined work in one day:
New Work Rate=(4m+8w)=(4m+8⋅12m)=(4m+4m)=8m
Let t be the number of days required to complete the remaining work of 50m:
Remaining Work=New Work Rate×t
Thus,
50m=8m×t
Solving for t:
t=50m8m=508=6.25 days
The work will be completed in 6.25 days after the changes in workforce.
Topper's Solved these Questions
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - MAINS QUESTIONS
55 Videos
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PREVIOUS YEAR QUESTIONS
32 Videos
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 1)
40 Videos
- SPEED, TIME AND DISTANCEBOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions
31 Videos
Similar Questions
Three men or five women can complete a piece of work in 8 days. In how many days can 6 men and 6 women complete it?
View Solution8 men and 4 woment together can complete a piece ot work in 6 days. Work done by a man in one day is double the work done by a women in one day 8 men and 4 women started working and after 2 days, 4 men left and 4 new women joined the work.
Quantity I: more days required to complete the work
II: 5 days
View Solution
Knowledge Check
8 men and 5 women together can complete a piece of work in 7 days and work done by a women in one day is half the work done by a man in one day. If 9 men and 3 women started working and after 4 days 4 men left the work and 4 new women joined then, in how many many more days will the work be completed
A7 daysB6 daysC5.25 daysD3.7 days8 men and 4 women together can complete a piece of work in
6 days. The work done by a man in one day is diuble the
work done by a woman in one day. If 8 men and 4 women
started working and after 2 days 4 men left and 4 new women
joined, in how many more days will the work be complete?A5 daysB8 daysC6 daysD4 days8 men and 4 women together can complete a piece of work in 6 days. Work done by a man in one day is double the work done by a woman in one day. If 8 men and 4 women started working and after 2 days, 4 men left and 4 new women joined, in how many more days will the work be completed?
A5 daysB8 daysC6 daysD4 days
10 men and 8 women can together complete a work in 5 days. Work done by a woman is equal to the half of the work done by a man. In how many days, will 4 men and 6 women complete that work ?
View Solution10 men and 8 women together can complete a work in 5 days. Work done by one woman in a day is equal to half the work done by a man in 1 day. How many days will it take for 4 men and 6 women to complete that work?
View Solution2 men and 3 women together or 4 men together can complete a piece of work in 20 days.3 men and 3 women will complete the same work in :
View Solution16 women take 12 days to complete a work which can be completed by 12 men in 8 days. 16 men started working and after 3 days 10 men left 4 women joined them. How many days will they take to complete the remaining work?
View Solution16 women take 12 days to complete a work which can be completed by 12 men in 8 days. 16 men started working and after 3 days 10 men left 4 women joined them. How many days will they take to complete the remaining work?
View Solution