7 men and 6 women together can complete a piece of work in 8 days and work done by a woman in one day is half the work done by a man in one day. If 8 men and 4 women started working and after 3 days 4 men left the work and 4 new women joined then, in how many more days will the work be completed.

A

A)7 days

B

B)6 days

C

C)5.25 days

D

D)6.25 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, let's break it down clearly:

Step 1: Determine the Work Done by Men and Women
Let the work done by one man in one day be m and the work done by one woman in one day be w. According to the problem, the work done by a woman in one day is half the work done by a man in one day. Therefore, we can express this as:
w=12m

Step 2: Calculate Total Work
We know that 7 men and 6 women can complete the work in 8 days. The total work can be calculated as:
Total Work=(Number of Workers)×(Efficiency)×(Time)
Thus,
Total Work=(7m+6w)×8
Substituting w in terms of m:
Total Work=(7m+612m)×8=(7m+3m)×8=10m×8=80m
So, the total work is 80m.

Step 3: Work Done by 8 Men and 4 Women in 3 Days
Next, we calculate how much work is done by 8 men and 4 women in 3 days:
Work Done=(8m+4w)×3
Substituting w:
Work Done=(8m+412m)×3=(8m+2m)×3=10m×3=30m

Step 4: Remaining Work After 3 Days
Now, we find the remaining work after 3 days:
Remaining Work=Total WorkWork Done=80m30m=50m

Step 5: Work Done After 4 Men Leave and 4 Women Join
After 3 days, 4 men leave and 4 new women join. The new workforce consists of 4 men and 8 women. We calculate their combined work in one day:
New Work Rate=(4m+8w)=(4m+812m)=(4m+4m)=8m

Step 6: Calculate Days to Complete Remaining Work
Let t be the number of days required to complete the remaining work of 50m:
Remaining Work=New Work Rate×t
Thus,
50m=8m×t
Solving for t:
t=50m8m=508=6.25 days

Final Answer
The work will be completed in 6.25 days after the changes in workforce.

---

Updated on:8/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • 8 men and 5 women together can complete a piece of work in 7 days and work done by a women in one day is half the work done by a man in one day. If 9 men and 3 women started working and after 4 days 4 men left the work and 4 new women joined then, in how many many more days will the work be completed

    A7 days
    B6 days
    C5.25 days
    D3.7 days
  • 8 men and 4 women together can complete a piece of work in
    6 days. The work done by a man in one day is diuble the
    work done by a woman in one day. If 8 men and 4 women
    started working and after 2 days 4 men left and 4 new women
    joined, in how many more days will the work be complete?

    A5 days
    B8 days
    C6 days
    D4 days
  • 8 men and 4 women together can complete a piece of work in 6 days. Work done by a man in one day is double the work done by a woman in one day. If 8 men and 4 women started working and after 2 days, 4 men left and 4 new women joined, in how many more days will the work be completed?

    A5 days
    B8 days
    C6 days
    D4 days