A, B and C can do a piece of work in 20 days, 10 days and 15 days respectively. They all started the work together but after 2 days B left the work and A left the work 1.5 days before the completion of work. Find the time in which work gets completed.

A

A)7.5 days

B

B)623days

C

C)8 days

D

D)6.5 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we will calculate the total work done by A, B, and C, and determine how long it takes to complete the work given the conditions stated in the question.

Step 1: Determine the work rates of A, B, and C
- A can complete the work in 20 days, so A's work rate is:
Work rate of A=120 work/day
- B can complete the work in 10 days, so B's work rate is:
Work rate of B=110 work/day
- C can complete the work in 15 days, so C's work rate is:
Work rate of C=115 work/day

Step 2: Calculate the combined work rate of A, B, and C
To find their combined work rate, we add their individual work rates:
Combined work rate=120+110+115
To add these fractions, we find a common denominator, which is 60:
120=360,110=660,115=460
Thus,
Combined work rate=360+660+460=1360 work/day

Step 3: Calculate the work done in the first 2 days
In the first 2 days, A, B, and C work together:
Work done in 2 days=2×1360=2660=1330 of the work

Step 4: Determine the remaining work
The total work is considered as 1 (whole work), so the remaining work after 2 days is:
Remaining work=11330=301330=1730

Step 5: Calculate the work rate after B leaves
After 2 days, B leaves, so only A and C continue working. Their combined work rate is:
Work rate of A and C=120+115
Finding a common denominator (60):
120=360,115=460
Thus,
Combined work rate of A and C=360+460=760 work/day

Step 6: Let t be the time taken by A and C to finish the remaining work
The remaining work is 1730. The time t taken by A and C to complete this work is given by:
Work=Rate×Time1730=760×t
Solving for t:
t=1730÷760=1730×607=347 days

Step 7: Calculate the total time taken
A leaves 1.5 days before the work is completed, so the total time taken (T) is:
T=2 days (initial)+t+1.5 days (A leaves)
Thus,
T=2+347+1.5
Converting 1.5 to a fraction:
1.5=32=2114=1510=3020
Now, converting everything to a common denominator (14):
T=2+347+2114=2814+6814+2114=117148.36 days

Final Calculation
The total time taken to complete the work is:
T=2+5.5=7.5 days

Conclusion
The total time taken to complete the work is 7.5 days.

Updated on:8/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?

    A7310
    B1025
    C10730
    Dnone of these
  • A , B and C can do a piece of work in 24days,36 days and 108 days, respectively. They started the work together but A left 9 days after the start of the work and B left 3 days before the work was completed. For how many days did C work ?

    Aa)20
    Bb)19
    Cc)30
    Dd)31
  • A, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?

    A7310
    B10215
    C10730
    Dnone of these