A and B do a piece of work in 20 days and B in 15 days. They work together for 2 days and then A goes away. In how many days will B finish the remaining work?
To solve the problem step by step, we will follow these calculations:
Step 1: Determine the work rates of A and B
- A can complete the work in 20 days. Therefore, A's work rate is:
Work rate of A=120 (work per day)
- B can complete the work in 15 days. Therefore, B's work rate is:
Work rate of B=115 (work per day)
Step 2: Calculate the combined work rate of A and B
- When A and B work together, their combined work rate is:
Combined work rate=Work rate of A+Work rate of B=120+115
- To add these fractions, we need a common denominator. The least common multiple of 20 and 15 is 60.
120=360,115=460
- Therefore,
Combined work rate=360+460=760 (work per day)
Step 3: Calculate the work done by A and B in 2 days
- In 2 days, the amount of work done by A and B together is:
Work done in 2 days=2×760=1460=730
Step 4: Determine the remaining work
- The total work is considered as 1 unit (whole work). Therefore, the remaining work after A and B work together for 2 days is:
Remaining work=1−730=3030−730=2330
Step 5: Calculate the time taken by B to finish the remaining work
- B's work rate is 115 work per day. To find the number of days B will take to finish 2330 of the work, we use the formula:
Time=Remaining workB's work rate=2330115
- This simplifies to:
Time=2330×15=23×1530=23×12=232=11.5 days
Final Answer
B will take 11.5 days to finish the remaining work.
---
- A can complete the work in 20 days. Therefore, A's work rate is:
Work rate of A=120 (work per day)
- B can complete the work in 15 days. Therefore, B's work rate is:
Work rate of B=115 (work per day)
- When A and B work together, their combined work rate is:
Combined work rate=Work rate of A+Work rate of B=120+115
- To add these fractions, we need a common denominator. The least common multiple of 20 and 15 is 60.
120=360,115=460
- Therefore,
Combined work rate=360+460=760 (work per day)
- In 2 days, the amount of work done by A and B together is:
Work done in 2 days=2×760=1460=730
- The total work is considered as 1 unit (whole work). Therefore, the remaining work after A and B work together for 2 days is:
Remaining work=1−730=3030−730=2330
- B's work rate is 115 work per day. To find the number of days B will take to finish 2330 of the work, we use the formula:
Time=Remaining workB's work rate=2330115
- This simplifies to:
Time=2330×15=23×1530=23×12=232=11.5 days
B will take 11.5 days to finish the remaining work.
Topper's Solved these Questions
Similar Questions
A and B do a piece of work in 20 days and B in 15 days. They work together for 2 days and then A goes away. In how many days will B finish the remaining work?
View SolutionA can do a piece of work in 40 days and B in 45 days.They work together for 10 days and then B goes away. In how many days will A finish the remaining work?
View Solution
Knowledge Check
A can do a piece of work in 25 days and B in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the remaining work ?
A17 daysB11 daysC10 daysD15 daysA can do a piece of work in 25 days and B can finish it in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the remaining work ?
A17 1/2 daysB11 daysC8 4/7 daysD10 daysA can do a work in 25 days and B can do the same work in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the work?
A9 daysB11 daysC15 daysD20 days
A can do a piece of work in 25 days and B can finish it in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the remaining work ?
View SolutionDeepak can do a piece of work in 25 days and Ashok can do the same work in 40 days. They work together for 5 days and then Deepak goes away. In how many days will Ashok finish the remaining work?
View SolutionA can do a piece of work in 12 days and B in 15 days. They work together for 5 days and then B left. The days taken by A to finish the remaining work is
View SolutionA can do a piece of work in 20 days and B in 30 days. They work together for 7 days and then both leave the work. Then Calone finIshes the remaining work in 10 days. In how many days will finish the full work?
View SolutionRakesh and Siva can do a piece of work in 15 days and 18 days respectively. They work together for 5 days and then Rakesh leaves. In how many days will Siva alone finish the remaining work?
View Solution