Shubham work for 5 days and remaining work was completed by Harvinder in 9 days. If Harvinder work for 12 days then remaining work was completed by Shubham in 3 days, then find how much time Harvinder will take to complete the work alone.
A)11 days
B)1612days
C)1623days
D)1112days
The correct Answer is:B
To solve the problem step by step, we will denote Shubham's work efficiency as S and Harvinder's work efficiency as H.
Step 1: Establish the equations based on the work done
1. Shubham works for 5 days, and then Harvinder completes the remaining work in 9 days.
- The equation for this scenario is:
5S+9H=Total Work(1)
2. If Harvinder works for 12 days, then Shubham completes the remaining work in 3 days.
- The equation for this scenario is:
12H+3S=Total Work(2)
Step 2: Set the two equations equal to each other
Since both equations represent the total work, we can set them equal to each other:
5S+9H=12H+3S
Step 3: Rearranging the equation
Rearranging the equation gives:
5S−3S=12H−9H
2S=3H
Step 4: Find the ratio of efficiencies
From the equation 2S=3H, we can express the ratio of Shubham's efficiency to Harvinder's efficiency:
SH=32
This means if Shubham's efficiency is 3 units, then Harvinder's efficiency is 2 units.
Step 5: Substitute efficiencies to find total work
Let’s assume Shubham's efficiency S=3 and Harvinder's efficiency H=2. Now we can substitute these values into either equation (1) or (2) to find the total work.
Using equation (1):
5S+9H=5(3)+9(2)=15+18=33
So, the total work is 33 units.
Step 6: Calculate the time taken by Harvinder to complete the work alone
To find out how long it would take Harvinder to complete the work alone, we use the formula:
Time=Total WorkEfficiency of Harvinder=332=16.5 days
Final Answer
Harvinder will take 16.5 days to complete the work alone.
---
1. Shubham works for 5 days, and then Harvinder completes the remaining work in 9 days.
- The equation for this scenario is:
5S+9H=Total Work(1)
- The equation for this scenario is:
12H+3S=Total Work(2)
Since both equations represent the total work, we can set them equal to each other:
5S+9H=12H+3S
Rearranging the equation gives:
5S−3S=12H−9H
2S=3H
From the equation 2S=3H, we can express the ratio of Shubham's efficiency to Harvinder's efficiency:
SH=32
This means if Shubham's efficiency is 3 units, then Harvinder's efficiency is 2 units.
Let’s assume Shubham's efficiency S=3 and Harvinder's efficiency H=2. Now we can substitute these values into either equation (1) or (2) to find the total work.
5S+9H=5(3)+9(2)=15+18=33
So, the total work is 33 units.
To find out how long it would take Harvinder to complete the work alone, we use the formula:
Time=Total WorkEfficiency of Harvinder=332=16.5 days
Harvinder will take 16.5 days to complete the work alone.
Topper's Solved these Questions
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - MAINS QUESTIONS
55 Videos
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PREVIOUS YEAR QUESTIONS
32 Videos
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 1)
40 Videos
- SPEED, TIME AND DISTANCEBOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions
31 Videos
Similar Questions
A works thrice as much as B. If A can complete this work in 12 days, then in how many days will both A and B complete this work ?
View SolutionA and B together can complete a work in 20 days. They started together but after 4 days A left the work. The remaining work was completed by B alone in 24 more days. In how many days can A complete the entire work alone?
View Solution
Knowledge Check
A can do a piece of work in 12 days and B in 20 days. If they together work on it for 5 days, and remaining work is completed by C in 3 days, then in how many days can C do the same work alone?
A10 daysB9 daysC12 daysD15 daysA can complete a work in 25 days, B can complete the same work in 20 days. If they work together for 10 days and remaining work is completed by C alone in 10 days. In how many days A, B, and C together can complete the same task?
A12 daysB15 daysC10 daysD8 daysA and B together can complete a work in 10 days. They started together but A left after 2 days and the remaining work was completed by B in 12 days. In how many days can A complete the entire work while working alone?
A15B20C30D45
X' can complete a work in 40 days while Y is 20% more effi-
cient then 'X' .'Y' worked for 8 days and lift, remaining work is
completed by 'Z' in 20 days. Find in how many days 'Z' can ltbegt complete the whole work alone?
View SolutionA and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?
View SolutionA can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?
View SolutionA can complete a piece of work in 25 days. After working for 5 days, remaining work is completed in 15 days with the help of B. Then B can complete the whole work in how many days?
View SolutionA man and a boy working together can complete a work in 24 days. If for the last 6 days, the man alone does the work, then it is completed in 26 days. How long will the boy take to complete the work alone ?
View Solution