Shubham work for 5 days and remaining work was completed by Harvinder in 9 days. If Harvinder work for 12 days then remaining work was completed by Shubham in 3 days, then find how much time Harvinder will take to complete the work alone.

A

A)11 days

B

B)1612days

C

C)1623days

D

D)1112days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we will denote Shubham's work efficiency as S and Harvinder's work efficiency as H.

Step 1: Establish the equations based on the work done
1. Shubham works for 5 days, and then Harvinder completes the remaining work in 9 days.
- The equation for this scenario is:
5S+9H=Total Work(1)

2. If Harvinder works for 12 days, then Shubham completes the remaining work in 3 days.
- The equation for this scenario is:
12H+3S=Total Work(2)

Step 2: Set the two equations equal to each other
Since both equations represent the total work, we can set them equal to each other:
5S+9H=12H+3S

Step 3: Rearranging the equation
Rearranging the equation gives:
5S3S=12H9H
2S=3H

Step 4: Find the ratio of efficiencies
From the equation 2S=3H, we can express the ratio of Shubham's efficiency to Harvinder's efficiency:
SH=32
This means if Shubham's efficiency is 3 units, then Harvinder's efficiency is 2 units.

Step 5: Substitute efficiencies to find total work
Let’s assume Shubham's efficiency S=3 and Harvinder's efficiency H=2. Now we can substitute these values into either equation (1) or (2) to find the total work.

Using equation (1):
5S+9H=5(3)+9(2)=15+18=33
So, the total work is 33 units.

Step 6: Calculate the time taken by Harvinder to complete the work alone
To find out how long it would take Harvinder to complete the work alone, we use the formula:
Time=Total WorkEfficiency of Harvinder=332=16.5 days

Final Answer
Harvinder will take 16.5 days to complete the work alone.

---

Updated on:8/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A can do a piece of work in 12 days and B in 20 days. If they together work on it for 5 days, and remaining work is completed by C in 3 days, then in how many days can C do the same work alone?

    A10 days
    B9 days
    C12 days
    D15 days
  • A can complete a work in 25 days, B can complete the same work in 20 days. If they work together for 10 days and remaining work is completed by C alone in 10 days. In how many days A, B, and C together can complete the same task?

    A12 days
    B15 days
    C10 days
    D8 days
  • A and B together can complete a work in 10 days. They started together but A left after 2 days and the remaining work was completed by B in 12 days. In how many days can A complete the entire work while working alone?

    A15
    B20
    C30
    D45