If Hemant works for 20 days and Manoj works for 15 days then 35th of the work has been completed. If Manoj works for 6 days and Hemant works for 16 days then 25th of the work has been completed. Find in how many days both can complete the work together.
A)30 days
B)50 days
C)70days
D)60 days
The correct Answer is:A
To solve the problem step by step, we will follow the information provided and derive the necessary equations to find the required solution.
Step 1: Define Variables
Let:
- H = Efficiency of Hemant (work done per day)
- M = Efficiency of Manoj (work done per day)
Step 2: Set Up the First Equation
According to the first condition:
- Hemant works for 20 days and Manoj works for 15 days, completing 35 of the total work.
This can be expressed as:
20H+15M=35K
where K is the total work.
Step 3: Set Up the Second Equation
According to the second condition:
- Manoj works for 6 days and Hemant works for 16 days, completing 25 of the total work.
This can be expressed as:
16H+6M=25K
Step 4: Express Total Work K
From the first equation, we can express K:
K=53(20H+15M)
From the second equation, we can also express K:
K=52(16H+6M)
Step 5: Equate the Two Expressions for K
Set the two expressions for K equal to each other:
53(20H+15M)=52(16H+6M)
Step 6: Simplify the Equation
We can eliminate 53 and 52 by cross-multiplying:
2(20H+15M)=3(16H+6M)
Expanding both sides:
40H+30M=48H+18M
Step 7: Rearrange the Equation
Rearranging gives:
40H−48H+30M−18M=0
−8H+12M=0
This simplifies to:
2H=3MorHM=32
Step 8: Express H in Terms of M
Let H=32M.
Step 9: Substitute Back to Find Total Work K
Substituting H back into one of the equations for K:
Using the first equation:
K=53(20H+15M)
Substituting H:
K=53(20⋅32M+15M)=53(30M+15M)=53(45M)=75M
Step 10: Find Combined Efficiency
Now, the combined efficiency of Hemant and Manoj:
H+M=32M+M=52M
Step 11: Calculate Time Taken to Complete Work
The time taken to complete the total work K together is given by:
Time=KH+M=75M52M=75⋅25=30 days
Final Answer
Thus, both Hemant and Manoj can complete the work together in 30 days.
---
Let:
- H = Efficiency of Hemant (work done per day)
- M = Efficiency of Manoj (work done per day)
According to the first condition:
- Hemant works for 20 days and Manoj works for 15 days, completing 35 of the total work.
20H+15M=35K
where K is the total work.
According to the second condition:
- Manoj works for 6 days and Hemant works for 16 days, completing 25 of the total work.
16H+6M=25K
From the first equation, we can express K:
K=53(20H+15M)
From the second equation, we can also express K:
K=52(16H+6M)
Set the two expressions for K equal to each other:
53(20H+15M)=52(16H+6M)
We can eliminate 53 and 52 by cross-multiplying:
2(20H+15M)=3(16H+6M)
Expanding both sides:
40H+30M=48H+18M
Rearranging gives:
40H−48H+30M−18M=0
−8H+12M=0
This simplifies to:
2H=3MorHM=32
Let H=32M.
Substituting H back into one of the equations for K:
Using the first equation:
K=53(20H+15M)
Substituting H:
K=53(20⋅32M+15M)=53(30M+15M)=53(45M)=75M
Now, the combined efficiency of Hemant and Manoj:
H+M=32M+M=52M
The time taken to complete the total work K together is given by:
Time=KH+M=75M52M=75⋅25=30 days
Thus, both Hemant and Manoj can complete the work together in 30 days.
Topper's Solved these Questions
- TIME AND WORK & PIPE AND CISTERN Book:ADDA247Chapter:TIME AND WORK & PIPE AND CISTERN Exercise:MAINS QUESTIONS
Explore 55 Videos
- TIME AND WORK & PIPE AND CISTERN Book:ADDA247Chapter:TIME AND WORK & PIPE AND CISTERN Exercise:PREVIOUS YEAR QUESTIONS
Explore 32 Videos
- TIME AND WORK & PIPE AND CISTERN Book:ADDA247Chapter:TIME AND WORK & PIPE AND CISTERN Exercise:PRELIMS QUESTIONS (LEVEL - 1)
Explore 40 Videos
- SPEED, TIME AND DISTANCEBook:ADDA247Chapter:SPEED, TIME AND DISTANCEExercise:Previous Year Questions
Explore 31 Videos
Similar Questions
A can do a work in x days while B can do the same work in y days then in how many days will they complete the work, working together?
View SolutionIf Ramesh can complete 2/5th of a work in 24 days and Satish can complete 1/3rd of the work in 30 days, then in how many days can they complete the work if they work together?
View Solution
Knowledge Check
A and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?
A60 daysB36 daysC45 daysD24 daysA and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?
A4B15C154D16P can complete a work in 15 days and Q in 24 days. They began the work together, but Q left the work 2 days before its completion. In how many days, was the work completed?
A8B10C9D11
If Ramesh can complete 2/5th of a work in 24 days and Satish can complete 1/3rd of the work in 30 days, then in how many days can they complete the work if they work together?
View SolutionIf Ramesh can complete 2/5th of a work in 24 days and Satish can complete 1/3rd of the work in 30 days, then in how many days can they complete the work if they work together?
View SolutionIf man A complete a work in 10 days & man B complete the same work in 15 days , in how many days the work is completed if they work together ?
View SolutionA is twice as fast as B and together they can complete a work in 20 days. In how many days can A alone complete the work?
View SolutionA is twice as fast as B and together they can complete a work in 20 days. In how many days can A alone complete the work?
View Solution