If 'a' number of males can do a work in (2a-8) days while (a-8) number of males can do that work in (2a + 12) days, then find in how many days a number of males can do of that work?
12 days
days
days
8 days
The correct Answer is:B
To solve the problem step by step, let's break it down:
Step 1: Determine the total work done
We know that the total work can be calculated using the formula:
Total Work=Number of Workers×Days Taken
From the first condition, we have:
- Number of males = a
- Days = 2a−8
Thus, the total work from the first condition is:
Total Work=a×(2a−8)=2a2−8a
From the second condition, we have:
- Number of males = a−8
- Days = 2a+12
Thus, the total work from the second condition is:
Total Work=(a−8)×(2a+12)=2a2+12a−16a−96=2a2−4a−96
Step 2: Equate the two expressions for total work
Since both expressions represent the same total work, we can set them equal to each other:
2a2−8a=2a2−4a−96
Step 3: Simplify the equation
Cancelling 2a2 from both sides gives:
−8a=−4a−96
Now, rearranging the equation:
−8a+4a=−96
−4a=−96
a=24
Step 4: Calculate the total work
Substituting a=24 back into the total work formula:
Total Work=a×(2a−8)=24×(2×24−8)
=24×(48−8)=24×40=960
Step 5: Determine the work needed
We need to find out how much work 13 of 3313% of the total work is:
3313%=33.33100=13
So, 13 of the total work is:
Work Needed=13×960=320
Step 6: Calculate the efficiency of 32a males
The number of males is:
32a=32×24=36
Step 7: Calculate the time taken to complete the work
The efficiency of one male is considered as 1 unit of work per day. Therefore, the total efficiency of 36 males is:
Total Efficiency=36
Now, the time taken to complete 320 units of work is given by:
Time=Total WorkEfficiency=32036=809
Step 8: Convert to mixed fraction
To express 809 as a mixed fraction:
809=889
Final Answer
Thus, the time taken by 32a males to do 3313% of the work is:
8 89 days
We know that the total work can be calculated using the formula:
Total Work=Number of Workers×Days Taken
- Number of males = a
- Days = 2a−8
Total Work=a×(2a−8)=2a2−8a
- Number of males = a−8
- Days = 2a+12
Total Work=(a−8)×(2a+12)=2a2+12a−16a−96=2a2−4a−96
Since both expressions represent the same total work, we can set them equal to each other:
2a2−8a=2a2−4a−96
Cancelling 2a2 from both sides gives:
−8a=−4a−96
−8a+4a=−96
−4a=−96
a=24
Substituting a=24 back into the total work formula:
Total Work=a×(2a−8)=24×(2×24−8)
=24×(48−8)=24×40=960
We need to find out how much work 13 of 3313% of the total work is:
3313%=33.33100=13
So, 13 of the total work is:
Work Needed=13×960=320
The number of males is:
32a=32×24=36
The efficiency of one male is considered as 1 unit of work per day. Therefore, the total efficiency of 36 males is:
Total Efficiency=36
Time=Total WorkEfficiency=32036=809
To express 809 as a mixed fraction:
809=889
Thus, the time taken by 32a males to do 3313% of the work is:
8 89 days
Topper's Solved these Questions
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - MAINS QUESTIONS
55 Videos
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PREVIOUS YEAR QUESTIONS
32 Videos
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 1)
40 Videos
- SPEED, TIME AND DISTANCEBOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions
31 Videos
Similar Questions
Knowledge Check
If A alone can do a work in 12 days and B alone can do it in 8 days, Working together, in how many days will they complete it?
A445 daysB4 daysC345 daysD6 daysA can do a work in 40 days and B can do the same work in 60 days. In how many days they can do it together?
A12B10C15D24A and B can do a work in 8 days and A alone can do it in 12 days. In how many days can B alone do it?
A12 daysB20 daysC24 daysD28 days
A can do a work in x days while B can do the same work in y days then in how many days will they complete the work, working together?
View SolutionB and C can do a certain work in 35 days, while A,B and C can do the same work in 17.5 days. In how many days can A do the same work alone?
View SolutionIf 6 men can do a piece of work in 8 days, then find the number of days in which 8 men can do the same work.
View SolutionIf 6 men can do a piece of work in 8 days, then find the number of days in which 8 men can do the same work.
View Solution24 men can do a work in 16 days while 36 women can do the same work in 24 days. In how many days will 8 men and 6 women together complete the same work ?
View Solution