8 men and 10 women can do a work in 15 days while 10 men and 18 women can do that work in 10 days. 4 men and 5 women started the work and after 10 days all men left the work then find how many more women would be required to complete the whole work in 21 days?
12
15
16
10
The correct Answer is:B
To solve the problem step by step, let's break it down:
Step 1: Determine the total work done in terms of men and women.
Given:
- 8 men and 10 women can complete the work in 15 days.
- 10 men and 18 women can complete the work in 10 days.
Total work (W) can be calculated using the formula:
W=(Number of workers)×(Days)
From the first condition:
W=(8M+10W)×15
From the second condition:
W=(10M+18W)×10
Step 2: Set the equations equal to each other.
Since both expressions equal the total work, we can set them equal:
(8M+10W)×15=(10M+18W)×10
Step 3: Expand and simplify the equation.
Expanding both sides:
120M+150W=100M+180W
Rearranging gives:
120M−100M=180W−150W
20M=30W
Step 4: Find the ratio of men to women.
Dividing both sides by 10:
2M=3W
Thus, the ratio of men to women is:
MW=32
Step 5: Calculate the total work in terms of one variable.
Let's express the total work in terms of women (W):
Using the first equation:
W=(8M+10W)×15
Substituting M=23W:
W=(8×23W+10W)×15
W=(163W+10W)×15
W=(16+303W)×15
W=(463W)×15
W=230W
Step 6: Calculate the work done by 4 men and 5 women in 10 days.
Using the ratio of work done:
- Work done by 4 men in 10 days:
Work by 4 men=4M×10=4×23W×10=803W
- Work done by 5 women in 10 days:
Work by 5 women=5W×10=50W
Total work done in 10 days:
Total Work Done=803W+50W=80+1503W=2303W
Step 7: Calculate remaining work.
Total work is 230W, and work done is 2303W:
Remaining work:
Remaining Work=230W−2303W=690−2303W=4603W
Step 8: Determine how many days remain.
Total days = 21, days already worked = 10, so remaining days = 11.
Step 9: Calculate the efficiency required to complete the remaining work.
Let x be the number of women required to complete the remaining work:
xW×11=4603W
Dividing both sides by W:
11x=4603
x=46033≈13.94
Step 10: Determine how many more women are needed.
Initially, there were 5 women working:
More women needed=x−5=13.94−5≈8.94
Since we need whole women, we round up to 9.
Conclusion
To complete the work in 21 days, 9 more women are required.
Given:
- 8 men and 10 women can complete the work in 15 days.
- 10 men and 18 women can complete the work in 10 days.
W=(Number of workers)×(Days)
W=(8M+10W)×15
From the second condition:
W=(10M+18W)×10
Since both expressions equal the total work, we can set them equal:
(8M+10W)×15=(10M+18W)×10
Expanding both sides:
120M+150W=100M+180W
120M−100M=180W−150W
20M=30W
Dividing both sides by 10:
2M=3W
Thus, the ratio of men to women is:
MW=32
Let's express the total work in terms of women (W):
Using the first equation:
W=(8M+10W)×15
Substituting M=23W:
W=(8×23W+10W)×15
W=(163W+10W)×15
W=(16+303W)×15
W=(463W)×15
W=230W
Using the ratio of work done:
- Work done by 4 men in 10 days:
Work by 4 men=4M×10=4×23W×10=803W
- Work done by 5 women in 10 days:
Work by 5 women=5W×10=50W
Total Work Done=803W+50W=80+1503W=2303W
Total work is 230W, and work done is 2303W:
Remaining work:
Remaining Work=230W−2303W=690−2303W=4603W
Total days = 21, days already worked = 10, so remaining days = 11.
Let x be the number of women required to complete the remaining work:
xW×11=4603W
Dividing both sides by W:
11x=4603
x=46033≈13.94
Initially, there were 5 women working:
More women needed=x−5=13.94−5≈8.94
To complete the work in 21 days, 9 more women are required.
Topper's Solved these Questions
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - MAINS QUESTIONS
55 Videos
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PREVIOUS YEAR QUESTIONS
32 Videos
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 1)
40 Videos
- SPEED, TIME AND DISTANCEBOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions
31 Videos
Similar Questions
Knowledge Check
3 men and 5 women can do a work in 14 days while 5 men can do it in 14 days. 5 men and 5 women can complete the work in
A13 daysB11 daysC10 daysD12 daysIf 10 men can do a work in 20 days, then how many men can do the same work in 4 days?
(a)60 men
(b)20 men
(c)50 men
(d)40 menA60 menB20 menC50 menD40 men2 men and 7 women can do a piece of work in 14 days whereas 3 men and 8 women can do it in 11 days. In how many days 5 men and 4 women can do the same work?
A11B12C14D10
12 men and 15 women can do a work in 6 days, and 6 men and 12 women can do it in 10 days, in how many days can 8 men and 10 women do the same work?
View Solution8 men can do a work in 12 days while 20 women can do it in 10 days. In how many days can 12 men and 15 women complete the same work.
View Solution6 men and 8 women can do a work in 10 days.Then, 3 men and 4 women can do the same work in (A) 24 days (B) 20 days (C) 12 days (D) 18 days
View SolutionWhen 6 men and 8 women can do a piece of work in 15 days, then 11 men and 16 women can do the same work in 8 days. In how many days can 4 men and 4 women do the work ?
View Solution3 men or 5 women can do a work in 12 days. How long will 6 men and 5 women take to finish the work?
View Solution