8 men and 10 women can do a work in 15 days while 10 men and 18 women can do that work in 10 days. 4 men and 5 women started the work and after 10 days all men left the work then find how many more women would be required to complete the whole work in 21 days?

A

12

B

15

C

16

D

10

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, let's break it down:

Step 1: Determine the total work done in terms of men and women.
Given:
- 8 men and 10 women can complete the work in 15 days.
- 10 men and 18 women can complete the work in 10 days.

Total work (W) can be calculated using the formula:
W=(Number of workers)×(Days)

From the first condition:
W=(8M+10W)×15
From the second condition:
W=(10M+18W)×10

Step 2: Set the equations equal to each other.
Since both expressions equal the total work, we can set them equal:
(8M+10W)×15=(10M+18W)×10

Step 3: Expand and simplify the equation.
Expanding both sides:
120M+150W=100M+180W

Rearranging gives:
120M100M=180W150W
20M=30W

Step 4: Find the ratio of men to women.
Dividing both sides by 10:
2M=3W
Thus, the ratio of men to women is:
MW=32

Step 5: Calculate the total work in terms of one variable.
Let's express the total work in terms of women (W):
Using the first equation:
W=(8M+10W)×15
Substituting M=23W:
W=(8×23W+10W)×15
W=(163W+10W)×15
W=(16+303W)×15
W=(463W)×15
W=230W

Step 6: Calculate the work done by 4 men and 5 women in 10 days.
Using the ratio of work done:
- Work done by 4 men in 10 days:
Work by 4 men=4M×10=4×23W×10=803W
- Work done by 5 women in 10 days:
Work by 5 women=5W×10=50W

Total work done in 10 days:
Total Work Done=803W+50W=80+1503W=2303W

Step 7: Calculate remaining work.
Total work is 230W, and work done is 2303W:
Remaining work:
Remaining Work=230W2303W=6902303W=4603W

Step 8: Determine how many days remain.
Total days = 21, days already worked = 10, so remaining days = 11.

Step 9: Calculate the efficiency required to complete the remaining work.
Let x be the number of women required to complete the remaining work:
xW×11=4603W
Dividing both sides by W:
11x=4603
x=4603313.94

Step 10: Determine how many more women are needed.
Initially, there were 5 women working:
More women needed=x5=13.9458.94

Since we need whole women, we round up to 9.

Conclusion
To complete the work in 21 days, 9 more women are required.

Updated on:8/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • 3 men and 5 women can do a work in 14 days while 5 men can do it in 14 days. 5 men and 5 women can complete the work in

    A13 days
    B11 days
    C10 days
    D12 days
  • If 10 men can do a work in 20 days, then how many men can do the same work in 4 days?
    (a)60 men
    (b)20 men
    (c)50 men
    (d)40 men

    A60 men
    B20 men
    C50 men
    D40 men
  • 2 men and 7 women can do a piece of work in 14 days whereas 3 men and 8 women can do it in 11 days. In how many days 5 men and 4 women can do the same work?

    A11
    B12
    C14
    D10