Efficiency of B is 40% more than efficiency of A and efficiency of C is 150% of efficiency of B. B alone can complete 40% of work in 6 days. Then, find in how many days 60% of the same work will be completed by A & C working together, if A is working with 5% more efficiency.
4 days
6 days
5 days
3 days
The correct Answer is:A
To solve the problem step by step, we will follow the information given in the question and derive the required values systematically.
Step 1: Determine the Efficiency of A, B, and C
Let the efficiency of A be EA.
Since the efficiency of B is 40% more than A:
EB=EA+0.4EA=1.4EA
The efficiency of C is 150% of B:
EC=1.5EB=1.5×1.4EA=2.1EA
Step 2: Calculate the Total Work
B can complete 40% of the work in 6 days. Therefore, the total work can be calculated as follows:
If 40% of work is done in 6 days, then 100% of work will take 6 days0.4=15 days.
Step 3: Calculate the Total Work in Terms of Efficiency
Now, we can calculate the total work (W):
W=Total Time×Efficiency of B=15×EB
Substituting EB=1.4EA:
W=15×1.4EA=21EA
Step 4: Calculate the Efficiency of A with 5% Increase
A's efficiency is increased by 5%:
E′A=EA+0.05EA=1.05EA
Step 5: Calculate the Combined Efficiency of A and C
Now, we can calculate the combined efficiency of A and C:
EA+C=E′A+EC=1.05EA+2.1EA=3.15EA
Step 6: Calculate the Work to be Done
We need to find out how much work corresponds to 60% of the total work:
Required Work=0.6W=0.6×21EA=12.6EA
Step 7: Calculate the Time Taken by A and C to Complete 60% of Work
Using the formula for time:
Time=WorkEfficiency=12.6EA3.15EA
The EA cancels out:
Time=12.63.15=4 days
Conclusion
Therefore, A and C working together can complete 60% of the work in 4 days.
---
EB=EA+0.4EA=1.4EA
EC=1.5EB=1.5×1.4EA=2.1EA
If 40% of work is done in 6 days, then 100% of work will take 6 days0.4=15 days.
W=Total Time×Efficiency of B=15×EB
Substituting EB=1.4EA:
W=15×1.4EA=21EA
E′A=EA+0.05EA=1.05EA
EA+C=E′A+EC=1.05EA+2.1EA=3.15EA
Required Work=0.6W=0.6×21EA=12.6EA
Time=WorkEfficiency=12.6EA3.15EA
The EA cancels out:
Time=12.63.15=4 days
Topper's Solved these Questions
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - MAINS QUESTIONS
55 Videos
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PREVIOUS YEAR QUESTIONS
32 Videos
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 1)
40 Videos
- SPEED, TIME AND DISTANCEBOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions
31 Videos
Similar Questions
A is 20% more efficient than B.B can do a piece of work in 20 days. In how many days can A do the same work?
View SolutionIf the ratio of work efficiency of A & B is 6:5 that of B & C is 6:5 . If A can complete the piece of work in 2 days , In houw many days the same work can be completed by B & C separately ?
View Solution
Knowledge Check
P is 20% more efficient than Q. If Q alone can finish a work in 10 days, then in how many days will P alone finish the work?
A813B8.5C9D12A is 20% more efficient than B. If B alone can complete a piece of work in 12 days, then A alone can complete the same work in how many days?
A10B12C14D15A is 20% more efficient than B.B can do a piece of work in 20 days. In how many days can A do the same work?
A10B12C14D16
A is 40 % more efficient than B. If B can complete this work in 24 days. In how many days will both A and B complete this work ?
View SolutionThe ratio of work efficiency of A & B is 2:5 . If A can complete a work in 10 days. In how many days the work can be completed by B and when they work together , in how many days the work would be completed ?
View SolutionThe efficiency of A is thrice as that of B and efficiency of B is twice as that of C. If B alone can finish a work in 15 days, in how many days A and C together will complete that work?
View SolutionThe efficiency of A is thrice as that of B and efficiency of B is twice as that of C. If B alone can finish a work in 15 days, in how many days A and C together will complete that work?
View SolutionVijay is 10% more efficient than Vikas. If Vikas can complete a piece of work in 33 days. Then Vijay can complete the same work in how many days ?
View Solution