A, B and C working alone can finish a work in 80 days, 50 days and 90 days respectively. A worked alone for 21 days, then B took over from A. B worked on it alone for 22 days and then C took over from B. In how many days will C finish the remaining work? (in days)

A

A)313140

B

B)263140

C

C)302740

D

D)283140

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we will first determine the work done by A, B, and C individually, then calculate the total work done after A and B have worked, and finally find out how long it will take C to finish the remaining work.

Step 1: Determine the work efficiency of A, B, and C
- A can finish the work in 80 days, so A's work efficiency = 1/80 of the work per day.
- B can finish the work in 50 days, so B's work efficiency = 1/50 of the work per day.
- C can finish the work in 90 days, so C's work efficiency = 1/90 of the work per day.

Step 2: Find the least common multiple (LCM) of the days
To find a common measure of work, we calculate the LCM of 80, 50, and 90.
- LCM(80, 50, 90) = 3600 units of work.

Step 3: Calculate the work done by each worker per day
- A's efficiency = 3600 / 80 = 45 units/day
- B's efficiency = 3600 / 50 = 72 units/day
- C's efficiency = 3600 / 90 = 40 units/day

Step 4: Calculate the work done by A in 21 days
- Work done by A in 21 days = 45 units/day * 21 days = 945 units.

Step 5: Calculate the work done by B in 22 days
- Work done by B in 22 days = 72 units/day * 22 days = 1584 units.

Step 6: Calculate the total work done by A and B
- Total work done by A and B = Work done by A + Work done by B = 945 + 1584 = 2529 units.

Step 7: Calculate the remaining work
- Remaining work = Total work - Work done by A and B = 3600 - 2529 = 1071 units.

Step 8: Calculate the time taken by C to finish the remaining work
- Time taken by C to finish the remaining work = Remaining work / C's efficiency = 1071 units / 40 units/day.

Step 9: Simplify the time taken by C
- Time taken by C = 1071 / 40 = 26.775 days, which can be expressed as 26 whole days and 31/40 of a day.

Final Answer
C will finish the remaining work in 26 whole days and 31/40 of a day.

---

|
Updated on:8/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can do a piece of work in 15 days and B alone can do it in 10 days. B works at it for 5 days and then leaves. In how many days, A alone can finish the remaining work?

    A7days
    B712 days
    C8 days
    D812days
  • Question 2 - Select One

    A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?

    A5
    B512
    C6
    D8
  • Question 3 - Select One

    A and B can finish a work in 15 days, B and C in 20 days, while C and A in 30 days, then A alone can finish the work in

    A40 days
    B24 days
    C120 days
    D13 days