A, B and C working alone can finish a work in 80 days, 50 days and 90 days respectively. A worked alone for 21 days, then B took over from A. B worked on it alone for 22 days and then C took over from B. In how many days will C finish the remaining work? (in days)
A)313140
B)263140
C)302740
D)283140
The correct Answer is:B
To solve the problem step by step, we will first determine the work done by A, B, and C individually, then calculate the total work done after A and B have worked, and finally find out how long it will take C to finish the remaining work.
Step 1: Determine the work efficiency of A, B, and C
- A can finish the work in 80 days, so A's work efficiency = 1/80 of the work per day.
- B can finish the work in 50 days, so B's work efficiency = 1/50 of the work per day.
- C can finish the work in 90 days, so C's work efficiency = 1/90 of the work per day.
Step 2: Find the least common multiple (LCM) of the days
To find a common measure of work, we calculate the LCM of 80, 50, and 90.
- LCM(80, 50, 90) = 3600 units of work.
Step 3: Calculate the work done by each worker per day
- A's efficiency = 3600 / 80 = 45 units/day
- B's efficiency = 3600 / 50 = 72 units/day
- C's efficiency = 3600 / 90 = 40 units/day
Step 4: Calculate the work done by A in 21 days
- Work done by A in 21 days = 45 units/day * 21 days = 945 units.
Step 5: Calculate the work done by B in 22 days
- Work done by B in 22 days = 72 units/day * 22 days = 1584 units.
Step 6: Calculate the total work done by A and B
- Total work done by A and B = Work done by A + Work done by B = 945 + 1584 = 2529 units.
Step 7: Calculate the remaining work
- Remaining work = Total work - Work done by A and B = 3600 - 2529 = 1071 units.
Step 8: Calculate the time taken by C to finish the remaining work
- Time taken by C to finish the remaining work = Remaining work / C's efficiency = 1071 units / 40 units/day.
Step 9: Simplify the time taken by C
- Time taken by C = 1071 / 40 = 26.775 days, which can be expressed as 26 whole days and 31/40 of a day.
Final Answer
C will finish the remaining work in 26 whole days and 31/40 of a day.
---
- A can finish the work in 80 days, so A's work efficiency = 1/80 of the work per day.
- B can finish the work in 50 days, so B's work efficiency = 1/50 of the work per day.
- C can finish the work in 90 days, so C's work efficiency = 1/90 of the work per day.
To find a common measure of work, we calculate the LCM of 80, 50, and 90.
- LCM(80, 50, 90) = 3600 units of work.
- A's efficiency = 3600 / 80 = 45 units/day
- B's efficiency = 3600 / 50 = 72 units/day
- C's efficiency = 3600 / 90 = 40 units/day
- Work done by A in 21 days = 45 units/day * 21 days = 945 units.
- Work done by B in 22 days = 72 units/day * 22 days = 1584 units.
- Total work done by A and B = Work done by A + Work done by B = 945 + 1584 = 2529 units.
- Remaining work = Total work - Work done by A and B = 3600 - 2529 = 1071 units.
- Time taken by C to finish the remaining work = Remaining work / C's efficiency = 1071 units / 40 units/day.
- Time taken by C = 1071 / 40 = 26.775 days, which can be expressed as 26 whole days and 31/40 of a day.
C will finish the remaining work in 26 whole days and 31/40 of a day.
Topper's Solved these Questions
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 2)40videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - MAINS QUESTIONS55videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - BASIC QUESTIONS15videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions31videos
SPEED, TIME AND DISTANCE
Similar Questions
A, B and C can finish a piece of work in 12 days, 15 days and 20 days respectively. They started working together. B left the work after working 3 days and C left the work 3 days before completion of the work. In how many days work will be finished?
View SolutionA can finish a work in 18 days and B can do the same work in 15 days B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?
(A) 5
(B) 5
(D) 8
(C) 6View Solution
Knowledge Check
- Question 1 - Select One
A can do a piece of work in 15 days and B alone can do it in 10 days. B works at it for 5 days and then leaves. In how many days, A alone can finish the remaining work?
A7daysB712 daysC8 daysD812days - Question 2 - Select One
A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?
A5B512C6D8 - Question 3 - Select One
A and B can finish a work in 15 days, B and C in 20 days, while C and A in 30 days, then A alone can finish the work in
A40 daysB24 daysC120 daysD13 days
A, B and C working together can finish a piece of work in 32 days. They started working together and worked for 20 days then A left the work. Rest work done by B and C in 20 days. In how many days A working alone will finish the work?
View SolutionA, B and C working together can finish a certain piece of work in 40 days. They work for 25 days and then B left and rest work done by A and C in 20 days. If efficiency of C is half of B's efficiency. Then in how many days A will finish the working alone?
View SolutionA and B can finish a work in 10 days while B and C can do it in 18 days. A started the work, worked for 5 days, then B worked for 10 days and the remaining work was finished by C in 15 days. In how many days could C alone have finished the whole work ?
A)30 days
B)15 days
C)45 days
D)24 daysView SolutionA, B and C can do a job working alone in 50, 75 and 20 days respectively. They all work together for 4 days, then C quits. How many days will A and B take to finish the rest of the job?
View SolutionA, B and C can do a job working alone in 50, 75 and 20 days respectively. They all work together for 4 days, then C quits. How many days will A and B take to finish the rest of the job?
View Solution