A and B can finish a work in 10 days while B and C can do it in 18 days. A started the work, worked for 5 days, then B worked for 10 days and the remaining work was finished by C in 15 days. In how many days could C alone have finished the whole work ?
A)30 days
B)15 days
C)45 days
D)24 days
30 days
15 days
45 days
24 days
The correct Answer is:C
To solve the problem step by step, we will first determine the efficiencies of A, B, and C based on the information provided.
Step 1: Determine the total work
Let the total work be represented in units. Since A and B can finish the work in 10 days, we can assume the total work is 90 units (as the LCM of 10 and 18 is 90).
Step 2: Calculate the efficiencies of A, B, and C
- Efficiency of A and B: They complete the work in 10 days.
Efficiency of A and B=90 units10 days=9 units/day
- Efficiency of B and C: They complete the work in 18 days.
Efficiency of B and C=90 units18 days=5 units/day
Step 3: Set up equations for individual efficiencies
Let the efficiencies of A, B, and C be represented as a, b, and c respectively:
- From the efficiency of A and B:
a+b=9(1)
- From the efficiency of B and C:
b+c=5(2)
Step 4: Solve the equations
From equation (1), we can express a in terms of b:
a=9−b(3)
Substituting equation (3) into equation (2):
b+c=5⟹c=5−b(4)
Step 5: Calculate work done by A, B, and C
Now, we analyze the work done:
- A worked for 5 days:
Work done by A=5a
- B worked for 10 days:
Work done by B=10b
- C worked for 15 days:
Work done by C=15c
Step 6: Total work equation
The total work done by A, B, and C must equal 90 units:
5a+10b+15c=90
Step 7: Substitute values from equations
Substituting c from equation (4) into the total work equation:
5a+10b+15(5−b)=90
Expanding this gives:
5a+10b+75−15b=90
Simplifying:
5a−5b+75=90
5a−5b=15
Dividing by 5:
a−b=3(5)
Step 8: Solve for a and b
Now we have two equations (1) and (5):
1. a+b=9
2. a−b=3
Adding these two equations:
2a=12⟹a=6
Substituting a back into equation (1):
6+b=9⟹b=3
Step 9: Find c
Using equation (4):
c=5−b=5−3=2
Step 10: Calculate the time taken by C alone
C's efficiency is c=2 units/day. To find how many days C would take to finish the whole work:
Days taken by C=90 units2 units/day=45 days
Final Answer
C alone could finish the whole work in 45 days.
Let the total work be represented in units. Since A and B can finish the work in 10 days, we can assume the total work is 90 units (as the LCM of 10 and 18 is 90).
- Efficiency of A and B: They complete the work in 10 days.
Efficiency of A and B=90 units10 days=9 units/day
Efficiency of B and C=90 units18 days=5 units/day
Let the efficiencies of A, B, and C be represented as a, b, and c respectively:
- From the efficiency of A and B:
a+b=9(1)
- From the efficiency of B and C:
b+c=5(2)
From equation (1), we can express a in terms of b:
a=9−b(3)
b+c=5⟹c=5−b(4)
Now, we analyze the work done:
- A worked for 5 days:
Work done by A=5a
- B worked for 10 days:
Work done by B=10b
- C worked for 15 days:
Work done by C=15c
The total work done by A, B, and C must equal 90 units:
5a+10b+15c=90
Substituting c from equation (4) into the total work equation:
5a+10b+15(5−b)=90
Expanding this gives:
5a+10b+75−15b=90
Simplifying:
5a−5b+75=90
5a−5b=15
Dividing by 5:
a−b=3(5)
Now we have two equations (1) and (5):
1. a+b=9
2. a−b=3
2a=12⟹a=6
Substituting a back into equation (1):
6+b=9⟹b=3
Using equation (4):
c=5−b=5−3=2
C's efficiency is c=2 units/day. To find how many days C would take to finish the whole work:
Days taken by C=90 units2 units/day=45 days
C alone could finish the whole work in 45 days.
Topper's Solved these Questions
- TIME AND WORKBOOK - DISHA PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - Practice Exercise (Standard Level)
37 Videos
- TIME AND WORKBOOK - DISHA PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - Practice Exercise (Expert Level)
27 Videos
- TIME AND WORKBOOK - DISHA PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - Test Yourself
15 Videos
- SET THEORYBOOK - DISHA PUBLICATIONCHAPTER - SET THEORYEXERCISE - Test Yourself
15 Videos
- TIME, SPEED AND DISTANCEBOOK - DISHA PUBLICATIONCHAPTER - TIME, SPEED AND DISTANCEEXERCISE - Test Yourself
15 Videos
Similar Questions
A and B can finish a work together in 12 days, and B and C together in 16 days. If A alone works for 5 days and then B alone continues for 7 days, then remaining work is done by C in 13 days. In how many days can C alone finish the complete work?
View Solution(A + B) can do a piece of work in 12 days. (B + C) can do same work in 16 days. A work for 5 days, B works for 7 days and C completed the remaining work in 13 days. In how many days will A, B and C do this work alone ?
View Solution
Knowledge Check
A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:
A5 daysB6 daysC10 daysD1012 daysA can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:
A5 daysB6 daysC10 daysD1012 daysA can finish a work in 12 days and B can do it in 15 days. After A had worked for 3 days, B also joined A to finish the remaining work. In how many days, the remaining work will be finished?
A3B4C5D6
A can finish a work in 12 days and B can do it in 15 days. ’After A had worked for 3 days, B also joined A to finish the remaining work. In how many days, the remaining work will be finished?
View SolutionA and B together can complete a work in 12 days and B and C can do it in 16 days. A work for 5 days and B for 7 days then C complete the remaining work in 13 days. In how many days B can finish the work?
View SolutionA can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but they are forced to leave after 3 days. The remaining work was done by A in
View SolutionA can do a piece of work in 30 days and B can do the same piece of work in 20 days. They start working together and work for 4 days and then both leave the work. C alone finishes the remaining work in 18 days. In how many days will C alone finish the whole work?
View SolutionA can do a piece of work in 20 days and B can do the same piece of work in 30 days. They start working together and work for 5 days and then both leave he work. C alone finishes the remaining work in 14 days. In how many days will C alone finish the whole work?
View Solution