A and B can finish a work in 10 days while B and C can do it in 18 days. A started the work, worked for 5 days, then B worked for 10 days and the remaining work was finished by C in 15 days. In how many days could C alone have finished the whole work ?
A)30 days
B)15 days
C)45 days
D)24 days

A

30 days

B

15 days

C

45 days

D

24 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will first determine the efficiencies of A, B, and C based on the information provided.

Step 1: Determine the total work
Let the total work be represented in units. Since A and B can finish the work in 10 days, we can assume the total work is 90 units (as the LCM of 10 and 18 is 90).

Step 2: Calculate the efficiencies of A, B, and C
- Efficiency of A and B: They complete the work in 10 days.
Efficiency of A and B=90 units10 days=9 units/day

- Efficiency of B and C: They complete the work in 18 days.
Efficiency of B and C=90 units18 days=5 units/day

Step 3: Set up equations for individual efficiencies
Let the efficiencies of A, B, and C be represented as a, b, and c respectively:
- From the efficiency of A and B:
a+b=9(1)
- From the efficiency of B and C:
b+c=5(2)

Step 4: Solve the equations
From equation (1), we can express a in terms of b:
a=9b(3)

Substituting equation (3) into equation (2):
b+c=5c=5b(4)

Step 5: Calculate work done by A, B, and C
Now, we analyze the work done:
- A worked for 5 days:
Work done by A=5a
- B worked for 10 days:
Work done by B=10b
- C worked for 15 days:
Work done by C=15c

Step 6: Total work equation
The total work done by A, B, and C must equal 90 units:
5a+10b+15c=90

Step 7: Substitute values from equations
Substituting c from equation (4) into the total work equation:
5a+10b+15(5b)=90
Expanding this gives:
5a+10b+7515b=90
Simplifying:
5a5b+75=90
5a5b=15
Dividing by 5:
ab=3(5)

Step 8: Solve for a and b
Now we have two equations (1) and (5):
1. a+b=9
2. ab=3

Adding these two equations:
2a=12a=6
Substituting a back into equation (1):
6+b=9b=3

Step 9: Find c
Using equation (4):
c=5b=53=2

Step 10: Calculate the time taken by C alone
C's efficiency is c=2 units/day. To find how many days C would take to finish the whole work:
Days taken by C=90 units2 units/day=45 days

Final Answer
C alone could finish the whole work in 45 days.

Updated on:8/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:

    A5 days
    B6 days
    C10 days
    D1012 days
  • A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:

    A5 days
    B6 days
    C10 days
    D1012 days
  • A can finish a work in 12 days and B can do it in 15 days. After A had worked for 3 days, B also joined A to finish the remaining work. In how many days, the remaining work will be finished?

    A3
    B4
    C5
    D6