20 male labours can finish the work in 30 days and 30 female labours can finish the same work in 24 days. If all of them work together, then in how many days they will finish the same work?

A

A)283days

B

B)203days

C

C)403days

D

D)343days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we can follow these calculations:

Step 1: Calculate the total work done in terms of units.
Given that:
- 20 male labours can finish the work in 30 days.

To find the total work in units, we can use the formula:
Total Work=Number of Labours×Days
Thus, for male labours:
Total Work=20 labours×30 days=600 units

Step 2: Calculate the efficiency of male labours.
The efficiency of the male labours can be calculated as:
Efficiency of Male Labours=Total WorkDays=600 units30 days=20 units per day

Step 3: Calculate the total work done by female labours.
Given that:
- 30 female labours can finish the work in 24 days.

Using the same formula for total work:
Total Work=30 labours×24 days=720 units

Step 4: Calculate the efficiency of female labours.
The efficiency of the female labours can be calculated as:
Efficiency of Female Labours=Total WorkDays=720 units24 days=30 units per day

Step 5: Calculate the combined efficiency of male and female labours.
Now, we can find the combined efficiency when both male and female labours work together:
Combined Efficiency=Efficiency of Male Labours+Efficiency of Female Labours
Combined Efficiency=20 units per day+30 units per day=50 units per day

Step 6: Calculate the time taken to finish the work together.
Now, we can find the time taken to complete the work when both groups work together:
Time=Total WorkCombined Efficiency
Using the total work calculated from either group (let's use the male labours' work):
Time=600 units50 units per day=12 days

Final Answer:
Thus, if all of them work together, they will finish the work in 12 days.

---

Updated on:8/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A can finish work in 20 days and B can finish the same work in 25 days. They began together, but B left the work after 5 days. How many more days will A take to finish the remaining work?
    A 20 दिनों में कार्य समाप्त कर सकता है तथा B इसी कार्य को 25 दिनों में पूरा कर सकता है | उन्होंने एक साथ कार्य करना शुरू किया, लेकिन B ने 5 दिनों के बाद कार्य छोड़ दिया | शेष कार्य पूरा करने में A को कितने अतिरिक्त दिन लगेंगे ?

    A16
    B8
    C21
    D11
  • A can finish a task in 45 days and B can finish the same task in 30 days. They work together for 3 days and then A leaves. In how many days will B finish the remaining task?

    A5
    B18
    C25
    D20
  • A can do a work in 25 days and B can do the same work in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the work?

    A9 days
    B11 days
    C15 days
    D20 days