20 male labours can finish the work in 30 days and 30 female labours can finish the same work in 24 days. If all of them work together, then in how many days they will finish the same work?
A)283days
B)203days
C)403days
D)343days
The correct Answer is:C
To solve the problem step by step, we can follow these calculations:
Step 1: Calculate the total work done in terms of units.
Given that:
- 20 male labours can finish the work in 30 days.
To find the total work in units, we can use the formula:
Total Work=Number of Labours×Days
Thus, for male labours:
Total Work=20 labours×30 days=600 units
Step 2: Calculate the efficiency of male labours.
The efficiency of the male labours can be calculated as:
Efficiency of Male Labours=Total WorkDays=600 units30 days=20 units per day
Step 3: Calculate the total work done by female labours.
Given that:
- 30 female labours can finish the work in 24 days.
Using the same formula for total work:
Total Work=30 labours×24 days=720 units
Step 4: Calculate the efficiency of female labours.
The efficiency of the female labours can be calculated as:
Efficiency of Female Labours=Total WorkDays=720 units24 days=30 units per day
Step 5: Calculate the combined efficiency of male and female labours.
Now, we can find the combined efficiency when both male and female labours work together:
Combined Efficiency=Efficiency of Male Labours+Efficiency of Female Labours
Combined Efficiency=20 units per day+30 units per day=50 units per day
Step 6: Calculate the time taken to finish the work together.
Now, we can find the time taken to complete the work when both groups work together:
Time=Total WorkCombined Efficiency
Using the total work calculated from either group (let's use the male labours' work):
Time=600 units50 units per day=12 days
Final Answer:
Thus, if all of them work together, they will finish the work in 12 days.
---
Given that:
- 20 male labours can finish the work in 30 days.
Total Work=Number of Labours×Days
Thus, for male labours:
Total Work=20 labours×30 days=600 units
The efficiency of the male labours can be calculated as:
Efficiency of Male Labours=Total WorkDays=600 units30 days=20 units per day
Given that:
- 30 female labours can finish the work in 24 days.
Total Work=30 labours×24 days=720 units
The efficiency of the female labours can be calculated as:
Efficiency of Female Labours=Total WorkDays=720 units24 days=30 units per day
Now, we can find the combined efficiency when both male and female labours work together:
Combined Efficiency=Efficiency of Male Labours+Efficiency of Female Labours
Combined Efficiency=20 units per day+30 units per day=50 units per day
Now, we can find the time taken to complete the work when both groups work together:
Time=Total WorkCombined Efficiency
Using the total work calculated from either group (let's use the male labours' work):
Time=600 units50 units per day=12 days
Thus, if all of them work together, they will finish the work in 12 days.
Topper's Solved these Questions
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 2)
40 Videos
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - MAINS QUESTIONS
55 Videos
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - BASIC QUESTIONS
15 Videos
- SPEED, TIME AND DISTANCEBOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions
31 Videos
Similar Questions
16 men can finish a work in 24 days and 48 boys can finish the same work in 16 days. 12 men started the work and after 4 days 12 boys joined them. In how many days can they finish the remaining work? 6 b. 12 c. 16 d. none of these
View SolutionIf 12 men and 16 boys can finish a work in 5 days, while 13 men and 24 boys can finish the same work in 4 days. Compare the one day work of 1 man and 1 boy.
View Solution
Knowledge Check
A can finish work in 20 days and B can finish the same work in 25 days. They began together, but B left the work after 5 days. How many more days will A take to finish the remaining work?
A 20 दिनों में कार्य समाप्त कर सकता है तथा B इसी कार्य को 25 दिनों में पूरा कर सकता है | उन्होंने एक साथ कार्य करना शुरू किया, लेकिन B ने 5 दिनों के बाद कार्य छोड़ दिया | शेष कार्य पूरा करने में A को कितने अतिरिक्त दिन लगेंगे ?A16B8C21D11A can finish a task in 45 days and B can finish the same task in 30 days. They work together for 3 days and then A leaves. In how many days will B finish the remaining task?
A5B18C25D20A can do a work in 25 days and B can do the same work in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the work?
A9 daysB11 daysC15 daysD20 days
1. A and B together can finish a work in 15 days. If If A alone can finish this work in 24 days, B alone can do this work In how many days?
View SolutionA and B together finish a work in 4 day while Aalone finishes the work girl 12 day In how many days will B finish the san work ?
View SolutionSixteen men can finish a work in 8 days. Eight men and nine women working together can finish the same work in 10 days. In how many days will twenty women finish the same work?
View SolutionA can finish a work in 7 days. B can finish the same work in 9 days. The days required to finish the work by both of them together.
View SolutionA can finish a work in 18 days and B can do the same work in 15 days B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?
(A) 5
(B) 5
(D) 8
(C) 6
View Solution