Anurag is 40% less efficient than Bholu, who can do the same work in 20% less time than Chotu. If Anurag and Bholu together can complete 80% of work in 12 days, then in how many days 60% of work can be completed by Bholu and Chotu together.
A)2 days
B)4 days
C)6 days
D)8 days
The correct Answer is:D
To solve the problem step by step, we will analyze the efficiencies of Anurag, Bholu, and Chotu, and then calculate the required time for Bholu and Chotu to complete 60% of the work.
Step 1: Determine the efficiency of Anurag and Bholu
Anurag is 40% less efficient than Bholu. If we assume Bholu's efficiency is 5 units, then Anurag's efficiency can be calculated as follows:
Anurag's efficiency=5−(0.4×5)=5−2=3 units
Step 2: Determine the efficiency of Chotu
Bholu can do the same work in 20% less time than Chotu. This means if Chotu takes 5 units of time, Bholu takes 4 units of time. The ratio of their efficiencies is the inverse of the ratio of their times:
Efficiency ratio of Bholu to Chotu=54
Thus, if Bholu's efficiency is 5 units, Chotu's efficiency can be calculated as:
Chotu's efficiency=4 units
Step 3: Calculate the total work done by Anurag and Bholu
Anurag and Bholu together can complete 80% of the work in 12 days. Their combined efficiency is:
Total efficiency of Anurag and Bholu=3+5=8 units
The total work (W) can be calculated using the formula:
Work=Efficiency×Time
Given that they complete 80% of the total work in 12 days:
45W=8×12
Calculating the right side:
45W=96⟹W=96×54=120 units
Step 4: Calculate the time taken by Bholu and Chotu to complete 60% of the work
Now we need to find out how many days Bholu and Chotu will take to complete 60% of the total work.
60% of the total work is:
Work to be done=0.6×120=72 units
The combined efficiency of Bholu and Chotu is:
Total efficiency of Bholu and Chotu=5+4=9 units
Now, we can calculate the time (T) taken by Bholu and Chotu to complete 72 units of work:
T=WorkEfficiency=729=8 days
Final Answer
Thus, Bholu and Chotu together can complete 60% of the work in 8 days.
---
Anurag is 40% less efficient than Bholu. If we assume Bholu's efficiency is 5 units, then Anurag's efficiency can be calculated as follows:
Bholu can do the same work in 20% less time than Chotu. This means if Chotu takes 5 units of time, Bholu takes 4 units of time. The ratio of their efficiencies is the inverse of the ratio of their times:
Anurag and Bholu together can complete 80% of the work in 12 days. Their combined efficiency is:
Now we need to find out how many days Bholu and Chotu will take to complete 60% of the total work.
Thus, Bholu and Chotu together can complete 60% of the work in 8 days.
Topper's Solved these Questions
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 2)40videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - MAINS QUESTIONS55videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - BASIC QUESTIONS15videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions31videos
SPEED, TIME AND DISTANCE
Similar Questions
Anand is 50% more efficient than Bharath and Bharath is 100% more efficient that Chandu. Working together, they can complete a work in 10 days. In how many days can Anand alone do the work?
View SolutionA is 40 % more efficient than B and B is 20 % less efficient than C. If A takes 6 days less than C to complete a work, then in how many days will B complete this work ?
View Solution
Knowledge Check
- Question 1 - Select One
The working capacity of A is 50% more than that of B. If A can complete a work in 12 days, then in how many days B will complete this work?
A18 daysB20 daysC15 daysD12 days - Question 2 - Select One
A and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?
A60 daysB36 daysC45 daysD24 days - Question 3 - Select One
A works 3 times as fast as B. If B can complete a work in 60 days, then in how many days can A and B together complete the same work ?
A20B12C15D30
A works 3 times as fast as B. If B can complete a work in 60 days, then in how many days can A and B together complete the same work ?
View SolutionAnil, Bhuvan and Chirag together can complete a work in 35 days. Anil and Chirag together can complete the same work in 60 days. In how many days Bhuvan alone can complete the same work?
View SolutionA is 20% more efficient than B. If B alone can complete a piece of work in 12 days, then A alone can complete the same work in how many days?
View SolutionA is 20% more efficient than B.B can do a piece of work in 20 days. In how many days can A do the same work?
View SolutionA works 3 times as fast as B. If B can complete a work in 60 days, then in how many days can A and B together complete the same work ?
View Solution