A works 3 times as fast as B. If B can complete a work in 60 days, then in how many days can A and B together complete the same work ?

A

20

B

12

C

15

D

30

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will follow these calculations:

Step 1: Determine the time taken by A to complete the work.
Since A works 3 times as fast as B, if B takes 60 days to complete the work, then A will take:
Time taken by A=603=20 days

Step 2: Calculate the work done by A and B in one day.
- Work done by A in one day:
Work done by A in one day=120 of the work
- Work done by B in one day:
Work done by B in one day=160 of the work

Step 3: Calculate the total work done by A and B together in one day.
To find the total work done by A and B together in one day, we add the work done by A and B:
Total work done in one day=120+160

To add these fractions, we need a common denominator. The least common multiple of 20 and 60 is 60. Thus, we can rewrite the fractions:
120=360
So,
Total work done in one day=360+160=460=115

Step 4: Calculate the total time taken by A and B together to complete the work.
If A and B together complete 115 of the work in one day, then the total time taken to complete the entire work is:
Total time=1115=15 days

Final Answer:
A and B together can complete the work in 15 days.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A alone can complete a work in 12 days and B alone can complete the same work in 24 days. In how many days can A and B together complete the same work?

    A6 days
    B4 days
    C10 days
    D8 days
  • A alone can complete a work in 6 days and B alone can complete the same work in 8 days. In how many days both A and B together can complete the same work?

    A4813 days
    B3513 days
    C267 days
    D247 days
  • A can work twice as fast as B.A. and C together can work three times as fast as B. If A ,B and C complete a job in 30 days working together, in how may days can each of them complete the work?

    A40, 80, 100
    B60, 120, 120
    C50, 100, 120
    D60, 100, 80