A and B can do 45th and 35th of a piece of work in 15 days and 10 days respectively. In how many days can A and B working together complete the work, if B worked for 5 days without A ?
6217
61017
6317
61217
The correct Answer is:C
To solve the problem step by step, let's break it down:
Step 1: Calculate A's one-day work
A can complete 45 of the work in 15 days. Therefore, the total work can be calculated as:
Total work=15×54=754
Now, A's one-day work is:
A′s one-day work=1Total days=475
Step 2: Calculate B's one-day work
B can complete 35 of the work in 10 days. Therefore, the total work can be calculated as:
Total work=10×53=503
Now, B's one-day work is:
B′s one-day work=1Total days=350
Step 3: Calculate the work done by B in 5 days
B works alone for 5 days. The work done by B in 5 days is:
Work done by B=5×B′s one-day work=5×350=1550=310
Step 4: Calculate the remaining work
The total work is considered as 1 unit. The remaining work after B has worked for 5 days is:
Remaining work=1−310=1010−310=710
Step 5: Calculate the combined one-day work of A and B
Now, we need to find out how much work A and B can do together in one day:
Combined one-day work=A′s one-day work+B′s one-day work=475+350
To add these fractions, we need a common denominator. The LCM of 75 and 50 is 150:
475=4×275×2=8150
350=3×350×3=9150
Now, adding these:
Combined one-day work=8150+9150=17150
Step 6: Calculate the number of days to complete the remaining work
Now, we need to find out how many days A and B will take to complete the remaining 710 of the work:
Days to complete remaining work=Remaining workCombined one-day work=71017150=710×15017=7×15010×17=1050170=10517
This can be simplified to:
10517≈6.176 days
Final Answer
Thus, A and B together can complete the remaining work in approximately 6117 days.
---
A can complete 45 of the work in 15 days. Therefore, the total work can be calculated as:
Total work=15×54=754
Now, A's one-day work is:
A′s one-day work=1Total days=475
B can complete 35 of the work in 10 days. Therefore, the total work can be calculated as:
Total work=10×53=503
Now, B's one-day work is:
B′s one-day work=1Total days=350
B works alone for 5 days. The work done by B in 5 days is:
Work done by B=5×B′s one-day work=5×350=1550=310
The total work is considered as 1 unit. The remaining work after B has worked for 5 days is:
Remaining work=1−310=1010−310=710
Now, we need to find out how much work A and B can do together in one day:
Combined one-day work=A′s one-day work+B′s one-day work=475+350
To add these fractions, we need a common denominator. The LCM of 75 and 50 is 150:
475=4×275×2=8150
350=3×350×3=9150
Now, adding these:
Combined one-day work=8150+9150=17150
Now, we need to find out how many days A and B will take to complete the remaining 710 of the work:
Days to complete remaining work=Remaining workCombined one-day work=71017150=710×15017=7×15010×17=1050170=10517
This can be simplified to:
10517≈6.176 days
Thus, A and B together can complete the remaining work in approximately 6117 days.
Topper's Solved these Questions
- TIME AND WORK PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-2)
20 Videos
- TIME AND WORK PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)
7 Videos
- TIME AND WORK PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - Essay Type Question
5 Videos
- TIME AND DISTANCE BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND DISTANCE EXERCISE - Concept Application (Level 2 )
3 Videos
- TIME AND WORK, PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)
7 Videos
Similar Questions
Knowledge Check
A' can do a piece of work in 4 days and B in 12 days. In how many days can A and B together complete the same piece of work ?
A7 daysB3 daysC2 daysD4 daysA can do a piece of work in 30 days while B can do it in 40 days. In how many days can A and B working together do it?
A70 daysB4234 daysC2717daysD1717 daysA and B can do 45th and 35th of a piece of work in 15 days and 10 days respectively. In how many days can A and B working together complete the work, if B worked for 5 days without A ?
A6217B61017C6317D61217
A can do of a work in 10 days. B can do of the work in 20 days. In how many days can both A and B together do the work?
View SolutionA can do a piece of work in 14 days while B can do it in 28 days. In how many days, working together will they complete the whole work?
View SolutionA can do 110 th of a piece of work in a day. B can do the same work in 15 days. In how many days can they do the same work, working together?
View SolutionA can do 110 th of a piece of work in a day. B can do the same work in 15 days. In how many days can they do the same work, working together?
View SolutionIf A and B together can complete a piece of work in 15 days and B alone in 20 days, in how many day can A alone complete the work?
View Solution