A and B started the work alternatively starting with A. On last day A completed the work by doing 12.5% of the whole work. Which of the following can be the possible value of time taken by B alone to do that work if A alone can do the whole work in 6 days.
15 days
8 days
10 days
6 days
The correct Answer is:B
To solve the problem step by step, we will analyze the information given and derive the necessary calculations.
Step 1: Understanding the Work Done by A
A can complete the whole work in 6 days. Therefore, the work done by A in one day is:
Work done by A in one day=16 of the total work
Step 2: Total Work Calculation
Let's assume the total work is 600 units (as suggested in the video). Hence, A can do:
Work done by A in one day=6006=100 units
Step 3: Work Done by A on the Last Day
On the last day, A completed 12.5% of the total work:
Work done by A on the last day=12.5% of 600=12.5100×600=75 units
Step 4: Total Work Done Before the Last Day
Since A completed 75 units on the last day, the work done before the last day is:
Total work done before last day=600−75=525 units
Step 5: Work Alternating Between A and B
A and B work alternately, starting with A. Let's denote the time taken by B to complete the whole work as x days. Therefore, the work done by B in one day is:
Work done by B in one day=600x units
Step 6: Total Days Calculation
Let’s say the total number of days taken to complete the work is n. Since A starts the work, the sequence of work done will be:
- Day 1: A works
- Day 2: B works
- Day 3: A works
- Day 4: B works
- ...
- Last Day: A works
If n is odd, A will work on the last day. The number of days A works will be:
Days A works=n+12
And the number of days B works will be:
Days B works=n−12
Step 7: Total Work Equation
The total work done by A and B can be expressed as:
Total Work=Work done by A+Work done by B
This gives us:
600=(n+12×100)+(n−12×600x)
Step 8: Solving for n and x
Substituting the known values and simplifying:
600=50(n+1)+300(n−1)x
This equation can be solved for n and x to find the possible values of time taken by B alone.
Conclusion
From the above steps, we can derive the possible values for x based on the equation we formed.
A can complete the whole work in 6 days. Therefore, the work done by A in one day is:
Work done by A in one day=16 of the total work
Let's assume the total work is 600 units (as suggested in the video). Hence, A can do:
Work done by A in one day=6006=100 units
On the last day, A completed 12.5% of the total work:
Work done by A on the last day=12.5% of 600=12.5100×600=75 units
Since A completed 75 units on the last day, the work done before the last day is:
Total work done before last day=600−75=525 units
A and B work alternately, starting with A. Let's denote the time taken by B to complete the whole work as x days. Therefore, the work done by B in one day is:
Work done by B in one day=600x units
Let’s say the total number of days taken to complete the work is n. Since A starts the work, the sequence of work done will be:
- Day 1: A works
- Day 2: B works
- Day 3: A works
- Day 4: B works
- ...
- Last Day: A works
Days A works=n+12
And the number of days B works will be:
Days B works=n−12
The total work done by A and B can be expressed as:
Total Work=Work done by A+Work done by B
This gives us:
600=(n+12×100)+(n−12×600x)
Substituting the known values and simplifying:
600=50(n+1)+300(n−1)x
This equation can be solved for n and x to find the possible values of time taken by B alone.
From the above steps, we can derive the possible values for x based on the equation we formed.
Topper's Solved these Questions
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 2)40videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - MAINS QUESTIONS55videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - BASIC QUESTIONS15videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions31videos
SPEED, TIME AND DISTANCE
Similar Questions
A can do a certain work in 15 days, while working together, A and B can do the same work in 7.5 days. How many days will B alone take to do the same work ?
View SolutionA can do a piece of work in 18 days. He worked at it for 12 days and B finished the remaining work in 8 days. B alone can do the whole work in
View Solution
Knowledge Check
- Question 1 - Select One
A and B can do a piece of work in 6 days and A alone can do it in 9 days. In how many days can B alone do it?
A18 daysB15 daysC12 daysD712 days - Question 2 - Select One
A and B together can do a piece of work in 4 days and A alone can do it in 6 days, B alone can do the same work in :
A1313 daysB12 daysC16 daysD11 days - Question 3 - Select One
A can do a piece of work in 20 days. He worked for 5 days and B finished the remaining work in 42 days. B alone can do the whole work in how many days?
Aa)56Bb)52Cc)46Dd)64
A and B can do a work in 8 days. B alone can do it in 24 days. In how many days, A alone can do the same work?
View SolutionA and B can do a piece of work in 12 days, B and C in 15 days, C and A in 20 days. In what time can A do it separately?
View SolutionA can do a piece of work in 30 days. He worked for 6 days and B finished the remaining work in 48 days. B alone can do the whole work in how many days?
View SolutionA and B together can do a piece of work in 5 days and A alone can do it in 8 days. B alone can do the same piece of work in:
View SolutionA and B can do a work in 12 days, Band C can do the same work in 15 days, C and A can do the same work in 20 days. The time taken by A, B and C to do the same work is
View Solution