A and B can do a piece of work in 12 days and 15 days, respectively. They began to work together but B left after 4 days. In how many more days would B alone complete the remaining work?
The correct Answer is:C
To solve the problem step by step, we will calculate the work done by A and B, and then determine how many more days B would take to complete the remaining work after A and B have worked together for 4 days.
Step 1: Determine the total work
A can complete the work in 12 days, and B can complete it in 15 days. To find the total work, we can take the least common multiple (LCM) of their working days.
- LCM of 12 and 15 is 60.
Step 2: Calculate the efficiency of A and B
Efficiency is calculated as the total work divided by the time taken to complete that work.
- Efficiency of A = Total Work / Time taken by A = 60 / 12 = 5
- Efficiency of B = Total Work / Time taken by B = 60 / 15 = 4
Step 3: Calculate the combined efficiency of A and B
When A and B work together, their efficiencies add up.
- Combined efficiency of A and B = Efficiency of A + Efficiency of B = 5 + 4 = 9
Step 4: Calculate the work done by A and B in 4 days
Now that we know their combined efficiency, we can calculate how much work they complete together in 4 days.
- Work done in 4 days = Combined efficiency × Number of days = 9 × 4 = 36
Step 5: Calculate the remaining work
Now we can find out how much work is left after A and B have worked together for 4 days.
- Remaining work = Total work - Work done in 4 days = 60 - 36 = 24
Step 6: Calculate how long it will take for B to complete the remaining work alone
Since B is the one who will complete the remaining work, we need to find out how long it will take B to finish the remaining 24 units of work.
- Time taken by B = Remaining work / Efficiency of B = 24 / 4 = 6 days
Final Answer
B will take 6 more days to complete the remaining work alone.
---
A can complete the work in 12 days, and B can complete it in 15 days. To find the total work, we can take the least common multiple (LCM) of their working days.
Efficiency is calculated as the total work divided by the time taken to complete that work.
- Efficiency of B = Total Work / Time taken by B = 60 / 15 = 4
When A and B work together, their efficiencies add up.
Now that we know their combined efficiency, we can calculate how much work they complete together in 4 days.
Now we can find out how much work is left after A and B have worked together for 4 days.
Since B is the one who will complete the remaining work, we need to find out how long it will take B to finish the remaining 24 units of work.
B will take 6 more days to complete the remaining work alone.
Topper's Solved these Questions
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 1)40videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 2)40videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - SOLVED EXAMPLE10videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions31videos
SPEED, TIME AND DISTANCE
Similar Questions
A, B and C can do a piece of work in 15, 12 and 20 days respectively. They started the work together, but C left after 2 days. In how many days will the remaining work be completed by A and B?
View SolutionA and B can do a piece of work in 45 and 40 days repectively. They began the work together but A left after some days and B finished the remaining work in 23 days. A left after
View Solution
Knowledge Check
- Question 1 - Select One
A and B can do a piece of work in 12 days and 15 days respectively. They began to work together but A left after 4 days. In how many more days would B alone complete the remaining work ?
A203 daysB253 daysC6 daysD5 days - Question 2 - Select One
A and B can complete a piece of work in 15 days and 10 days, respectively . They work together for 4 days and then B leavs. In how many days will A alone complete the remaining work ?
A6B8C5D10 - Question 3 - Select One
A, B and C, one can do a piece of work in 9, 12 and 18 days respectively. They all started the work together, but A left after 3 days. In how many days, was the remaining work completed?
A2B52C114D95
A and B can do a piece of work in 45 and 40 days respectively. They began the work together, but A leaves after some days and B finished the remaining work in 23 days. After how many days did A leave
View SolutionA and B can do a piece of work in 45 and 40 days respectively. They began the work together, but A leaves after some days and B finished the remaining work in 23 days. After how many days did A leave
View SolutionA and B can do a piece of work in 28 and 35 days respectively. They began to work together but A leaves after some time and B completed the remaining work in 17 days. After how many days did A leave ?
View SolutionA and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days, B had to leave and A alone completed the remaining work. The whole work was completed in:
View SolutionA and B can do a piece of work in 20 and 25 days respectively. They began to work together but A leaves after sometime and B completed remaining work in 17 days. After how many days did A leave?
View Solution