A and B can do a piece of work in 12 days and 15 days, respectively. They began to work together but B left after 4 days. In how many more days would B alone complete the remaining work?

A

20 3

B

25 3

C

24 5

D

20 5

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will calculate the work done by A and B, and then determine how many more days B would take to complete the remaining work after A and B have worked together for 4 days.

Step 1: Determine the total work
A can complete the work in 12 days, and B can complete it in 15 days. To find the total work, we can take the least common multiple (LCM) of their working days.

- LCM of 12 and 15 is 60.

Step 2: Calculate the efficiency of A and B
Efficiency is calculated as the total work divided by the time taken to complete that work.

- Efficiency of A = Total Work / Time taken by A = 60 / 12 = 5
- Efficiency of B = Total Work / Time taken by B = 60 / 15 = 4

Step 3: Calculate the combined efficiency of A and B
When A and B work together, their efficiencies add up.

- Combined efficiency of A and B = Efficiency of A + Efficiency of B = 5 + 4 = 9

Step 4: Calculate the work done by A and B in 4 days
Now that we know their combined efficiency, we can calculate how much work they complete together in 4 days.

- Work done in 4 days = Combined efficiency × Number of days = 9 × 4 = 36

Step 5: Calculate the remaining work
Now we can find out how much work is left after A and B have worked together for 4 days.

- Remaining work = Total work - Work done in 4 days = 60 - 36 = 24

Step 6: Calculate how long it will take for B to complete the remaining work alone
Since B is the one who will complete the remaining work, we need to find out how long it will take B to finish the remaining 24 units of work.

- Time taken by B = Remaining work / Efficiency of B = 24 / 4 = 6 days

Final Answer
B will take 6 more days to complete the remaining work alone.

---

|
Updated on:8/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B can do a piece of work in 12 days and 15 days respectively. They began to work together but A left after 4 days. In how many more days would B alone complete the remaining work ?

    A203 days
    B253 days
    C6 days
    D5 days
  • Question 2 - Select One

    A and B can complete a piece of work in 15 days and 10 days, respectively . They work together for 4 days and then B leavs. In how many days will A alone complete the remaining work ?

    A6
    B8
    C5
    D10
  • Question 3 - Select One

    A, B and C, one can do a piece of work in 9, 12 and 18 days respectively. They all started the work together, but A left after 3 days. In how many days, was the remaining work completed?

    A2
    B52
    C114
    D95