Working efficiencies of A and B for completing a piece of work are in the ratio 7 : 9. The number of days to be taken by them to complete the work will be in the ratio
9:7
7:9
4:7
7:4
The correct Answer is:D
To solve the problem, we need to determine the ratio of the time taken by A and B to complete the work based on their efficiencies.
1. Understand the Given Information:
- The working efficiencies of A and B are given in the ratio of 7:9.
- This means that for every 7 units of work A can do, B can do 9 units of work in the same time.
2. Define the Efficiency:
- Let the efficiency of A be 7 units of work per day.
- Let the efficiency of B be 9 units of work per day.
3. Determine the Total Work:
- Assume the total work to be done is a common multiple of their efficiencies. For simplicity, we can take the total work as the least common multiple (LCM) of 7 and 9, which is 63 units of work.
4. Calculate the Time Taken by A:
- Time taken by A to complete the work = Total Work / Efficiency of A
- Time taken by A = 63 / 7 = 9 days.
5. Calculate the Time Taken by B:
- Time taken by B to complete the work = Total Work / Efficiency of B
- Time taken by B = 63 / 9 = 7 days.
6. Establish the Ratio of Time Taken:
- The ratio of time taken by A and B = Time taken by A : Time taken by B = 9 : 7.
Final Answer:
The ratio of the number of days taken by A and B to complete the work is 9 : 7.
---
- The working efficiencies of A and B are given in the ratio of 7:9.
- This means that for every 7 units of work A can do, B can do 9 units of work in the same time.
- Let the efficiency of A be 7 units of work per day.
- Let the efficiency of B be 9 units of work per day.
- Assume the total work to be done is a common multiple of their efficiencies. For simplicity, we can take the total work as the least common multiple (LCM) of 7 and 9, which is 63 units of work.
- Time taken by A to complete the work = Total Work / Efficiency of A
- Time taken by A = 63 / 7 = 9 days.
- Time taken by B to complete the work = Total Work / Efficiency of B
- Time taken by B = 63 / 9 = 7 days.
- The ratio of time taken by A and B = Time taken by A : Time taken by B = 9 : 7.
The ratio of the number of days taken by A and B to complete the work is 9 : 7.
Topper's Solved these Questions
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 1)
40 Videos
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 2)
40 Videos
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - SOLVED EXAMPLE
10 Videos
- SPEED, TIME AND DISTANCEBOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions
31 Videos
Similar Questions
Knowledge Check
Working efficiencies of P and Q for completing a piece of work are in the ratio 3:4. The number of days to be taken by them to complete the work will be in the ratio
A3:2B2:3C3:4D4:3The rates of working of A and B are in the ratio 3:4.The number of days taken by them to finish the work are in the ratio
A3:4B9:16C4:3DNone of theseThe rates of working of A and B are In the ratio of 2:3. The number of days taken by each of them to finish the work is in the ratio:
A2:3B4:9C3:2D9:4
Ratio of efficiency of P and Q is 3 : 4. Find the ratio of number of days they will take to complete the work
View SolutionA is twice as efficient as B and they together can complete a piece of work in 24 days. Find the number of days, that A alone takes to compelete the work.
View SolutionIf a work can be completed by A in 30 days and by B in 60 days. Then, the number of days taken by them to complete the work, working together is
View SolutionIf a work can be completed by A in 30 days and by B in 60 days. Then, the number of days taken by them to complete the work, working together is
View SolutionA is thrice as efficient as B.A and B cam complete a piece of work in 12 days. Find the number of days in which A alone complete it.
View Solution