If 10 persons can do a job in 24 days, then 20 persons with twice the efficiency can do the same job in :
5 days
10 days
12 days
6 days
The correct Answer is:A
To solve the problem, we need to determine how long it will take for 20 persons with twice the efficiency to complete the same job that 10 persons can do in 24 days.
1. Identify the Work Done by 10 Persons:
- Given that 10 persons can complete the job in 24 days, we can denote the total work as W.
- The work done by 10 persons in 24 days can be represented as:
W=10 persons×24 days×1 efficiency unit=240 person-days
2. Determine the Efficiency of 20 Persons:
- If 20 persons have twice the efficiency, then their effective efficiency can be calculated as:
Efficiency of 20 persons=20 persons×2 (twice the efficiency)=40 efficiency units
3. Calculate the Time Taken by 20 Persons:
- We need to find how many days D it will take for these 20 persons with 40 efficiency units to complete the same amount of work W:
W=Efficiency×Time
- Therefore, we can set up the equation:
240 person-days=40 efficiency units×D
- Rearranging gives:
D=240 person-days40 efficiency units=6 days
4. Conclusion:
- Thus, 20 persons with twice the efficiency can complete the job in 6 days.
Final Answer:
The answer is 6 days.
- Given that 10 persons can complete the job in 24 days, we can denote the total work as W.
- The work done by 10 persons in 24 days can be represented as:
W=10 persons×24 days×1 efficiency unit=240 person-days
- If 20 persons have twice the efficiency, then their effective efficiency can be calculated as:
Efficiency of 20 persons=20 persons×2 (twice the efficiency)=40 efficiency units
- We need to find how many days D it will take for these 20 persons with 40 efficiency units to complete the same amount of work W:
W=Efficiency×Time
- Therefore, we can set up the equation:
240 person-days=40 efficiency units×D
- Rearranging gives:
D=240 person-days40 efficiency units=6 days
- Thus, 20 persons with twice the efficiency can complete the job in 6 days.
The answer is 6 days.
Topper's Solved these Questions
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 1)
40 Videos
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 2)
40 Videos
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - SOLVED EXAMPLE
10 Videos
- SPEED, TIME AND DISTANCEBOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions
31 Videos
Similar Questions
Knowledge Check
If 10 persons can do a job in 20 days, then 20 person with twice the efficiency can do the same job in :
A5 daysB40 daysC10 daysD20 daysIf 15 persons can do a job in 30 days, then 30 persons with twice the efficiency can do the same job in how many days ?
A. 7
B. 3 . 5
C. 5
D. 7 . 5ADBACBDCIf 10 people can do a job in 20 days, then 20 people with twice the efficiency can do the same job in
A5 daysB10 daysC20 daysD40 days
10 persons can do a job in X days. If 20 persons with twice the efficiency can do the same job in 5 days, then find the value of X?
A 40 B 15 C 20 D 30
View SolutionIf 3 persons can do a piece of work in 4 days, then 4 persons can do it in …… days.
View SolutionIf two persons, with equal abilities, can do two jobs in two days, then 100 persons with equal abilities can do 100 similar Jobs in
View SolutionIf two persons, with equal abilities, can do two jobs in two days, then 100 persons with equal abilities can do 100 similar Jobs in
View SolutionA and B together can finish a job in 24 days , while A,B and C together can finish can finish the same job in 8 days. C along will finish the job in
View Solution