A and B can do a piece of work in 20 and 25 days respectively. They began to work together but A leaves after sometime and B completed remaining work in 17 days. After how many days did A leave?
1425 days
9 days
8 days
359 days
The correct Answer is:C
To solve the problem, we need to find out how many days A worked before leaving, given that A and B can complete a piece of work in 20 and 25 days respectively, and B completed the remaining work in 17 days after A left.
1. Calculate the work done by A and B in one day:
- A's work rate = 1/20 (A can complete 1/20 of the work in one day)
- B's work rate = 1/25 (B can complete 1/25 of the work in one day)
2. Find the combined work rate of A and B:
- Combined work rate = A's work rate + B's work rate
- Combined work rate = 1/20 + 1/25
- To add these fractions, we need a common denominator. The least common multiple of 20 and 25 is 100.
- Convert the fractions:
- 1/20 = 5/100
- 1/25 = 4/100
- Combined work rate = 5/100 + 4/100 = 9/100
3. Determine the total work done by B in 17 days:
- Work done by B in 17 days = B's work rate × 17
- Work done by B = (1/25) × 17 = 17/25
4. Calculate the total work completed:
- Since the total work is considered as 1 (or 100%), the work completed by A and B together before A left can be calculated as:
- Total work = Work completed by A and B together + Work completed by B alone
- Let the work completed by A and B together before A left be W.
- Therefore, W + 17/25 = 1
- W = 1 - 17/25 = 8/25
5. Calculate the time A and B worked together:
- Let the number of days A and B worked together be x.
- The work done by A and B together in x days = (Combined work rate) × x
- (9/100) × x = 8/25
- To solve for x, we can multiply both sides by 100 to eliminate the fraction:
- 9x = (8/25) × 100
- 9x = 32
- x = 32/9
- x ≈ 3.56 days
Conclusion:
A worked together with B for approximately 3.56 days before leaving.
- A's work rate = 1/20 (A can complete 1/20 of the work in one day)
- B's work rate = 1/25 (B can complete 1/25 of the work in one day)
- Combined work rate = A's work rate + B's work rate
- Combined work rate = 1/20 + 1/25
- To add these fractions, we need a common denominator. The least common multiple of 20 and 25 is 100.
- Convert the fractions:
- 1/20 = 5/100
- 1/25 = 4/100
- Combined work rate = 5/100 + 4/100 = 9/100
- Work done by B in 17 days = B's work rate × 17
- Work done by B = (1/25) × 17 = 17/25
- Since the total work is considered as 1 (or 100%), the work completed by A and B together before A left can be calculated as:
- Total work = Work completed by A and B together + Work completed by B alone
- Let the work completed by A and B together before A left be W.
- Therefore, W + 17/25 = 1
- W = 1 - 17/25 = 8/25
- Let the number of days A and B worked together be x.
- The work done by A and B together in x days = (Combined work rate) × x
- (9/100) × x = 8/25
- To solve for x, we can multiply both sides by 100 to eliminate the fraction:
- 9x = (8/25) × 100
- 9x = 32
- x = 32/9
- x ≈ 3.56 days
A worked together with B for approximately 3.56 days before leaving.
Topper's Solved these Questions
- TIME AND WORKBOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-III
31 Videos
- TIME AND WORKBOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-IV
32 Videos
- TIME AND WORKBOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TEST YOURSELF
25 Videos
- TIME AND DISTANCEBOOK - KIRAN PUBLICATIONCHAPTER - TIME AND DISTANCEEXERCISE - Type -XI
74 Videos
- TRIGONOMETRY BOOK - KIRAN PUBLICATIONCHAPTER - TRIGONOMETRY EXERCISE - TEST YOURSELF
25 Videos
Similar Questions
A and B can do a piece of work in 28 and 35 days respectively. They began to work together but A leaves after some time and B completed the remaining work in 17 days. After how many days did A leave? 759days b. 8 days c. 9 days d. 1425days
View SolutionA and B can do a piece of work in 45 and 40 days respectively. They began the work together but A leaves after some days and B finished the remaining work in 23 days. After how many days did A leave?
View Solution
Knowledge Check
A and B can do a piece of work in 20 and 25 days respectively. They began to work together but A leaves after sometime and B completed remaining work in 17 days. After how many days did A leave?
A1425 daysB9 daysC8 daysD359 daysA and B can do a piece of work in 28 and 35 days respectively. They began to work together but A leaves after some time and B completed the remaining work in 17 days. After how many days did A leave ?
A1425 daysB9daysC8daysD759 daysA and B can do a piece of work in 30 and 36 days respectively. They began the work together but A leaves after some days and B finished the remaining wrok in 25 days. After how many days did A leave?
A5 daysB10 daysC11 daysD6 days
A and B can do a piece of work in 45 and 40 days respectively. They began the work together, but A leaves after some days and B finished the remaining work in 23 days. After how many days did A leave
View SolutionA and B can do a piece of work in 45 and 40 days respectively. They began the work together, but A leaves after some days and B finished the remaining work in 23 days. After how many days did A leave
View SolutionA and B can do a piece of work in 45 and 40 days respectively. They began the work together but A leaves after some das and B finished the remaining work in 23 days. After how many days did A leave?
View SolutionA and B can do a piece of work in 10 days and 15 days respectively. They started the work together but B left after sometime and A finished the remaining work in 5 days. After how many days from the start did B leave ?
View SolutionA and B can do a job in 15 days and 10 days, respectively. They began the work together but A leaves after some days and B finished the remaining job in 5 days. After how many days did A leave?
View Solution