If p men working p hours per day for p days produce p units of work, then the units of work produced by n men working n hours a day for n days is

A

p 2 n 2

B

p 3 n 2

C

n 2 p 2

D

n 3 p 2

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, we will use the concept of work done, which can be expressed using the formula:

Work=Number of Men×Number of Hours per Day×Number of Days

Step 1: Establish the Work Done by p Men
Given that p men working p hours per day for p days produce p units of work, we can express this as:

Work=p×p×p=p3

So, we have:

p3=p(1)

Step 2: Establish the Work Done by n Men
Now, we need to find the work done by n men working n hours a day for n days. Using the same formula for work, we have:

Work=n×n×n=n3

Step 3: Relate the Two Scenarios
From the first scenario, we know that p3 units of work corresponds to p units of work. Therefore, we can set up a ratio of the work done:

m1t1d1w1=m2t2d2w2

Where:
- m1=p (number of men in the first scenario)
- t1=p (hours per day in the first scenario)
- d1=p (days in the first scenario)
- w1=p (work done in the first scenario)
- m2=n (number of men in the second scenario)
- t2=n (hours per day in the second scenario)
- d2=n (days in the second scenario)
- w2 is the work done in the second scenario which we need to find.

Step 4: Substitute Values into the Equation
Substituting the values into the equation gives us:

p×p×pp=n×n×nw2

This simplifies to:

p2=n3w2

Step 5: Solve for w2
Rearranging the equation to solve for w2:

w2=n3p2

Final Result
Thus, the units of work produced by n men working n hours a day for n days is:

w2=n3p2

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • If 7 men working 7 hrs a day for each of 7 days produce 7 units of work, then the units of work produced by 5 men working 5 hrs a day for each of 5 days is 25

    A25343
    B12549
    C49125
    D34325
  • If x men, working x hours per day, can do x units of work in x days, then y mens, working y hours per day would be able to complete how many units of work in y days? x2y3 b. x3y2 c. x3y2 d. y3x2

    Ax2y3 units of work
    Bx3y2 units of work
    Cy2x3 units of work
    Dy3x2 units of work
  • If 9 men working 712 hours a day can finish a piece of work in 20 days, then how many days will be taken by 12 men, working 6 hours a day to finish the work? It is being given that 2 men of latter type work as much as 3 men of the former type. 11 b. 13 c. 912 d. 1212

    A12.5
    B13
    C9.5
    D11