If A and B together can finish a piece of work in 20 days, B and C in 10 days and C and A in 12 days, then A, B, C jointly can finish the same work in

A

427 days

B

30 days

C

847 days

D

760 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem, we need to find out how long A, B, and C together can finish the work based on the information given about their individual and combined efficiencies.

1. Understanding the Work Rates:
- Let the total work be represented in terms of units. We can assume the total work is 60 units (this is a common multiple of the days given).
- A and B together can finish the work in 20 days, so their combined work rate is:
Work rate of A and B=60 units20 days=3 units/day
- B and C together can finish the work in 10 days, so their combined work rate is:
Work rate of B and C=60 units10 days=6 units/day
- C and A together can finish the work in 12 days, so their combined work rate is:
Work rate of C and A=60 units12 days=5 units/day

2. Setting Up Equations:
- Let the work rates of A, B, and C be a, b, and c respectively.
- From the above work rates, we can set up the following equations:
a+b=3(1)
b+c=6(2)
c+a=5(3)

3. Solving the Equations:
- We can add all three equations:
(a+b)+(b+c)+(c+a)=3+6+5
This simplifies to:
2a+2b+2c=14
Dividing by 2 gives:
a+b+c=7(4)

4. Finding Individual Work Rates:
- Now we can use equation (4) to find the individual work rates:
- From equation (1):
c=7(a+b)=73=4
- From equation (2):
a=7(b+c)=76=1
- From equation (3):
b=7(c+a)=75=2
- Thus, we have:
a=1,b=2,c=4

5. Calculating the Combined Work Rate:
- Now, we can find the combined work rate of A, B, and C:
a+b+c=1+2+4=7 units/day

6. Calculating the Time Taken by A, B, and C Together:
- To find out how many days A, B, and C together can finish the work:
Time=Total WorkCombined Work Rate=60 units7 units/day=607 days
- This can be expressed as:
847 days

Final Answer:
A, B, and C together can finish the work in 847 days.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B can finish a work in 15 days, B and C in 20 days, while C and A in 30 days, then A alone can finish the work in

    A40 days
    B24 days
    C120 days
    D13 days
  • Question 2 - Select One

    A and B can do a piece of work in 18 days. B and C in 24 days, C and A in 36 days. Find the time in whichA, Band C working together can finish the work.

    A8
    B16
    C24
    D36
  • Question 3 - Select One

    A and B can do a piece of work in 10 days, B and C can do it in 12 days. C and A in 15 days. In how many days will c finish it alone?

    A30 days
    B24 days
    C60 days
    D40 days