To do a certain work B would take time thrice as long as A and C together and C twice as long as A and B together. The three men together complete the work in 10 days. The time taken by A to complete the work separately is: a 22 days b 24 days c 30 days d 20 days
Correct option b 24 days Explanation: According to question Since we know efficiency of persons will remain same. So we will balance it.Now we can see B’s efficiency is 3 units and C’s is 4 units and total is 12 units.So A’s efficiency is 12 – 4 – 3 = 5 units Total work = 10days × 12units A can complete separately in
Related Solutions
To do a certain work, B would take time thrice as long as A and C together and C twice as long as A and B together. The three men together complete the work in 10 days. The time taken by A to complete the work separately is
View SolutionA और B दिए गए किसी काम को 8 दिन में कार सकता है ,बी और C उसी काम को 12 दिनों में कर सकते है और A,B ,C उसे 6 दिन में पूरा में पूरा कर सकते है A और c द्वारा उस काम को पूरा करने में कितने दिन लगेंगे ?
View SolutionA takes three times as long as (B + C) together to complete a work. B takes four times as much as (A + C) together to complete a work. If all the three, working together can complete the work in 22 days, then find the number of days A, B and C alone will take to complete this work
View SolutionA piece of work can be completed in 18 days if A and B work together, in 24 days if B and C work together and in 36 days if A and C work together. The number of days required if all the three work together is
View SolutionB और C मिलकर एक काम को करने में जितना समय लेते हैं, उससे तीन गुणा अधिक समयA लेता है। A और C मिलकर उसी काम को करने में जितना समय लेते हैं, B उससे चार गुणा अधिक समय लेता है। यदि तीनों मिलकर उस काम को 24 दिन में पूरा कर सकते हैं, तो A के अकेले उस काम को करने में कितने दिन लगेंगे?
View SolutionTo complete a certain work, C working alone takes twice as long as A and B working together. A working alone takes 3 times as long as B and C working together. All the three together can complete the work in 5 days. How long would each take to complete th work individually?
View SolutionB takes two times as long as (A + C) together to complete a work. C takes three times as much as (A + B) together to complete a work. If all the three, working together can complete the work in 36 days, then find the number of days A, B and C alone will take to complete this work.
View SolutionA and B together can complete a work in 8 days and B and C together in 12 days. All of the three together can complete the work in 6 days. In how much time will A and C together complete the work?
View SolutionA and B together can do a piece of work in 24 days and B and C together can do that work in 30 days. If the efficiency of A is twice that of C, then in how many days will B alone complete the work?
View SolutionB works three times more slowly than A and C together. C can do it twice slowly than A and B. if they work together, the work is completed in 10 days. In how many days they will do it separately?
View SolutionA and B complete a piece of work in 24 days, B and C do the same work in 36 days, and A, B and C together finish it in 18 days. In how many days will :
A and C together, complete the work ?
View SolutionA and B together complete a work in days, B and C together complete same work in days, C and A together complete the same work days, In how many days A, B and C together can complete the same work?
View SolutionA and B together can complete a task in 10 days, B and C can do in 15 days, and C and A together can do it in 12 days. How long will they take to complete the task working together?
View SolutionA is as efficient as B and C together. Working together A and B can complete a work in 36 days and C alone can complete it in 60 days. A and C work together for 10 days. B alone will complete the remaining work in :
A की कार्य क्षमता B और C की कुल कार्य क्षमता के बराबर है | एक साथ कार्य करते हुए, A और B किसी कार्य को 36 दिनों में कर सकते हैं तथा C अकेले इस कार्य को 60 दिनों में कर सकता है | A और C 10 दिनों तक एक साथ कार्य करते हैं | B अकेले शेष कार्य कितने दिनों में समाप्त करेगा ?
View SolutionA तथा B मिलकर किसी कार्य को 24 दिन में B तथा C मिलकर 30 दिन में तथा C और A मिलकर 40 दिन में पूरा कर सकते है । वे अकेले-अकेले उस कार्य को कितने-कितने समय में पूरा करेंगे ?
View SolutionA can complete a piece of work in 18 days, B in 20 days and C in 30 days. B and C together start the work and are forced to leave after 2 days. The time taken by A alone to complete the remaining work is
View SolutionA is twice as efficient as B and B is thrice as efficient as C. Working together, they can finish a certain work in 5 days. If A and C worked together for 5 days then B alone would complete the remaining work in .......
View SolutionA and B can together complete a work in 16 days. B and C can together complete the same work in 24 days and A, B and C together can complete the work in 12 days. Find time taken by A and C to complete the work together.
(a)12 days
(b)14 days
(c)16 days
(d)18 days
View SolutionA can complete a work in 18 days, B in 20 days and C in 30 days. B and C together start the work but after 2 days, they left the work. How many days will a take to complete the remaining work ?
View SolutionB takes thrice as much time as (A and C) to do a piece of work. It takes twice as long as (A + B) to do the same work, if all three together do the work in 10 days, then in how much time they will do it separately
View Solution