A is twice as efficient as B and B is thrice as efficient as C. Working together, they can finish a certain work in 5 days. If A and C worked together for 5 days then B alone would complete the remaining work in .......

A

8 days

B

5 days

C

6 days

D

4 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, let's define the efficiencies of A, B, and C based on the information given.

Step 1: Define the efficiencies
Let the efficiency of C be x.
Then the efficiency of B, being thrice as efficient as C, is 3x.
And the efficiency of A, being twice as efficient as B, is 2×3x=6x.

Step 2: Calculate total efficiency
Now, the total efficiency of A, B, and C working together is:
Efficiency of A+Efficiency of B+Efficiency of C=6x+3x+x=10x

Step 3: Determine the work done in 5 days
According to the problem, A, B, and C can finish the work together in 5 days. Therefore, the total work (W) can be expressed as:
W=Total Efficiency×Time=10x×5=50x

Step 4: Work done by A and C in 5 days
Now, we need to find out how much work A and C can do together in 5 days. Their combined efficiency is:
Efficiency of A+Efficiency of C=6x+x=7x
Thus, the work done by A and C in 5 days is:
Work done by A and C=7x×5=35x

Step 5: Remaining work
The remaining work after A and C have worked for 5 days is:
Remaining Work=Total WorkWork done by A and C=50x35x=15x

Step 6: Time taken by B to complete the remaining work
Now, we need to find out how long it will take for B to complete the remaining work. The efficiency of B is 3x. The time taken by B to finish the remaining work is given by:
Time=Remaining WorkEfficiency of B=15x3x=5 days

Final Answer
Thus, B alone would complete the remaining work in 5 days.

---

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • A is as efficient as B and C together. Working together A and B can complete a work in 36 days and C alone can complete it in 60 days. A and C work together for 10 days. B alone will complete the remaining work in :
    A की कार्य क्षमता B और C की कुल कार्य क्षमता के बराबर है | एक साथ कार्य करते हुए, A और B किसी कार्य को 36 दिनों में कर सकते हैं तथा C अकेले इस कार्य को 60 दिनों में कर सकता है | A और C 10 दिनों तक एक साथ कार्य करते हैं | B अकेले शेष कार्य कितने दिनों में समाप्त करेगा ?

    A110 days
    B88 days
    C84 days
    D90 days
  • A is 40% more efficient than B and C is 20% less efficient than B. Working together, they can finish a work is 5 days. In how many days will A alone complete 70% that work?

    A9
    B7
    C10
    D8
  • A takes twice as much time as B and thrice as much time as C finish a piece of work. Working together, they can finish the work in 2 days. A can do the work alone in:

    A4 days
    B6 days
    C8 days
    D12 days