The ratio of the efficiencies of A, B and C to do a certain work is 7:3:5. Working together, they can complete the work in 21 days. A and C worked together for 5 days. The remaining work will be completed by B alone in :
54 days
45 days
60 days
85 days
The correct Answer is:D
To solve the problem step by step, we will follow the outlined process to find out how long it will take for B to complete the remaining work after A and C have worked together for 5 days.
Step 1: Determine the efficiencies of A, B, and C
The efficiencies of A, B, and C are given in the ratio 7:3:5. This means:
- Efficiency of A = 7x
- Efficiency of B = 3x
- Efficiency of C = 5x
Step 2: Calculate the total efficiency when A, B, and C work together
To find the total efficiency when A, B, and C work together, we add their efficiencies:
Total Efficiency=7x+3x+5x=15x
Step 3: Calculate the total work
It is given that A, B, and C together can complete the work in 21 days. Therefore, the total work can be calculated as:
Total Work=Total Efficiency×Number of Days=15x×21=315x
Step 4: Determine the efficiency of A and C working together
Now, we need to find out how much work A and C can do together in one day:
Efficiency of A and C=7x+5x=12x
Step 5: Calculate the work done by A and C in 5 days
If A and C work together for 5 days, the total work done by them is:
Work done by A and C=Efficiency of A and C×Number of Days=12x×5=60x
Step 6: Calculate the remaining work
Now, we can find out the remaining work after A and C have worked for 5 days:
Remaining Work=Total Work−Work done by A and C=315x−60x=255x
Step 7: Determine how long B will take to complete the remaining work
B's efficiency is 3x. To find out how many days B will take to complete the remaining work, we use the formula:
Days taken by B=Remaining WorkEfficiency of B=255x3x=85 days
Final Answer
B will take 85 days to complete the remaining work.
---
The efficiencies of A, B, and C are given in the ratio 7:3:5. This means:
- Efficiency of A = 7x
- Efficiency of B = 3x
- Efficiency of C = 5x
To find the total efficiency when A, B, and C work together, we add their efficiencies:
Total Efficiency=7x+3x+5x=15x
It is given that A, B, and C together can complete the work in 21 days. Therefore, the total work can be calculated as:
Total Work=Total Efficiency×Number of Days=15x×21=315x
Now, we need to find out how much work A and C can do together in one day:
Efficiency of A and C=7x+5x=12x
If A and C work together for 5 days, the total work done by them is:
Work done by A and C=Efficiency of A and C×Number of Days=12x×5=60x
Now, we can find out the remaining work after A and C have worked for 5 days:
Remaining Work=Total Work−Work done by A and C=315x−60x=255x
B's efficiency is 3x. To find out how many days B will take to complete the remaining work, we use the formula:
Days taken by B=Remaining WorkEfficiency of B=255x3x=85 days
B will take 85 days to complete the remaining work.
Topper's Solved these Questions
Similar Questions
The ratio of the efficiencies of A, B and C is 3: 5:1. Working together, they can complete a piece of work in 5 days. A and B work together for 3 days. The remaining work will be completed by C alone in?
View SolutionThe ratio of the efficiencies of A, B and C is 7:5:8. Working together, they can complete a piece of work in 42 days. B and C worked together for 21 days and the remaining work was completed by A alone. The whole work was completed in:
View Solution
Knowledge Check
To do a certain work the ratio of the efficincies of A, B and C is 7:5:6. Working together they can complete the same work in 35 days. B and C work together for 21 days. The remaining work will be completed by A alone in:
A60 daysB57 daysC54 daysD50 daysThe efficiencies of A, B and C are in the ratio 5: 3: 8. Working together they can complete a work in 30 days. A and B worked together for 20 days. The remaining work will be completed by C alone in:
A30 daysB32 daysC36 daysD40 daysThe efficiences of A , B and C are in ratio 5 : 3 : 8. Working together they can complete a work in 30 days. A and B worked together for 20 days. The remaining work will be completed by C alone in :
A, B और C की कार्य क्षमता 5 : 3 : 8 है| एक साथ कार्य करते हुए, वे किसी कार्य को 30 दिनों में कर सकते हैं | A और B ने 20 दिनों तक कार्य किया | शेष कार्य पूरा करने में C को अकेले कितने दिन लगेंगे?A40 daysB36 daysC30 daysD32 days
To do a certain work, the ratio of efficiency of A to that of B is 3:7.Working together, they can complete the work in 1012 days. They work together for 8 days. 60% of the remaining work will be completed by A alone in :
किसी कार्य को करने में, A की कार्य क्षमता तथा 8 की कार्य क्षमता का अनुपात 3: 7 है | एक साथ कार्य करते हुए, वे इस कार्य को 1012 दिनों में कर सकते हैं | वे 8 दिनों तक साथ कार्य करते हैं | शेष कार्य का 60% हिस्सा A अकेले कितने दिनों में पूरा करेगा ?
View SolutionTo do a certain work, the ratio of the efficiencies of X and Y is 5:4. Working together, they can complete the same work in 10 days. Y alone starts the work and leaves after 5 days. The remaining work will be completed by X alone in :
View SolutionThe ratio of the efficiencies of A, B and C is 7:5:4. Working together, they can finish work in 35 days. A and B work together for 28 days. The remaining work will be completed (in days) by C alone:
A, B और C की कार्य क्षमता का अनुपात 7 : 5 : 4 है | एक साथ कार्य करते हुए, वे किसी कार्य को 35 दिनों में समाप्त कर सकते हैं | A और B एक साथ 28 दिनों तक कार्य करते हैं | C शेष कार्य कितने दिनों में पूरा करेगा ?
View SolutionThe ratios of efficiencies of A and B of doing a certain work is 5 : 8. Working together they can complete the work in 20 days, A alone will complete 25% of that work in:
View SolutionThe ratio of the efficiencies of A, B, C is 7:5:4. Working togehter, they can finish a work in 35 days. A and B work together for 28 days. The remaining work will be completed (in days) by C alone.
View Solution