To do a certain work, the ratio of the efficiencies of X and Y is 5:4. Working together, they can complete the same work in 10 days. Y alone starts the work and leaves after 5 days. The remaining work will be completed by X alone in :
14 days
12 days
15 days
10 days
The correct Answer is:A
To solve the problem step by step, we will follow these calculations:
Step 1: Determine the efficiencies of X and Y
The ratio of the efficiencies of X and Y is given as 5:4. This means:
- Efficiency of X = 5 units of work per day
- Efficiency of Y = 4 units of work per day
Step 2: Calculate the total work
When X and Y work together, they complete the work in 10 days.
- The combined efficiency of X and Y = 5 + 4 = 9 units of work per day.
- Therefore, the total work = Combined efficiency × Total days = 9 units/day × 10 days = 90 units of work.
Step 3: Calculate the work done by Y in 5 days
Y starts the work and works for 5 days.
- Work done by Y in 5 days = Efficiency of Y × Number of days = 4 units/day × 5 days = 20 units of work.
Step 4: Calculate the remaining work
Now, we need to find out how much work is left after Y has worked for 5 days.
- Remaining work = Total work - Work done by Y = 90 units - 20 units = 70 units of work.
Step 5: Calculate the time taken by X to complete the remaining work
Now, X will complete the remaining work alone.
- Efficiency of X = 5 units of work per day.
- Time taken by X to complete the remaining work = Remaining work / Efficiency of X = 70 units / 5 units/day = 14 days.
Final Answer
The remaining work will be completed by X alone in 14 days.
---
The ratio of the efficiencies of X and Y is given as 5:4. This means:
- Efficiency of X = 5 units of work per day
- Efficiency of Y = 4 units of work per day
When X and Y work together, they complete the work in 10 days.
- The combined efficiency of X and Y = 5 + 4 = 9 units of work per day.
- Therefore, the total work = Combined efficiency × Total days = 9 units/day × 10 days = 90 units of work.
Y starts the work and works for 5 days.
- Work done by Y in 5 days = Efficiency of Y × Number of days = 4 units/day × 5 days = 20 units of work.
Now, we need to find out how much work is left after Y has worked for 5 days.
- Remaining work = Total work - Work done by Y = 90 units - 20 units = 70 units of work.
Now, X will complete the remaining work alone.
- Efficiency of X = 5 units of work per day.
- Time taken by X to complete the remaining work = Remaining work / Efficiency of X = 70 units / 5 units/day = 14 days.
The remaining work will be completed by X alone in 14 days.
Topper's Solved these Questions
Similar Questions
The efficiences of A , B and C are in ratio 5 : 3 : 8. Working together they can complete a work in 30 days. A and B worked together for 20 days. The remaining work will be completed by C alone in :
A, B और C की कार्य क्षमता 5 : 3 : 8 है| एक साथ कार्य करते हुए, वे किसी कार्य को 30 दिनों में कर सकते हैं | A और B ने 20 दिनों तक कार्य किया | शेष कार्य पूरा करने में C को अकेले कितने दिन लगेंगे?
View SolutionTo do a certain work, the ratio of efficiency of A to that of B is 3:7.Working together, they can complete the work in 1012 days. They work together for 8 days. 60% of the remaining work will be completed by A alone in :
किसी कार्य को करने में, A की कार्य क्षमता तथा 8 की कार्य क्षमता का अनुपात 3: 7 है | एक साथ कार्य करते हुए, वे इस कार्य को 1012 दिनों में कर सकते हैं | वे 8 दिनों तक साथ कार्य करते हैं | शेष कार्य का 60% हिस्सा A अकेले कितने दिनों में पूरा करेगा ?
View Solution
Knowledge Check
To do a certain work the ratio of the efficincies of A, B and C is 7:5:6. Working together they can complete the same work in 35 days. B and C work together for 21 days. The remaining work will be completed by A alone in:
A60 daysB57 daysC54 daysD50 daysThe ratio of the efficiencies of A, B and C to do a certain work is 7:3:5. Working together, they can complete the work in 21 days. A and C worked together for 5 days. The remaining work will be completed by B alone in :
A54 daysB45 daysC60 daysD85 daysThe ratio of the efficiencies of A, B and C is 3: 5:1. Working together, they can complete a piece of work in 5 days. A and B work together for 3 days. The remaining work will be completed by C alone in?
A18 daysB24 daysC21 daysD15 days
To do a certain work, the ratio of the efficiencies of A and B is 7 : 5. Working together, they can complete the same work in 1712 days. A alone will complete 60% of the same work in:
View SolutionThe efficiencies of A, B and C are in the ratio 5: 3: 8. Working together they can complete a work in 30 days. A and B worked together for 20 days. The remaining work will be completed by C alone in:
View SolutionThe ratio of the efficiencies of A, B and C is 7:5:4. Working together, they can finish work in 35 days. A and B work together for 28 days. The remaining work will be completed (in days) by C alone:
A, B और C की कार्य क्षमता का अनुपात 7 : 5 : 4 है | एक साथ कार्य करते हुए, वे किसी कार्य को 35 दिनों में समाप्त कर सकते हैं | A और B एक साथ 28 दिनों तक कार्य करते हैं | C शेष कार्य कितने दिनों में पूरा करेगा ?
View SolutionThe ratio of the efficiencies of A, B, C is 7:5:4. Working togehter, they can finish a work in 35 days. A and B work together for 28 days. The remaining work will be completed (in days) by C alone.
View SolutionTo complete a certain task, X is 40% more efficient than Y, and Z is 40% less efficient than Y. Working together, they can complete the task in 21 days. Y and Z together worked for 35 days. The remaining work will be completed by X alone in:
किसी निश्चित कार्य को पूरा करने के लिए, X, Y की तुलना में 40% अधिक कार्य कुशल है तथा Z, Y से 40% कम कार्य कुशल है| एक साथ कार्य करते हुए, वे इस कार्य को 21 दिनों में पूरा कर सकते हैं | Y तथा Z ने 35 दिनों तक एक साथ कार्य किया | शेष कार्य A अकेला कितने दिनों में पूरा करेगा ?
View Solution