A can do 40% of a work in 12 days, whereas B can do 60% of the same work in 15 days. Both work together for 10 days. C completes the remaining work alone in 4 days. A, B and C together will complete 28% of the same work in :
212 days
3 days
112 days
2 days
The correct Answer is:D
To solve the problem step by step, we will calculate the efficiencies of A, B, and C, the total work done, and then determine how long A, B, and C together will take to complete 28% of the work.
Step 1: Calculate the efficiencies of A and B
1. A's Efficiency:
- A can do 40% of the work in 12 days.
- Therefore, A can do 100% of the work in 12 days0.4=30 days.
- A's efficiency = 10030=103 % of work per day.
2. B's Efficiency:
- B can do 60% of the work in 15 days.
- Therefore, B can do 100% of the work in 15 days0.6=25 days.
- B's efficiency = 10025=4 % of work per day.
Step 2: Calculate the combined efficiency of A and B
- Combined efficiency of A and B = 103+4=103+123=223 % of work per day.
Step 3: Calculate the total work done by A and B in 10 days
- Work done by A and B in 10 days = 10×223=2203 % of work.
Step 4: Calculate the remaining work
- Total work = 100% (or 150 units).
- Work completed by A and B = 2203 %.
- Remaining work = 100−2203=300−2203=803 % of work.
Step 5: Calculate C's efficiency
- C completes the remaining work in 4 days.
- Therefore, C's efficiency = 80/34=203 % of work per day.
Step 6: Calculate the combined efficiency of A, B, and C
- Combined efficiency of A, B, and C = 103+4+203=10+12+203=423=14 % of work per day.
Step 7: Calculate the time taken to complete 28% of the work
- Work to be completed = 28% of total work = 28 %.
- Time taken = 2814=2 days.
Final Answer
A, B, and C together will complete 28% of the work in 2 days.
---
- A can do 40% of the work in 12 days.
- Therefore, A can do 100% of the work in 12 days0.4=30 days.
- A's efficiency = 10030=103 % of work per day.
- B can do 60% of the work in 15 days.
- Therefore, B can do 100% of the work in 15 days0.6=25 days.
- B's efficiency = 10025=4 % of work per day.
- Work completed by A and B = 2203 %.
- Remaining work = 100−2203=300−2203=803 % of work.
- Therefore, C's efficiency = 80/34=203 % of work per day.
- Time taken = 2814=2 days.
Topper's Solved these Questions
Similar Questions
A can do a work in 4 days while B can do that same work in 6 days. If they worked together, then that work would be completed in
View SolutionA and B can do a piece of work in 12 days and B and C can do the same piece of work in 16 days. A work for 5 days and B work for 7 days and C complete the remaining work in 13 days then in how many days C would complete the same work?
View Solution
Knowledge Check
A can do 45 of a work in 20 days and B can do 34 of the same work in 15 days. They work together for 10 days. C alone completes the remaining work in 1 day. B and C together can complete 34 of the same work in:
A8 daysB5 daysC4 daysD6 daysA can do 25 of a work in 12 days while B can do 6623% of the same work in 16 days. They work together for 10 days. B alone will complete the remaining work in
A6 daysB4 daysC8 daysD9 daysA can do 25 of a work in 6 days and B can do 23 of the same work in 12 days. A and B worked together for 6 days. C alone completed the remaining work in 8 days. A and C, working together, will complete the same work in:
A12 daysB9 daysC10 daysD8 days
A can do 13 of a work in 30 days. B can do 25 of the same work in 24 days. They worked together for 20 days. C completed the remaining work in 8 days. Working together A, B and C will complete the same work in:
View SolutionA can complete a work in 25 days, B can complete the same work in 20 days. If they work together for 10 days and remaining work is completed by C alone in 10 days. In how many days A, B, and C together can complete the same task?
View SolutionSurbhi can do a piece of work in 24 days. She completed 38 of the work and then left it. Amita complete the remaining work in 10 days. Working together, they will complete 125% of the same work in:
View SolutionA can complete one-third of a work in 10 days and B can do 35th of the same work in 24 days. They worked together for 10 days. The remaining work was completed by C alone in 15 days. In how many days can C alone do 23 of the same work?
View SolutionA can do 40% of a work in 6 days and B can do 30% of the same work in 3 days. They started the work together but B left after 2 days and A continued to work. In how many days was the entire work completed ?
A किसी कार्य का 40% भाग 6 दिनों में तथा B इसी कार्य का 30% भाग 3 दिनों में पूरा कर सकता है | उन्होंने एक साथ कार्य शुरू किया लेकिन 2 दिनों के बाद B हट गया और A ने कार्य जारी रखा | पूरा कार्य कितने दिनों में समाप्त हुआ ?
View Solution