A can do 40% of a work in 12 days, whereas B can do 60% of the same work in 15 days. Both work together for 10 days. C completes the remaining work alone in 4 days. A, B and C together will complete 28% of the same work in :

A

212 days

B

3 days

C

112 days

D

2 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, we will calculate the efficiencies of A, B, and C, the total work done, and then determine how long A, B, and C together will take to complete 28% of the work.

Step 1: Calculate the efficiencies of A and B

1. A's Efficiency:
- A can do 40% of the work in 12 days.
- Therefore, A can do 100% of the work in 12 days0.4=30 days.
- A's efficiency = 10030=103 % of work per day.

2. B's Efficiency:
- B can do 60% of the work in 15 days.
- Therefore, B can do 100% of the work in 15 days0.6=25 days.
- B's efficiency = 10025=4 % of work per day.

Step 2: Calculate the combined efficiency of A and B

- Combined efficiency of A and B = 103+4=103+123=223 % of work per day.

Step 3: Calculate the total work done by A and B in 10 days

- Work done by A and B in 10 days = 10×223=2203 % of work.

Step 4: Calculate the remaining work

- Total work = 100% (or 150 units).
- Work completed by A and B = 2203 %.
- Remaining work = 1002203=3002203=803 % of work.

Step 5: Calculate C's efficiency

- C completes the remaining work in 4 days.
- Therefore, C's efficiency = 80/34=203 % of work per day.

Step 6: Calculate the combined efficiency of A, B, and C

- Combined efficiency of A, B, and C = 103+4+203=10+12+203=423=14 % of work per day.

Step 7: Calculate the time taken to complete 28% of the work

- Work to be completed = 28% of total work = 28 %.
- Time taken = 2814=2 days.

Final Answer

A, B, and C together will complete 28% of the work in 2 days.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A can do 45 of a work in 20 days and B can do 34 of the same work in 15 days. They work together for 10 days. C alone completes the remaining work in 1 day. B and C together can complete 34 of the same work in:

    A8 days
    B5 days
    C4 days
    D6 days
  • A can do 25 of a work in 12 days while B can do 6623% of the same work in 16 days. They work together for 10 days. B alone will complete the remaining work in

    A6 days
    B4 days
    C8 days
    D9 days
  • A can do 25 of a work in 6 days and B can do 23 of the same work in 12 days. A and B worked together for 6 days. C alone completed the remaining work in 8 days. A and C, working together, will complete the same work in:

    A12 days
    B9 days
    C10 days
    D8 days