A can do 13 of a work in 30 days. B can do 25 of the same work in 24 days. They worked together for 20 days. C completed the remaining work in 8 days. Working together A, B and C will complete the same work in:

A

15 days

B

10 days

C

18 days

D

12 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, we will first determine the work rates of A, B, and C, and then find out how long it will take for A, B, and C to complete the work together.

Step 1: Calculate the total work in terms of work units.
A can do 13 of the work in 30 days. Therefore, the total work can be considered as 1 unit of work.

If A does 13 of the work in 30 days, then the total work (W) can be calculated as:
W=3×30=90 days of work

Step 2: Calculate the work rate of A.
A's work rate is:
Work rate of A=13 of work/30 days=190 of work per day

Step 3: Calculate the work rate of B.
B can do 25 of the work in 24 days. Therefore, B's work rate is:
Work rate of B=25 of work/24 days=2120=160 of work per day

Step 4: Calculate the combined work rate of A and B.
The combined work rate of A and B is:
Combined work rate of A and B=190+160
To add these fractions, find a common denominator, which is 180:
190=2180,160=3180
Thus,
Combined work rate of A and B=2180+3180=5180=136 of work per day

Step 5: Calculate the work done by A and B in 20 days.
In 20 days, A and B together will complete:
Work done by A and B in 20 days=20×136=2036=59 of the work

Step 6: Calculate the remaining work.
The remaining work after A and B have worked together for 20 days is:
Remaining work=159=49 of the work

Step 7: Calculate the work rate of C.
Let’s assume C can complete the remaining work in 8 days. Therefore, C's work rate is:
Work rate of C=49 of work/8 days=472=118 of work per day

Step 8: Calculate the combined work rate of A, B, and C.
Now, we can find the combined work rate of A, B, and C:
Combined work rate of A, B, and C=190+160+118
Finding a common denominator (which is 180):
190=2180,160=3180,118=10180
Thus,
Combined work rate of A, B, and C=2180+3180+10180=15180=112 of work per day

Step 9: Calculate the time taken by A, B, and C to complete the work together.
If A, B, and C work together, they will complete the work in:
Time=1 unit of work112 of work per day=12 days

Final Answer:
A, B, and C together will complete the work in 12 days.

---

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • A can do 25 of a work in 6 days and B can do 23 of the same work in 12 days. A and B worked together for 6 days. C alone completed the remaining work in 8 days. A and C, working together, will complete the same work in:

    A12 days
    B9 days
    C10 days
    D8 days
  • A can do 25 of a work in 12 days while B can do 6623% of the same work in 16 days. They work together for 10 days. B alone will complete the remaining work in

    A6 days
    B4 days
    C8 days
    D9 days
  • A can do 45 of a work in 20 days and B can do 34 of the same work in 15 days. They work together for 10 days. C alone completes the remaining work in 1 day. B and C together can complete 34 of the same work in:

    A8 days
    B5 days
    C4 days
    D6 days