A can do 13 of a work in 30 days. B can do 25 of the same work in 24 days. They worked together for 20 days. C completed the remaining work in 8 days. Working together A, B and C will complete the same work in:
15 days
10 days
18 days
12 days
The correct Answer is:D
To solve the problem step by step, we will first determine the work rates of A, B, and C, and then find out how long it will take for A, B, and C to complete the work together.
Step 1: Calculate the total work in terms of work units.
A can do 13 of the work in 30 days. Therefore, the total work can be considered as 1 unit of work.
If A does 13 of the work in 30 days, then the total work (W) can be calculated as:
W=3×30=90 days of work
Step 2: Calculate the work rate of A.
A's work rate is:
Work rate of A=13 of work/30 days=190 of work per day
Step 3: Calculate the work rate of B.
B can do 25 of the work in 24 days. Therefore, B's work rate is:
Work rate of B=25 of work/24 days=2120=160 of work per day
Step 4: Calculate the combined work rate of A and B.
The combined work rate of A and B is:
Combined work rate of A and B=190+160
To add these fractions, find a common denominator, which is 180:
190=2180,160=3180
Thus,
Combined work rate of A and B=2180+3180=5180=136 of work per day
Step 5: Calculate the work done by A and B in 20 days.
In 20 days, A and B together will complete:
Work done by A and B in 20 days=20×136=2036=59 of the work
Step 6: Calculate the remaining work.
The remaining work after A and B have worked together for 20 days is:
Remaining work=1−59=49 of the work
Step 7: Calculate the work rate of C.
Let’s assume C can complete the remaining work in 8 days. Therefore, C's work rate is:
Work rate of C=49 of work/8 days=472=118 of work per day
Step 8: Calculate the combined work rate of A, B, and C.
Now, we can find the combined work rate of A, B, and C:
Combined work rate of A, B, and C=190+160+118
Finding a common denominator (which is 180):
190=2180,160=3180,118=10180
Thus,
Combined work rate of A, B, and C=2180+3180+10180=15180=112 of work per day
Step 9: Calculate the time taken by A, B, and C to complete the work together.
If A, B, and C work together, they will complete the work in:
Time=1 unit of work112 of work per day=12 days
Final Answer:
A, B, and C together will complete the work in 12 days.
---
A can do 13 of the work in 30 days. Therefore, the total work can be considered as 1 unit of work.
W=3×30=90 days of work
A's work rate is:
Work rate of A=13 of work/30 days=190 of work per day
B can do 25 of the work in 24 days. Therefore, B's work rate is:
Work rate of B=25 of work/24 days=2120=160 of work per day
The combined work rate of A and B is:
Combined work rate of A and B=190+160
To add these fractions, find a common denominator, which is 180:
190=2180,160=3180
Thus,
Combined work rate of A and B=2180+3180=5180=136 of work per day
In 20 days, A and B together will complete:
Work done by A and B in 20 days=20×136=2036=59 of the work
The remaining work after A and B have worked together for 20 days is:
Remaining work=1−59=49 of the work
Let’s assume C can complete the remaining work in 8 days. Therefore, C's work rate is:
Work rate of C=49 of work/8 days=472=118 of work per day
Now, we can find the combined work rate of A, B, and C:
Combined work rate of A, B, and C=190+160+118
Finding a common denominator (which is 180):
190=2180,160=3180,118=10180
Thus,
Combined work rate of A, B, and C=2180+3180+10180=15180=112 of work per day
If A, B, and C work together, they will complete the work in:
Time=1 unit of work112 of work per day=12 days
A, B, and C together will complete the work in 12 days.
Similar Questions
A can do a work in 4 days while B can do that same work in 6 days. If they worked together, then that work would be completed in
View SolutionA and B can do a piece of work in 12 days and B and C can do the same piece of work in 16 days. A work for 5 days and B work for 7 days and C complete the remaining work in 13 days then in how many days C would complete the same work?
View Solution
Knowledge Check
A can do 25 of a work in 6 days and B can do 23 of the same work in 12 days. A and B worked together for 6 days. C alone completed the remaining work in 8 days. A and C, working together, will complete the same work in:
A12 daysB9 daysC10 daysD8 daysA can do 25 of a work in 12 days while B can do 6623% of the same work in 16 days. They work together for 10 days. B alone will complete the remaining work in
A6 daysB4 daysC8 daysD9 daysA can do 45 of a work in 20 days and B can do 34 of the same work in 15 days. They work together for 10 days. C alone completes the remaining work in 1 day. B and C together can complete 34 of the same work in:
A8 daysB5 daysC4 daysD6 days
A can do 40% of a work in 12 days, whereas B can do 60% of the same work in 15 days. Both work together for 10 days. C completes the remaining work alone in 4 days. A, B and C together will complete 28% of the same work in :
View SolutionA can do 35th of a work in 12 days, B can do 13rd of that work in 15 days. They worked together for 12 days and then A left the work , B alone will complete the remaining work in?
View SolutionSurbhi can do a piece of work in 24 days. She completed 38 of the work and then left it. Amita complete the remaining work in 10 days. Working together, they will complete 125% of the same work in:
View SolutionA can complete one-third of a work in 10 days and B can do 35th of the same work in 24 days. They worked together for 10 days. The remaining work was completed by C alone in 15 days. In how many days can C alone do 23 of the same work?
View SolutionA can do a work in 25 days and B can do the same work in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the work?
View Solution