Doubtnut Promotions Sticky

To do a certain work, the ratio of the efficiencies of A and B is 7 : 5. Working together, they can complete the same work in 1712 days. A alone will complete 60% of the same work in:

A

21 days

B

16 days

C

15 days

D

18 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:D

|
Answer

Step by step video, text & image solution for To do a certain work, the ratio of the efficiencies of A and B is 7 : 5. Working together, they can complete the same work in 17(1)/(2) days. A alone will complete 60% of the same work in: by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Similar Practice Problems

  • Question 1 - Select One

    The ratio of the efficiencies of A, B and C is 4 : 5 : 3. Working together, they can complete that work in 25 days. A and C together will complete 35% of that work in:
    A, B तथा C की कार्य क्षमता का अनुपात 4 : 5 : 3 है | एक साथ कार्य करते हुए वे 25 दिनों में कार्य पूरा कर लेते हैं | इस कार्य का 35% भाग A और C कितने दिनों में पूरा करेंगे ?

    A12 days
    B10 days
    C18 days
    D15 days
  • Question 1 - Select One

    The ratios of efficiencies of A and B of doing a certain work is 5 : 8. Working together they can complete the work in 20 days, A alone will complete 25% of that work in:

    A14 days
    B12 days
    C11 days
    D13 days
  • Question 1 - Select One

    To do a certain work the ratio of the efficincies of A, B and C is 7:5:6. Working together they can complete the same work in 35 days. B and C work together for 21 days. The remaining work will be completed by A alone in:

    A60 days
    B57 days
    C54 days
    D50 days
  • Question 1 - Select One

    To do a certain work, the ratio of the efficiencies of X and Y is 5:4. Working together, they can complete the same work in 10 days. Y alone starts the work and leaves after 5 days. The remaining work will be completed by X alone in :

    A14 days
    B12 days
    C15 days
    D10 days
  • Question 1 - Select One

    To do a certain work, the ratio of efficiency of A to that of B is 3:7.Working together, they can complete the work in 1012 days. They work together for 8 days. 60% of the remaining work will be completed by A alone in :
    किसी कार्य को करने में, A की कार्य क्षमता तथा 8 की कार्य क्षमता का अनुपात 3: 7 है | एक साथ कार्य करते हुए, वे इस कार्य को 1012 दिनों में कर सकते हैं | वे 8 दिनों तक साथ कार्य करते हैं | शेष कार्य का 60% हिस्सा A अकेले कितने दिनों में पूरा करेगा ?

    A512 days
    B5 days
    C612 days
    D4 days
  • Question 1 - Select One

    The efficiencies of A, B and C are in the ratio 2 : 5 : 7 working together, they can complete a work in 10 days. In how many days will, A alone be able to complete 30% of that work?
    A, B और C की कार्य क्षमता 2 : 5: 7 के अनुपात में है | एक साथ कार्य करते हुए वे किसी कार्य को 10 दिनों में समाप्त कर सकते हैं | इस कार्य का 30% भाग समाप्त करने में A को अकेले कितना समय (दिन ) लगेगा ?

    A20
    B28
    C30
    D21
  • Question 1 - Select One

    The ratio of the efficiencies of A, B and C to do a certain work is 7:3:5. Working together, they can complete the work in 21 days. A and C worked together for 5 days. The remaining work will be completed by B alone in :

    A54 days
    B45 days
    C60 days
    D85 days
  • Question 1 - Select One

    The ratio of the efficiencies of A, B and C is 7:5:8. Working together, they can complete a piece of work in 42 days. B and C worked together for 21 days and the remaining work was completed by A alone. The whole work was completed in:

    A96 days
    B99 days
    C102 days
    DNone of these
  • Question 1 - Select One

    The ratio of the efficiencies of A, B and C is 3: 5:1. Working together, they can complete a piece of work in 5 days. A and B work together for 3 days. The remaining work will be completed by C alone in?

    A18 days
    B24 days
    C21 days
    D15 days

Similar Questions