A and B together can complete a work in 8 days and B and C together in 12 days. All of the three together can complete the work in 6 days. In how much time will A and C together complete the work?

A

8 days

B

10 days

C

12 days

D

20 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we will first determine the work rates of A, B, and C based on the information provided.

Step 1: Determine the work done by A and B together.
A and B together can complete the work in 8 days. Therefore, the amount of work they can do in one day is:
Work rate of A + B=18 (work per day)
If we consider the total work to be 24 units, then:
Work done by A + B in 1 day=248=3 units

Step 2: Determine the work done by B and C together.
B and C together can complete the work in 12 days. Therefore, their work rate is:
Work rate of B + C=112 (work per day)
Thus, the work done by B and C in one day is:
Work done by B + C in 1 day=2412=2 units

Step 3: Determine the work done by A, B, and C together.
A, B, and C together can complete the work in 6 days. Therefore, their work rate is:
Work rate of A + B + C=16 (work per day)
Thus, the work done by A, B, and C in one day is:
Work done by A + B + C in 1 day=246=4 units

Step 4: Set up equations for the work rates.
From the above calculations, we have:
- A + B = 3 units/day
- B + C = 2 units/day
- A + B + C = 4 units/day

Step 5: Find the work done by A and C together.
To find the work done by A and C together, we can use the following relationship:
(A + C)=(A + B + C)(B)
We can express B in terms of the other equations.

From A + B + C = 4 units and B + C = 2 units, we can find B:
B=(A+B+C)(A+C)=4(A+C)
Now, substituting the value of B from B + C:
B+C=2(4(A+C))+C=2
This simplifies to:
4A=2A=2 units

Step 6: Substitute to find C.
Now substituting A back into A + B = 3:
2+B=3B=1 unit
Now substituting B into B + C = 2:
1+C=2C=1 unit

Step 7: Calculate A + C.
Now we can find A + C:
A+C=2+1=3 units/day

Step 8: Calculate the time taken by A and C to complete the work.
To find the time taken by A and C together to complete the work:
Time=Total WorkWork Rate of A + C=243=8 days

Final Answer:
A and C together can complete the work in 8 days.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A and B can together complete a work in 16 days. B and C can together complete the same work in 24 days and A, B and C together can complete the work in 12 days. Find time taken by A and C to complete the work together.
    (a)12 days
    (b)14 days
    (c)16 days
    (d)18 days

    A12 days
    B14 days
    C16 days
    D18 days
  • A and B together complete a work in 20 days, B and C together complete same work in 30 days, C and A together complete the same work 24 days, In how many days A, B and C together can complete the same work?

    A8
    B16
    C12
    D15
  • A and C together can complete a work in 120 days, C and E together can complete the same work in 80 days and A and E together can complete the same work in 160 days. In how many days A, C and E together can complete the same work?

    A12013 days
    B48013 days
    C24013 days
    D96013 days