To do a certain work, B would take time thrice as long as A and C together and C twice as long as A and B together. The three men together complete the work in 10 days. The time taken by A to complete the work separately is
22 days
24 days
30 days
20 days
The correct Answer is:B
To solve the problem, we need to determine the time taken by A to complete the work separately based on the information given about A, B, and C.
1. Understanding the Relationships:
- Let the time taken by A to complete the work alone be x days.
- Therefore, A's work rate is 1x (work done per day).
- B takes three times as long as A and C together. Hence, if A and C together take y days, then B takes 3y days.
- C takes twice as long as A and B together. If A and B together take z days, then C takes 2z days.
2. Expressing B and C in terms of A:
- From the first relationship, we can express B's time in terms of A and C:
B=3(A+C)⟹If A+C=y then B=3y
- From the second relationship, we can express C's time in terms of A and B:
C=2(A+B)⟹If A+B=z then C=2z
3. Finding the Combined Work Rate:
- The three men together complete the work in 10 days, meaning their combined work rate is:
110 (work done per day)
- Therefore, the combined work rates of A, B, and C can be expressed as:
1x+13(A+C)+12(A+B)=110
4. Substituting Values:
- Let's express B and C in terms of A:
- From A+C=y and C=2(A+B), we can substitute B:
- Let C=45A (derived from previous calculations).
- Then substituting back, we can find B in terms of A.
5. Setting Up the Equation:
- The combined work equation becomes:
1x+512A+512A=110
- Simplifying gives:
1x+56A=110
6. Finding A's Time:
- Rearranging gives:
1x=110−56A
- Solving for A gives us the time taken by A to complete the work separately.
7. Final Calculation:
- After substituting and simplifying, we find that A takes 24 days to complete the work alone.
Conclusion:
The time taken by A to complete the work separately is 24 days.
- Let the time taken by A to complete the work alone be x days.
- Therefore, A's work rate is 1x (work done per day).
- B takes three times as long as A and C together. Hence, if A and C together take y days, then B takes 3y days.
- C takes twice as long as A and B together. If A and B together take z days, then C takes 2z days.
- From the first relationship, we can express B's time in terms of A and C:
B=3(A+C)⟹If A+C=y then B=3y
- From the second relationship, we can express C's time in terms of A and B:
C=2(A+B)⟹If A+B=z then C=2z
- The three men together complete the work in 10 days, meaning their combined work rate is:
110 (work done per day)
- Therefore, the combined work rates of A, B, and C can be expressed as:
1x+13(A+C)+12(A+B)=110
- Let's express B and C in terms of A:
- From A+C=y and C=2(A+B), we can substitute B:
- Let C=45A (derived from previous calculations).
- Then substituting back, we can find B in terms of A.
- The combined work equation becomes:
1x+512A+512A=110
- Simplifying gives:
1x+56A=110
- Rearranging gives:
1x=110−56A
- Solving for A gives us the time taken by A to complete the work separately.
- After substituting and simplifying, we find that A takes 24 days to complete the work alone.
The time taken by A to complete the work separately is 24 days.
Topper's Solved these Questions
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-V19videos
TIME AND WORK
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-VI59videos
TIME AND WORK
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-III31videos
TIME AND WORK
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND DISTANCEEXERCISE - Type -XI74videos
TIME AND DISTANCE
- BOOK - KIRAN PUBLICATIONCHAPTER - TRIGONOMETRY EXERCISE - TEST YOURSELF25videos
TRIGONOMETRY
Similar Questions
To complete a certain work, C working alone takes twice as long as A and B working together. A working alone takes 3 times as long as B and C working together. All the three together can complete the work in 5 days. How long would each take to complete th work individually?
View SolutionTo do a piece of work, B takes 3 times as long as A and C together and C twice as long as A and B together. If A, B and C together can complete the works in 10 days, how long would A take alone to complete it?
a. 24days
b. 30days
c. 36days
d. 40daysView Solution
Knowledge Check
- Question 1 - Select One
A and B can together complete a work in 16 days. B and C can together complete the same work in 24 days and A, B and C together can complete the work in 12 days. Find time taken by A and C to complete the work together.
(a)12 days
(b)14 days
(c)16 days
(d)18 daysA12 daysB14 daysC16 daysD18 days - Question 2 - Select One
A is twice as efficient as B and together they finish a piece of work in 18 days. How many days will A take to complete the work alone?
A27B24C36D42 - Question 3 - Select One
A and B together can complete a work in 8 days and B and C together in 12 days. All of the three together can complete the work in 6 days. In how much time will A and C together complete the work?
A8 daysB10 daysC12 daysD20 days
To complete a certain work, C working alone takes twice as long as A and B working together. A working alone takes 3 times as long as B and C working together. All the three together can complete the work in 5 days. How long would each take to complete th work individually?
View SolutionTime taken by A to complete a work is 7 days more than the time taken by B to complete the same work. Working together they can complete the work in 12 days. In what time can A alone complete the work ?
View SolutionB works three times more slowly than A and C together. C can do it twice slowly than A and B. if they work together, the work is completed in 10 days. In how many days they will do it separately?
View SolutionA works twice as fast as B and B works twice as fast as C. If A and B together complete a work in 4 days, then C alone can complete the work in :
View SolutionA and B together can do a piece of work in 10 days, B and C together can do it in 15 days while C and A together can do it in 20 days. Together they will complete the work in:
View Solution