Two workers A and B working together completed a job in 5 days. If A worked twice as efficiently as he actually did and B worked 13 as efficiently as he actually did, the work would have been completed in 3 days. To complete the job alone. A would require

A

515 days

B

614 days

C

712 days

D

834 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we will define the efficiencies of workers A and B, set up equations based on the given information, and solve for the time A would take to complete the job alone.

1. Define Variables:
Let the efficiency of worker A be x (work done per day) and the efficiency of worker B be y (work done per day).

2. Total Work Done:
Since A and B together complete the job in 5 days, the total work W can be expressed as:
W=(x+y)5

3. Modified Efficiencies:
If A worked twice as efficiently, his new efficiency would be 2x. If B worked at one-third of his efficiency, his new efficiency would be y3.

4. New Work Completion Time:
With these modified efficiencies, they would complete the work in 3 days:
W=(2x+y3)3

5. Set Up Equations:
From the two expressions for W, we can set them equal to each other:
(x+y)5=(2x+y3)3

6. Simplifying the Equation:
Expanding both sides gives:
5x+5y=6x+y1
Rearranging terms leads to:
5yy1=6x5x
This simplifies to:
4y=x

7. Substituting Back:
Substitute x=4y back into the equation for W:
W=(4y+y)5=5y5=25y

8. Finding Time for A Alone:
To find how long A would take to complete the work alone:
Time for A=Wx=25y4y=254=6.25 days

Final Answer:
A would require 614 days to complete the job alone.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Two workers A and B working together completed a job in 5
    days. If A worked twice as efficiently as he actually did and
    B worked 1/3 as efficiently as he actually did, the work would
    have completed in 3 days. Fine the time for A to complete
    the job alone.

    A614 days
    B534 days
    C5 days
    D3 days
  • Two workers A and B working together completed a job in 5
    days. If A worked twice as efficiently as he actually did and
    B worked 1/3 as efficiently as he actually did, the work would
    have completed in 3 days. Fine the time for A to complete
    the job alone.

    A612
    B614
    C634
    D1212
  • Bunty and Babli working together completed a job in 8 days. If Bunty worked twice efficiently as he actually did and Babli worked as efficiently as she actually did, the work would have been completed in 6 days. Find the time taken by Bunty to complete the job alone :

    A8 days
    B3835 days
    C152
    D1313