A is 1.5 times efficient than B therefore takes 8 days less than B to complete a work. If A and B work on alternate days and A works on first day, then in how many days the work will be completed?
17
19
19.5
21
The correct Answer is:B
To solve the problem step by step, we will break it down into manageable parts.
Step 1: Determine the time taken by A and B to complete the work.
Let the time taken by B to complete the work be x days. Since A is 1.5 times more efficient than B, the time taken by A to complete the work will be x1.5=2x3.
According to the problem, A takes 8 days less than B to complete the work:
2x3=x−8
Step 2: Solve the equation for x.
To eliminate the fraction, multiply the entire equation by 3:
2x=3x−24
Rearranging gives:
3x−2x=24⟹x=24
Step 3: Calculate the time taken by A.
Now that we have x=24, we can find the time taken by A:
Time taken by A=2x3=2×243=16 days
Step 4: Determine the work done by A and B in one day.
The work done by A in one day is:
Work done by A in one day=116
The work done by B in one day is:
Work done by B in one day=124
Step 5: Calculate the total work done in two days.
Since A and B work on alternate days, we can calculate the work done in 2 days (A works on the first day and B on the second day):
Work done in 2 days=116+124
To add these fractions, find a common denominator (which is 48):
116=348,124=248
Thus,
Work done in 2 days=348+248=548
Step 6: Calculate the total number of days required to complete the work.
Let W be the total work, which we can consider as 1 unit of work. The number of 2-day cycles needed to complete the work is:
Number of 2-day cycles=1548=485=9.6 cycles
This means it will take 9 complete cycles (18 days) and a fraction of a cycle to complete the work.
Step 7: Calculate the remaining work after 9 cycles.
After 9 cycles (18 days), the work done is:
Work done in 18 days=9×548=4548
The remaining work is:
1−4548=348=116
Step 8: Determine how long it will take to finish the remaining work.
Since A works on the first day of the next cycle, A will complete the remaining work of 116 in 1 day.
Final Calculation: Total days taken.
Thus, the total days taken to complete the work is:
Total days=18+1=19 days
Conclusion:
The work will be completed in 19 days.
---
Let the time taken by B to complete the work be x days. Since A is 1.5 times more efficient than B, the time taken by A to complete the work will be x1.5=2x3.
2x3=x−8
To eliminate the fraction, multiply the entire equation by 3:
2x=3x−24
Rearranging gives:
3x−2x=24⟹x=24
Now that we have x=24, we can find the time taken by A:
Time taken by A=2x3=2×243=16 days
The work done by A in one day is:
Work done by A in one day=116
The work done by B in one day is:
Work done by B in one day=124
Since A and B work on alternate days, we can calculate the work done in 2 days (A works on the first day and B on the second day):
Work done in 2 days=116+124
To add these fractions, find a common denominator (which is 48):
116=348,124=248
Thus,
Work done in 2 days=348+248=548
Let W be the total work, which we can consider as 1 unit of work. The number of 2-day cycles needed to complete the work is:
Number of 2-day cycles=1548=485=9.6 cycles
This means it will take 9 complete cycles (18 days) and a fraction of a cycle to complete the work.
After 9 cycles (18 days), the work done is:
Work done in 18 days=9×548=4548
The remaining work is:
1−4548=348=116
Since A works on the first day of the next cycle, A will complete the remaining work of 116 in 1 day.
Thus, the total days taken to complete the work is:
Total days=18+1=19 days
The work will be completed in 19 days.
Topper's Solved these Questions
- TIME AND WORKBOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-V
19 Videos
- TIME AND WORKBOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-VI
59 Videos
- TIME AND WORKBOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-III
31 Videos
- TIME AND DISTANCEBOOK - KIRAN PUBLICATIONCHAPTER - TIME AND DISTANCEEXERCISE - Type -XI
74 Videos
- TRIGONOMETRY BOOK - KIRAN PUBLICATIONCHAPTER - TRIGONOMETRY EXERCISE - TEST YOURSELF
25 Videos
Similar Questions
A and B can do a piece of work in 6 days and 9 days respectively, they work on alternative days starting with A on the first day. In how many days will the work be completed ?
View SolutionIf man A complete a work in 10 days & man B complete the same work in 15 days , in how many days the work is completed if they work together ?
View Solution
Knowledge Check
A is three times efficient than B. If A takes 24 days less than B to complete the work, then find in how many days A and B together can complete the whole work.
A9 daysB12 daysC18 daysD24 daysP is four times as efficient as Q. P can complete a work in 45 days less than Q. If both of them work together, then in how many days the work will be completed?
A10B12C15D30A is twice as good a workman as B and therefore A takes 6 days less than B to finish the work individually. If A and B working complete together the work in 4 days, then how many days are required by B to complete the work alone?
A12B18C8D6
A and B can do a piece of work in 6 days and 9 days respectively, they work on alternative days starting with A on the first day. In how many days will the work be completed ?
View SolutionA and B can do a work in 30 days and 10 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed?
View SolutionA is twice as good a workman as B and therefore A takes 6 days less than B to finish the work individually. If A and B working complete together the work in 4 days, then how many days are required by B to complete the work alone?
View SolutionA can do a work in 6 days, B can do it in 8 days and C can complete it in 12 days. If A starts the work and they work in alternatively, then in how many days, the work will be completed?
View SolutionA can complete a work in 10 days and B can complete it in 15 days. If A starts the work and 5 days later B also joins him, then in how many days the work will be finished?
View Solution