A and B together can do a piece of work in 10 days, B and C together can do it in 15 days while C and A together can do it in 20 days. Together they will complete the work in:
12 days
315 days
16 days
9313 days
The correct Answer is:C
To solve the problem step by step, we will first determine the work done by each pair of workers (A and B, B and C, C and A) and then find the total work done by A, B, and C together.
1. Identify the work done by each pair:
- A and B together can complete the work in 10 days.
- B and C together can complete the work in 15 days.
- C and A together can complete the work in 20 days.
2. Calculate the work done by each pair in one day:
- Work done by A and B in one day = 110
- Work done by B and C in one day = 115
- Work done by C and A in one day = 120
3. Set up equations for the work done:
- Let the work done by A in one day be a.
- Let the work done by B in one day be b.
- Let the work done by C in one day be c.
From the information given:
- a+b=110 (Equation 1)
- b+c=115 (Equation 2)
- c+a=120 (Equation 3)
4. Add all three equations:
(a+b)+(b+c)+(c+a)=110+115+120
This simplifies to:
2a+2b+2c=110+115+120
5. Calculate the right-hand side (RHS):
- Find the LCM of 10, 15, and 20, which is 60.
- Convert each fraction:
- 110=660
- 115=460
- 120=360
Thus,
110+115+120=6+4+360=1360
6. Substituting back:
2(a+b+c)=1360
Therefore,
a+b+c=13120
7. Calculate the total work done by A, B, and C together in one day:
- The total work done by A, B, and C together in one day is 13120.
8. Calculate the number of days they will take to complete the work together:
- The total time taken to complete the work is the reciprocal of the work done in one day:
Time=113120=12013
9. Convert to mixed number:
- 12013=9313 days.
Final Answer:
Together, A, B, and C will complete the work in 9313 days.
- A and B together can complete the work in 10 days.
- B and C together can complete the work in 15 days.
- C and A together can complete the work in 20 days.
- Work done by A and B in one day = 110
- Work done by B and C in one day = 115
- Work done by C and A in one day = 120
- Let the work done by A in one day be a.
- Let the work done by B in one day be b.
- Let the work done by C in one day be c.
- a+b=110 (Equation 1)
- b+c=115 (Equation 2)
- c+a=120 (Equation 3)
(a+b)+(b+c)+(c+a)=110+115+120
This simplifies to:
2a+2b+2c=110+115+120
- Find the LCM of 10, 15, and 20, which is 60.
- Convert each fraction:
- 110=660
- 115=460
- 120=360
110+115+120=6+4+360=1360
2(a+b+c)=1360
Therefore,
a+b+c=13120
- The total work done by A, B, and C together in one day is 13120.
- The total time taken to complete the work is the reciprocal of the work done in one day:
Time=113120=12013
- 12013=9313 days.
Together, A, B, and C will complete the work in 9313 days.
Similar Questions
A and B together can do a piece of work in 36 days, B and C together can do it in 24 days. A and C together can do it in 18 days. The three working together can finish the work in
View SolutionA and B together can do a piece of work in 12 days; B and C can do it in 20 days while C and A can do it in 15 days. A, B and C all working together can do it in
View Solution
Knowledge Check
A and B together can do a piece of work in 10 days, B and C together can do it in 15 days while C and A together can do it in 20 days. They work together for 8 days. C alone will complete the remaining work in:
A और B एक साथ किसी कार्य को 10 दिनों में कर सकते हैं |B और C इसे एक साथ 15 दिनों में तथा C और A इसे एक साथ 20 दिनों में कर सकते हैं | वे 8 दिनों तक साथ कार्य करते हैं | शेष कार्य पूरा करने में C को अकेले कितने दिन लगेंगेA12 daysB315 daysC16 daysD513 daysA can do a piece of work in 4 days. B and C together can do it in 3 days, while A and C together can do it in 2 days. How many days will B take to do the work alone?
A8 daysB12 daysC10 daysD16 daysA and B together can complete a task in 10 days, B and C can do in 15 days, and C and A together can do it in 12 days. How long will they take to complete the task working together?
A12 daysB8 daysC14 daysD10 days
A and B together can do a work in 8 days, B and C together in 6 days while C and A together in 10 days, if they all work together, the work will be completed in :
View SolutionA and B together can do a piece of work in 4 days and A alone can do it in 6 days, B alone can do the same work in :
View SolutionA and B together can do a piece of work in 10 days. A alone can do it in 30 days. The time in which B alone can do it is
View SolutionA and B together can do a piece of work in 10 days. A alone can do it in 30 days. The time in which B alone can do it is:
View SolutionA can do a piece of work in 10 days, B can do it in 15 days working together they can finish the work in :
View Solution