A and B together complete a work in 20 days, B and C together complete same work in 30 days, C and A together complete the same work 24 days, In how many days A, B and C together can complete the same work?

A

8

B

16

C

12

D

15

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem, we need to find out how many days A, B, and C together can complete the work based on the information given about their combined work rates.

1. Identify the work rates of each pair:
- A and B together complete the work in 20 days.
- B and C together complete the work in 30 days.
- C and A together complete the work in 24 days.

2. Calculate the total work:
- The total work can be represented as the least common multiple (LCM) of the days taken by each pair.
- Calculate LCM of 20, 30, and 24.
- LCM(20, 30, 24) = 120 units.

3. Determine the work done by each pair in one day:
- A and B together: 120 units20 days=6 units/day
- B and C together: 120 units30 days=4 units/day
- C and A together: 120 units24 days=5 units/day

4. Set up equations for work rates:
- Let the work done by A in one day be a, by B be b, and by C be c.
- From the pairs, we can write:
- a+b=6 (1)
- b+c=4 (2)
- c+a=5 (3)

5. Solve the equations:
- From equation (1): b=6a
- Substitute b in equation (2):
(6a)+c=4c=46+ac=a2(4)
- Substitute c in equation (3):
(a2)+a=52a2=52a=7a=3.5
- Now substitute a back to find b and c:
- From (1): b=63.5=2.5
- From (4): c=3.52=1.5

6. Calculate the total work rate of A, B, and C together:
- Total work rate a+b+c=3.5+2.5+1.5=7.5 units/day

7. Determine the total time taken by A, B, and C together to complete the work:
- Time taken = Total WorkTotal Work Rate=120 units7.5 units/day=16 days

Final Answer:
A, B, and C together can complete the work in 16 days.

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • A and C together can complete a work in 120 days, C and E together can complete the same work in 80 days and A and E together can complete the same work in 160 days. In how many days A, C and E together can complete the same work?

    A12013 days
    B48013 days
    C24013 days
    D96013 days
  • C alone can complete a work in 20 days and D alone can complete the same workin 30 days. In how many days C and D together can complete the same work?

    A6 days
    B12 days
    C15 days
    D8 days
  • A alone can complete a work in 6 days and B alone can complete the same work in 8 days. In how many days both A and B together can complete the same work?

    A4813 days
    B3513 days
    C267 days
    D247 days